This is PermitBase’s published record for Aspen as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Aspen building permits
VerifiedAspen, Colorado — as published 2026-07-06.
Verified 2026-07-06 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction, Single-Family/Duplex/Townhouse)
VerifiedRequired for new construction of single-family, duplex, and townhouse structures in the City of Aspen. Reviewed under the 2021 IBC as locally amended (the IRC has not been adopted in Aspen) per the City's 'Building Permit Application Checklist for Singlefamily, Duplex, and Townhouse Projects (2021 IBC)'. Classified as a 'New Major Permit' under the City's queue-designator system since new construction changes floor area, height, net livable, or net leasable area.
Verified 2026-07-06 · Source
Requirements
- Reviewed under the 2021 IBC as amended by the City of Aspen; the IRC has NOT been adopted and is not applied to single-family/duplex/townhouse projects
- Ground snow load of 100 psf applies per the City's published Roof/Re-Roof Application Checklist design criteria; a Letter of Structural Integrity from a Structural Engineer is required if roof insulation does not meet this load rating
- Classified as a 'New Major Permit' (Queue Designator priority level 1, the lowest/slowest priority tier) since new construction changes floor area, height, net livable, or net leasable area
- All contractors must hold a current City of Aspen contractor license
- Asbestos test and clearance reports, or a State Asbestos Demolition Approval Notice, required per the Building Permit Application Checklist
- Special Inspection and Testing Agreement, Verification of Structural Integrity, and a Soils Report required for new construction per the Building Permit Application Checklist
- If the project meets or exceeds the City's 40% exterior-surface-area demolition threshold, a demolition allotment must be secured before the building permit can proceed (capped at 6 per calendar year, first-come first-served, plus 2 more for 35-year Aspen homeowners)
- Applications submitted via the City's Salesforce Permit Portal; Building Support reviews for completeness before issuing submittal fees due
Required documents
- RequiredBuilding Permit Application Checklist for Singlefamily, Duplex, and Townhouse Projects (2021 IBC)Lists required 8.5x11 documents (permit application packet, asbestos reports, energy code compliance, soils report, special inspection agreement, etc.) and required 24x36 plans (cover sheet, survey, site plan, floor plans, structural plans, etc.) by project type: New Construction, Addition, Alteration/Remodel, Alteration (Interior only), Demo (Complete), Repair
- RequiredPermit Application Signature PacketMust be filled out entirely or the submission will not be accepted
- RequiredAsbestos Test and Clearance Reports / State Asbestos Demolition Approval Notice
- RequiredSoils Report
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static valuation-percentage table is published as plain text on the Building Department's web pages; contact a Permit Coordinator (970-920-7090) or use the published Excel estimator for a specific figure |
| Construction Use Tax | Applies per Municipal Code; not itself published as a flat percentage on the Building Department pages reviewed for this file | — |
Residential Addition / Alteration-Remodel Permit
VerifiedRequired for additions and interior/exterior alterations to existing single-family, duplex, and townhouse structures in Aspen. Classified as either a 'New Minor Permit' (alterations not falling into Mini or Major categories) or 'New Major Permit' (if the addition changes floor area, height, net livable, or net leasable area) per the City's queue-designator system.
Verified 2026-07-06 · Source
Requirements
- Reviewed under the 2021 IBC as locally amended
- Classified as a New Minor Permit or New Major Permit depending on whether the addition/remodel changes floor area, height, net livable, or net leasable area (Major) versus other alterations (Minor)
- The Building Permit Application Checklist distinguishes required submittals by column: New Construction, Addition, Alteration/Remodel, and Alteration (Interior only) each have different required document sets
- Asbestos test required if affecting more than 160 sq ft of potentially asbestos-containing materials when altering interior walls, per the EPIC Permit Policy's interior-wall-change requirements (also applicable outside EPIC scope)
- A Licensed Structural Engineer's stamped plans or stamped letter of structural engagement required for any interior wall changes
- If alteration area exceeds 50% of the building footprint, Engineering Development requires a major grading & drainage report, stamped civil plan, current survey, and a soils report
Required documents
- RequiredBuilding Permit Application Checklist for Singlefamily, Duplex, and Townhouse Projects (2021 IBC)Addition and Alteration/Remodel columns specify the applicable document set
- OptionalStamped Structural Engineer Letter or PlansRequired if any interior walls are proposed for removal or alteration
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static valuation-percentage table published as plain text on Building Department web pages reviewed for this file |
Electrical Permit
VerifiedRequired for installation, alteration, or repair of electrical systems in Aspen. Governed by the 2023 National Electrical Code (NEC) as adopted, effective August 1, 2023. Typically submitted as an MEP sub-permit under a master building permit number, or as its own standalone permit for standalone electrical work (e.g. solar PV, panel upgrades).
Verified 2026-07-06 · Source
Requirements
- Governed by the 2023 NEC as adopted by the City of Aspen
- MEP sub-permits are submitted in Salesforce using the master permit number when part of a larger project, and require load forms/fixture calculators/HOA compliance forms per the City's Document & Resource Library
- Classified under the 'MEP (Mechanical/Electrical/Plumbing)' queue category for standalone trade permits
- Contractors must hold a current City of Aspen contractor license
- For homeowner-performed electrical work: the homeowner may personally perform wiring only if the property is not for sale/rent/lease and not generally open to the public, all work is inspected before and after concealment, and work complies with the NEC
Required documents
- RequiredElectrical Permit Application (Salesforce Permit Portal)
- OptionalHOA Compliance FormRequired for MEP sub-permits per the Building Document and Resource Library
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text; Colorado statute CRS 12-23-117(3) sets a state-mandated base electrical fee schedule that home-rule municipalities may surcharge, but this session could not confirm whether Aspen's ordinance follows that statutory base (unlike Vail, which explicitly does) — not assumed without direct confirmation |
Plumbing Permit
VerifiedRequired for installation, alteration, or repair of plumbing systems in Aspen. Governed by the 2021 International Plumbing Code (IPC) as adopted. Typically submitted as an MEP sub-permit under a master building permit number for larger projects, or as a standalone trade permit.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2021 IPC as adopted by the City of Aspen
- MEP sub-permits submitted in Salesforce using the master permit number, with required load forms/fixture calculators/HOA compliance forms
- Contractors must hold a current City of Aspen contractor license
- Changes to water fixture counts require an ECU (Excel) calculator, sanitation acknowledgement, and sanitation abandon agreement if a sewer disconnection or plumbing demo is involved, per the Building Document and Resource Library
Required documents
- RequiredPlumbing Permit Application (Salesforce Permit Portal)
- OptionalResidential ECU Calculator (Excel)Required for changes to water fixture counts
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plumbing Permit Fee | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text on Building Department web pages reviewed for this file |
Mechanical / HVAC Permit
VerifiedRequired for heating, cooling, ventilation, and gas appliance installation or replacement in Aspen. Governed by the 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC) as adopted.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2021 IMC and 2021 IFGC as adopted by the City of Aspen
- MEP sub-permits submitted in Salesforce using the master permit number for larger projects
- Contractors must hold a current City of Aspen contractor license
- Adding, moving, or changing fireplaces requires specification/installation sheets and a completed REMP spreadsheet fireplace tab, per the Building Document and Resource Library
Required documents
- RequiredMechanical Permit Application (Salesforce Permit Portal)
- OptionalREMP Spreadsheet (Fireplace Tab)Required for fireplace additions, relocations, or changes
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mechanical Permit Fee | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text on Building Department web pages reviewed for this file |
Roofing Permit (Re-Roof)
VerifiedRequired for all re-roofing projects in Aspen (patching less than one square, 10'x10', does not require a permit). Governed by the Roof Assembly sections of the currently adopted codes; roof work involving changes to height, slope, footprint, structural framing, or insulation requires a full building permit instead of a roofing permit. Ground snow load design criterion is 100 psf.
Verified 2026-07-06 · Source
Requirements
- All re-roofing projects require a Roofing Permit; roof work changing height, slope, footprint, structural framing, or cavity insulation requires a Building Permit instead
- Patching less than 1 square (10 ft x 10 ft) does not require any permit
- UL or ICC-ES report required for the listed Class A roof assembly specific to the roofing product and installation (per Ordinance 1, 2023)
- Ground snow load of 100 psf: if adding insulation above the roof deck and the building was not constructed to this snow load, a Letter of Structural Integrity from a Structural Engineer is required
- If insulation is present above the roof deck, required minimum values are R-40 above deck (Commercial) or R-49 above deck (Residential), or an alternate design approved by the Building Department for justified infeasibility
- Snowguards/stops required on roofs that shed onto neighboring properties or occupied areas (walkways, stairways, alleys, decks, pedestrian/vehicular exits, or areas above gas/electric utility meters)
- If heat tape is installed (new or existing) exceeding 1,000 watts, REMP fees apply, and a sub-electrical permit is required for any roof with heat tape
- If the address is on the City's Inventory of Historic Sites and Structures or within a Historic District, HPC Approval is required before the roofing permit
- Two photographs of existing conditions required (one showing the overall structure, one close-up of the existing roof)
- An asbestos test is NOT required if all materials to be removed are asphaltic/tar-impregnated/non-friable, removed by hand (no circular saws), and disposed of rather than recycled — all three conditions must be met
Required documents
- RequiredRoof/Re-Roof Application ChecklistUpdated 9/25/23; must be completed entirely including site plan, roof assembly drawing, and asbestos screening questions
- RequiredPermit Application Signatures PacketAll 6 pages, owner/contractor signatures where applicable
- RequiredConstruction Management Plan (CMP)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roofing / Re-Roof Permit Fee | Established in the currently adopted Building Department fee schedule; computed via the Roofing Fee Calculator (Excel), a separate tool from the general Building Permit Fee Estimator | Per the Roofing and Re-roofing Memorandum of Policy (Nov. 12, 2018); no static percentage table published as plain text |
Solar Photovoltaic (PV) System Permit
VerifiedRequired for installation of photovoltaic solar systems in Aspen. Governed by the 2023 NEC as adopted, plus the City's own Photovoltaic Solar System Installation Guidelines covering installer qualifications, submittal content, and inspection sequence.
Verified 2026-07-06 · Source
Requirements
- DC-side wiring must be installed by a Colorado-licensed electrical contractor, a NABCEP-certified contractor, a COSIA-certified contractor, or the homeowner
- AC-side wiring must be installed by a Colorado-licensed electrical contractor or the homeowner
- A homeowner performing their own wiring must personally do the work on a property not for sale/rent/lease and not generally open to the public, with all work inspected before concealment and again at completion, and full NEC compliance
- At time of application: one-line diagram with wire sizing, circuit voltage, voltage drop, grounding, and fusing; manufacturer specifications and installation documents for module, array, combiner box, inverter, mounting hardware, batteries (if applicable), and disconnect; drawings detailing panel azimuth/zenith alignment, equipment elevations, and site plan; proposed PV system kW capacity rating
- City of Aspen Electric Department Interconnect Agreement form must be filled out, signed, and approved prior to permit issuance
- 'Fully electric new projects qualify for expediting' per the Building Document and Resource Library, which may include solar/battery-paired all-electric projects
Required documents
- RequiredSolar/Electrical Permit Application (Salesforce Permit Portal)
- RequiredOne-Line DiagramWire sizing, circuit voltage, voltage drop, grounding, fusing
- RequiredCity of Aspen Electric Department Interconnect Agreement
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee (PV installation) | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text on Building Department web pages reviewed for this file |
Demolition Permit
VerifiedRequired for demolition of any structure not being replaced with another structure, and separately gates any project meeting the City's residential demolition threshold (40% or more of existing exterior wall/roof surface area removed) before a building permit for redevelopment can be issued. Aspen caps qualifying residential demolition allotments at 6 per calendar year, first-come first-served, plus 2 additional allotments per year reserved for 35-year Aspen homeowners.
Verified 2026-07-06 · Source
Requirements
- 'Demolition' is defined as razing, disassembling, tearing down, or destroying 40% or more of a structure, measured by existing (pre-demolition) exterior wall (above finished grade) and roof surface area, excluding fenestration, compared against the same area proposed for removal
- A project meeting or exceeding this 40% threshold can only proceed to a building permit if a demolition allotment is available; allotments are capped at 6 per calendar year and awarded first-come, first-served, with 2 additional allotments per year for applicants who have owned their Aspen home for at least 35 years
- Approved demolition allotments are valid for 3 years, within which the project must submit for both the demolition and the building permit
- Redevelopment following a qualifying demolition must meet residential redevelopment standards: minimum 35% by weight non-hazardous waste diversion from landfill, carbon-usage reporting for the building process/materials and projected future energy use, and design/construction readiness for future 100% electric conversion plus on-site PV/battery storage accommodation
- Projects over 2,000 sq ft affecting square footage and/or triggering demolition additionally require a Construction Waste Diversion Plan
- Contact the Building Department directly for restrictions associated with this permit type before selecting it, per the City's Permit Types & Triggers document
- Only applications deemed 'complete' under the Land Use Code enter the queue for a demolition allotment
Required documents
- RequiredDemolition Permit Application (Salesforce Permit Portal)
- RequiredDemolition Percentage CalculationAssemblies to be removed divided by total exterior surface area (excluding fenestration); example calculations available in the Building Document and Resource Library under Zoning Requirement Examples
- OptionalConstruction Waste Diversion PlanRequired for projects over 2,000 sq ft affecting square footage and/or triggering demolition
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit Fee | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text; note that per the City's Permit Types & Triggers document, Demolition/IFFR/Repair/Change Orders/Temporary Structure permits are excluded from standard submittal fees |
Fence Permit
VerifiedRequired for construction of a fence, constructed barrier, or berm in Aspen. Governed by Aspen Municipal Code Sec. 26.575.050 (allowed materials) and Sec. 26.575.e.5.q (height limits), plus the 2024 Colorado Wildfire Resiliency Code's noncombustible/ignition-resistant material requirements near structures.
Verified 2026-07-06 · Source
Requirements
- Allowed fence materials per Sec. 26.575.050: metal, masonry, stone, and wood
- Wildfire Resiliency Code requirement: fences within 8 feet of a structure must be constructed of noncombustible or ignition-resistant materials; hedges within 5 feet of a structure must use ignition-resistant vegetation
- Maximum fence/hedge height per Sec. 26.575.e.5.q, measured from finished grade: up to 42 inches generally, or up to 6 feet in areas entirely recessed behind the vertical plane of the building facade closest to the street (applies on all street-facing facades of a parcel)
- If the property is historically designated, a signed Certificate of No Negative Effect is required (contact Historic Preservation staff)
- Signed Homeowner Association Compliance form required
- Improvement Survey with an original wet stamp/signature showing property lines, all easements/rights-of-way, all existing structures/improvements/fences, and location/trunk diameter/species of all trees is required; if a tree's critical root zone will be impacted, Parks Department approval and a separate permit are required
- Elevation drawings showing design, dimensions, and materials of the proposed fence required
- Reach out to Engineering if a fence is proposed within an easement or right-of-way
Required documents
- RequiredFence Permit Application ChecklistLast Updated 04/2026
- RequiredImprovement Survey (wet-stamped)
- RequiredElevation Drawings
- RequiredHomeowner Association Compliance Form
- OptionalCertificate of No Negative EffectRequired only if the property is historically designated
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fence Permit Fee | Computed via the City's Building Permit Fee Estimator (Excel) referencing the current Municipal Code Fee Ordinance (Title 2) | No static percentage-based fee table published as plain text on Building Department web pages reviewed for this file |
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Aspen building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.