This is PermitBase’s published record for Pueblo as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Pueblo building permits
Pueblo, Colorado — as published 2026-07-20.
Reviewed 2026-07-03 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
Required for construction of new single-family homes, duplexes, and other one- and two-family dwellings within the City of Pueblo. Reviewed against the 2021 IRC as amended by Pueblo City Code Title IV, Chapter 6, plus the 2021 IECC (unmodified) and Colorado Model Electric and Solar Ready Code effective 6/30/2026. Issued by the Southern Colorado Building Department (SoCoBD), the joint City of Pueblo/Town of Boone building authority.
Reviewed 2026-07-03 · Source
Requirements
- Building permit required for new single-family and two-family dwelling construction within City of Pueblo limits
- Plans must comply with the 2021 IRC as amended by Pueblo City Code Title IV, Chapter 6, and the 2021 IECC (unmodified) plus the Colorado Model Electric and Solar Ready Code for plans/permits submitted on or after 8/1/2026
- Design must account for local Design Criteria: 106 mph residential wind load, ground snow load per elevation (20-59 psf table), 26-inch minimum frost/foundation depth, Seismic Zone B
- New 1- and 2-family residence permits are subject to an additional 10% plan review fee on top of the base valuation-based permit fee
- Contractor Permit Application (for licensed contractors) or Homeowner Permit Application (owner-occupied principal residence only, verified per Pueblo City Code Sec. 4-1-9) required
- Submitted via the SoCoBD E-Gov Dashboard (online) or emailed to permits@socobd.com / faxed to 719-543-0062
Required documents
- RequiredContractor Permit ApplicationFillable PDF; submitted via SoCoBD E-Gov Dashboard, email, or fax
- OptionalHomeowner Permit ApplicationFillable PDF for owner-occupied principal-residence permits only
- RequiredResidential Plan Submittal ChecklistSoCoBD checklist for residential plan submittals
- RequiredConstruction DrawingsSite plan, foundation plan, floor plan, framing, elevations, and structural details per 2021 IRC and local Design Criteria (wind, snow, frost depth, seismic zone)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Residence — All Finished Living Area | $73.93 per square foot (valuation basis, Table A) | SoCoBD Fee Table (PDF) |
| New Residence — Basement, Unfinished | $12.50 per square foot | SoCoBD Fee Table (PDF) |
| New Residence — Finished Garden Level or Basement Level | $32.00 per square foot | SoCoBD Fee Table (PDF) |
| Building Permit Fee — total valuation $2,001 to $25,000 | $66.15 for the first $2,000 plus $9.92 for each additional $1,000 or fraction thereof | SoCoBD Fee Table, Table B |
| Building Permit Fee — total valuation $100,001 to $500,000 | $721.98 for the first $100,000 plus $3.86 for each additional $1,000 or fraction thereof | SoCoBD Fee Table, Table B |
| Additional Plan Review Fee (new 1- and 2-family residences) | 10% of the base permit fee | SoCoBD Fee Table (PDF) |
Residential Addition / Remodel / Alteration Permit
Required for additions, remodels, and structural alterations to existing one- and two-family dwellings in the City of Pueblo, including garages, decks, patios, and interior remodels affecting structural, mechanical, electrical, or plumbing systems. Reviewed against the 2021 IRC as amended locally.
Reviewed 2026-07-03 · Source
Requirements
- Building permit required for additions, remodels, and alterations affecting structure, or mechanical/electrical/plumbing systems, including like-for-like change-outs
- Garages and carports require a permit regardless of size
- Sheds/storage buildings: residential projects larger than 200 sq ft require a permit (commercial projects larger than 120 sq ft); zoning/planning approval may still be required regardless of size
- Decks: a permit is required for any deck attached to a building or 30 inches or more above grade; decks 200 sq ft or less, not more than 30 inches above grade, unattached, and not serving a required exit door are exempt per IRC Section R105.2
- Interior remodels (adding a bathroom, finishing a basement, changing floorplan, etc.) require a permit
- Design must meet local Design Criteria: 106 mph residential wind load, snow load per elevation, 26-inch frost depth
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax
- RequiredResidential Plan Submittal ChecklistSoCoBD checklist for residential plan submittals
- OptionalBuilding Guide — Residential Addition / Detached Garage / Uncovered Decks / Carports & Patio Covers / Enclosing a Patio / Finishing a BasementColorado Chapter ICC building guides published by SoCoBD for common project types
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Detached Garage | $24.00 per square foot | SoCoBD Fee Table, Table A |
| Attached Garage | $22.00 per square foot | SoCoBD Fee Table, Table A |
| Carports — open on two or more sides | $15.00 per square foot | SoCoBD Fee Table, Table A |
| Open Patios or Porches with Roof | $11.00 per square foot | SoCoBD Fee Table, Table A |
| Enclosed Patio | $25.00 per square foot | SoCoBD Fee Table, Table A |
| Deck (uncovered) | $10.00 per square foot | SoCoBD Fee Table, Table A |
| Deck with Roof | $20.00 per square foot | SoCoBD Fee Table, Table A |
| Building Permit Fee — total valuation up to $500 | $33.08 | SoCoBD Fee Table, Table B |
Electrical Permit
Required for electrical installation, alteration, or repair work in the City of Pueblo, governed by the 2023 National Electrical Code (NEC) as amended by Pueblo City Code Title IV, Chapter 3.
Reviewed 2026-07-03 · Source
Requirements
- Electrical permit required for new/upgraded service, new wiring or upgrades, added circuits/lighting/receptacles, and solar installation or upgrade
- Governed by the 2023 NEC as amended by Pueblo City Code Title IV, Chapter 3
- Reconnect (utility-required safety inspection before releasing service) does not itself require a work permit, but failing the safety inspection may require a licensed contractor to pull permits to fix issues
- Meter height must be between 4 feet and 5.5 feet to the bottom of the meter can per City ordinance
- Apply via SoCoBD E-Gov Dashboard, email, or fax
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Upgrade/Replace Service (Residential Electrical Only Permit) | $55.13 | SoCoBD Fee Table, Table C |
| Solar PV Systems (Residential Electrical Only Permit) | $319.73 | SoCoBD Fee Table, Table C |
| A/C Hook Up (Residential Electrical Only Permit) | $44.10 | SoCoBD Fee Table, Table C |
Plumbing Permit
Required for plumbing installation, alteration, or repair work in the City of Pueblo, governed by the 2021 International Plumbing Code (IPC) as amended by Pueblo City Code Title IV, Chapter 4. Note: Pueblo uses the IPC, not the Uniform Plumbing Code.
Reviewed 2026-07-03 · Source
Requirements
- Plumbing permit required for water heater installation/replacement, water/sewer line replacement or repair, re-plumbing, and lawn sprinkler system installation
- Governed by the 2021 IPC as amended by Pueblo City Code Title IV, Chapter 4
- Water service lines must be installed at 48 inches deep (meets the code requirement of 1 ft below the local frost line in the majority of areas)
- Sewer and water penetrations through concrete walls require sleeves, tightly caulked/sealed
- Homeowner (owner-occupant) permits available only for the applicant's own principal residence; rentals require a licensed contractor per City ordinance Sec. 4-1-9
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sewer Connection (Residential Plumbing Only Permit) | $55.13 | SoCoBD Fee Table, Table C |
| Water Connection (Residential Plumbing Only Permit) | $44.10 | SoCoBD Fee Table, Table C |
| Lawn Sprinkler System (Residential Plumbing Only Permit) | $60.64 | SoCoBD Fee Table, Table C |
Mechanical / HVAC Permit
Required for heating, ventilation, air conditioning, and gas-fired appliance installations in the City of Pueblo, governed by the 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC).
Reviewed 2026-07-03 · Source
Requirements
- Mechanical and/or Electrical permit required to install or replace a furnace, including adding air conditioning to an existing furnace
- Plumbing and/or Electrical permit required to install/replace a water heater
- Gas piping repairs/replacement may require a permit; a pressure test (minimum 10 lbs for 15 minutes, or 60 lbs for 24 hours on welded pipe) may be required before utility turn-on
- Carbon monoxide detectors are required whenever mechanical/gas work is performed inside the home
- Reconnect/gas air-test inspections (utility-required before releasing service) are safety inspections only, not a work permit, but failed inspections may require a licensed contractor to pull permits for repairs
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Water Heater Replacement (Residential Mechanical Only Permit) | $44.10 | SoCoBD Fee Table, Table C |
| Furnace Replacement (Residential Mechanical Only Permit) | $71.66 | SoCoBD Fee Table, Table C |
| Furnace/AC Replacement (Residential Mechanical Only Permit) | $88.20 | SoCoBD Fee Table, Table C |
| Gas Air Test (Residential Mechanical Only Permit) | $44.10 | SoCoBD Fee Table, Table C |
Re-Roofing Permit
Required for residential and commercial re-roofing in the City of Pueblo. Reviewed against the 2021 IRC/IBC roofing provisions (Chapter 9 / Section 1507) with SoCoBD local interpretations effective July 1, 2023.
Reviewed 2026-07-03 · Source
Requirements
- A building permit is required for re-roofing; contact SoCoBD or the Authority Having Jurisdiction for area-specific requirements
- Homeowners may perform their own re-roof work
- Asphalt shingles not permitted on roof pitch less than 2:12; two layers of underlayment required for pitch 2:12 to 4:12; one layer required for 4:12 and over
- Drip edge required at eave and rake edges of shingle roofs (IRC R905.2.8.5 / IBC 1507.2.8.3)
- Ice barrier is NOT required per Section R905.1.2 in this jurisdiction (local application)
- Roof decking is considered 'solidly sheathed' only if the joint width between wood structural panels does not exceed 1/4 inch (SoCoBD interpretation, effective 7/1/2023); wider gaps require re-decking or a minimum 1/4-inch CDX/OSB overlay with its own permit and final inspection
- Roofing contractors may only replace vent cap, storm collar, and jack on a B-Vent; any repair/replacement of the B-Vent connection or the vent itself requires a licensed HVAC contractor and permit
- A Remove-and-Reset solar permit (obtained by a licensed contractor) is required before detaching solar arrays for re-roofing
- Typical asphalt and Direct-to-Deck metal shingle residential roofs do not require a mid-roof inspection; tile roofs require a roof dry-in inspection after underlayment/battens/sub-flashing are installed and before any tile is placed
- Re-roof permits are not required to be posted at the property
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax
- OptionalReroofing Guidelines (Colorado Chapter ICC Building Guide)SoCoBD-published summary of 2021 IRC/IBC re-roof requirements and local interpretations
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roofing Permit — 10 squares, Shingles | $76.07 | SoCoBD Roofing Permit Fees (2016) schedule |
| Roofing Permit — 30 squares, Shingles | $155.67 | SoCoBD Roofing Permit Fees (2016) schedule |
| Roofing Permit — 30 squares, Modified | $135.59 | SoCoBD Roofing Permit Fees (2016) schedule |
| Roofing Permit — 30 squares, Rolled | $76.07 | SoCoBD Roofing Permit Fees (2016) schedule |
| Roofing Permit — 60 squares, Shingles | $195.11 | SoCoBD Roofing Permit Fees (2016) schedule; full square-by-square table (10-60 squares) published for Shingles/Modified/Rolled roofing |
Solar Photovoltaic (PV) Permit
VerifiedRequired for installation of rooftop or ground-mount solar photovoltaic systems within the City of Pueblo. Residential projects require routing approval and plan review prior to permit issuance (effective 1/2/2024); commercial and utility-scale projects follow separate submittal tracks.
Verified 2026-07-20 · Source
Requirements
- Solar project routing must be created through the applicant's SoCoBD E-Gov Dashboard account when logged in
- Commercial installations under 2 MW use the normal commercial plan submittal process
- Utility-scale projects over 2 MW require a pre-submittal meeting before submitting via the commercial plan review process
- Residential projects require routing approval, and plans are reviewed prior to permit issuance (effective 1/2/2024)
- A Remove-and-Reset permit (by a licensed contractor) is required before detaching an existing solar array for re-roofing work
Required documents
- RequiredSolar PV Basic GuideSoCoBD guide for building a required plan set of jobsite information
- OptionalExample Plan SetSample solar PV plan set; applicants should use the manufacturer's toolkit to calculate values
- OptionalRooftop Access GuideSoCoBD guide covering rooftop access requirements for solar installers
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar PV Systems (Residential Electrical Only Permit) | $319.73 | SoCoBD Fee Table, Table C. RE-VERIFIED 2026-07-20: socobd.com is live again (the 2026-07-13 outage noted elsewhere in this file has resolved); Show full citationHideSoCoBD Fee Table, Table C. RE-VERIFIED 2026-07-20: socobd.com is live again (the 2026-07-13 outage noted elsewhere in this file has resolved); the Fee Table PDF was re-fetched directly and re-parsed. The PDF's raw text stream is column-shifted (a known layout artifact of this document), but reconstructing the Table C row order against the labeled a./b./c. sub-items confirms $319.73 is the Solar PV Systems figure (Upgrade/Replace Service = $55.13, Solar PV Systems = $319.73, A/C Hook Up = $44.10), consistent with this file's original reading. SoCoBD's homepage now states a NEW fee schedule takes effect for plans/permits submitted on or after August 1, 2026 ('Updated Documents will be posted soon') — this $319.73 figure is the CURRENT rate through 7/31/2026 but should be reconfirmed after that date. |
Fence and Retaining Wall Permit
Fences and retaining walls in the City of Pueblo are exempt from a building permit below specific height/design thresholds per IRC/IBC Section 105.2; taller or load-bearing structures require a permit and, for retaining walls, may require engineered plans.
Reviewed 2026-07-03 · Source
Requirements
- Fences not over 7 feet high do not require a building permit (per IRC/IBC Section 105.2); fences over 7 feet require a permit and engineered plans
- Zoning rules may still apply to fences of any height, especially fences extending past the front of a building — check with the appropriate department before starting
- Retaining walls not over 4 feet in height (measured from the bottom of the footing to the top of the wall) are exempt from a building permit, unless the wall supports a surcharge (or, per the IBC exemption, unless it impounds Class I, II, or IIIA liquids)
- Retaining walls exceeding these thresholds, or any wall supporting a surcharge regardless of height, require a building permit and are commonly engineered
Required documents
- RequiredContractor or Homeowner Permit ApplicationRequired only for fences over 7 feet or regulated retaining walls; submitted via SoCoBD E-Gov Dashboard, email, or fax
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — total valuation up to $500 (fences/walls requiring a permit) | $33.08 | SoCoBD Fee Table, Table B (general valuation-based schedule; no fence/retaining-wall-specific fixed fee was published) |
EV Charging Station Permit (Electrical Permit)
VerifiedRequired for installation of a Level 2 (or higher) electric vehicle charging station/EVSE within the City of Pueblo, permitted the same way as any other electrical work under the 2023 NEC as amended by Pueblo City Code Title IV, Chapter 3, and issued by the Southern Colorado Building Department (SoCoBD). Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act) designates the City of Pueblo a 'covered municipality' (population over 10,000) and Pueblo County a 'covered county' (population over 20,000), requiring both to have adopted, by 12/31/2025, either the Colorado Energy Office's EV Charger Permitting Model Code, an equivalent locally-adopted objective standard, or a resolution affirming continued use of their existing permitting review process — this file could not independently confirm which of the three compliance options SoCoBD/the City selected.
Verified 2026-07-20 · Source
Requirements
- Electrical permit required for the new/upgraded circuit and EVSE connection, the same as any other electrical work per Pueblo City Code Title IV, Chapter 3 (2023 NEC as amended)
- Installation must comply with NEC Article 625 (Electric Vehicle Power Transfer System); GFCI protection applies per NEC 625 where the EVSE is cord-and-plug connected
- Apply via the SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax, the same intake channels used for the file's general electrical-permit entry
- If the charger install requires a panel/service upgrade, that scope is included in the same electrical permit application
- No dedicated EV/EVSE fee line item exists in SoCoBD's Fee Table Table C (Residential Electrical Only Permits) -- confirmed by reading the full table, which lists exactly three fixed-fee residential electrical categories (Upgrade/Replace Service, Solar PV Systems, A/C Hook Up) and no others; a standalone EV charger circuit addition with no service upgrade does not match any of the three
- Because a plain EV charger circuit addition is not one of Table C's fixed-fee categories, it falls back to SoCoBD's general valuation-based permit fee (Table B), applied to the contractor's declared job value for the electrical work -- the same mechanism Table C's own instructions specify for any permit type not itemized as a fixed fee
- If the installation instead requires a service/panel upgrade to support the charger, it is billed under Table C's fixed 'Upgrade/Replace Service' fee ($55.13) instead of the valuation-based Table B calculation
Required documents
- RequiredContractor or Homeowner Permit ApplicationSubmitted via SoCoBD E-Gov Dashboard, email (permits@socobd.com), or fax — same application used for the file's general electrical-permit entry
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| General valuation-based permit fee (Table B) — applies to a standalone EV charger circuit addition (not a Table C fixed-fee category) | Up to $500 valuation: $33.08 flat. $501-$2,000: $33.08 for the first $500 plus $2.21 per additional $100 or fraction thereof. $2,001-$25,000: $66.15 for the first $2,000 plus $9.92 per additional $1,000 or fraction thereof. | SoCoBD Fee Table (PDF), Table B — the full table was read directly; Show full citationHideSoCoBD Fee Table (PDF), Table B — the full table was read directly; Table C (Residential Electrical Only Permits, fixed-fee) lists only three categories (Upgrade/Replace Service $55.13, Solar PV Systems $319.73, A/C Hook Up $44.10) and none covers a plain EV charger/EVSE circuit addition, so it defaults to Table B's declared-valuation sliding scale per the fee table's own stated logic. A typical Level 2 EVSE circuit install (materials + labor in the roughly $1,500-$3,000 range) would fall in the $501-$2,000 or $2,001-$25,000 bracket depending on declared job value. Verified directly against the current SoCoBD Fee Table PDF as of 2026-07-20. |
| SoCoBD Residential Electrical Only Permit (Table C) — Upgrade/Replace Service (if the charger install requires a service/panel upgrade) | $55.13 flat | SoCoBD Fee Table (PDF), Table C, Residential Electrical Only Permits — confirmed as one of only three fixed-fee residential electrical categories, applicable if the EVSE installation includes a service or panel upgrade rather than just a new branch circuit |
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-03.
Fee schedules
Checklists & handouts
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pueblo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.