Eaton building permits
VerifiedEaton, Colorado — as published 2026-07-07.
Verified 2026-07-06 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction / Addition / Remodel / Repair / Basement Finish)
VerifiedRequired for new single-family/duplex/multi-family dwellings, garages, additions, remodels, repairs, and basement finishes in Eaton, using the Town's own 'Residential Building Permit' application form. Reviewed under the 2024 IBC/IRC as locally amended by Ordinance No. 664; inspections and plan review performed under contract by SAFEbuilt, with permits issued by the Town Clerk's Office.
Verified 2026-07-06 · Source
Requirements
- Completed and signed Residential Building Permit application (PURPOSE OF PERMIT covers New Building, Addition, Remodel, Repair, and Basement Finish on a single form)
- Digital submittal (flash drive, emailed, or uploaded via CommunityCore)
- Building plans: wall sections, floor plan, framing plan, elevations, door and window schedule, cabinet layout
- Engineered foundation drawings
- Plot plan showing all distances to lot lines and structures
- Site grading plan stamped by a civil engineer
- Mechanical, plumbing, and electrical drawings
- Energy code compliance documents, including Manual J, S, D and supporting documents
- Contractors must register/be verified in CommunityCore and pay the Town's $50/year Contractor Fee before applying online
- An 'Energy Compliance Certificate' (per the 2024 IECC) is required, along with leak-test reports for ductwork and building envelope, available to the inspector at final inspection and required before Certificate of Occupancy
Required documents
- RequiredResidential Building Permit ApplicationTown of Eaton form; covers new construction, additions, remodels, repairs, and basement finishes
- RequiredConstruction Drawings / Building PlansWall sections, floor plan, framing plan, elevations, door/window schedule, cabinet layout, per the application form's document checklist
- RequiredEngineered Foundation Drawings
- RequiredPlot PlanDistances to lot lines and structures
- RequiredEnergy Compliance Certificate (2024 IECC)Plus ductwork and building-envelope leak-test reports
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Construction Building Permit Fee | Per Appendix L, 2018 IRC valuation table (as referenced in the Town's current Fee Schedule) | Town of Eaton Fee Schedule, Building Department Fees, p.2; valuations based on provided labor/material costs or the current ICC BVD table, whichever is more accurate |
| Plan Review Fee | 65% of Permit Fee | — |
| Residential Admin Fee | $50.00 | — |
| Residential Repeat Master Plan Review Fee | $200.00 | — |
| Contractor Fee (annual, per contractor) | $50.00 per year | Plumbers and electricians are exempt from this fee |
| Re-Inspection Fee | $85.00 per inspection | — |
| Credit/Debit Card Payment Surcharge | 3% of permit total | — |
Electrical Permit
VerifiedRequired for new electrical service, panel work, or living-space electrical wiring in Eaton. Governed by the 2023 NEC as adopted by Ordinance No. 664. Fees are structured differently for new residential living space (area-based) versus all other electrical work (valuation-based).
Verified 2026-07-06 · Source
Requirements
- Electrical Permit application (via the Residential Building Permit / Commercial Permit / Counter Building Permit forms, which each include an Electrical Contractor section) submitted through CommunityCore
- Licensed electrical contractor information, or the Town's contractor registration for homeowner-performed work
- Electrical plan review required for all electrical permits (residential and non-residential)
Required documents
- RequiredElectrical Permit Application (CommunityCore)
- OptionalElectrical Diagram/Panel ScheduleFor new service or panel work
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Creating New Living Space — 0 to 1,000 SF | $200.00 | Town of Eaton Fee Schedule, Electrical Permit Fees, p.2 |
| Residential Creating New Living Space — 1,001 to 1,500 SF | $250.00 | — |
| Residential Creating New Living Space — 1,501 to 2,000 SF | $300.00 | — |
| Residential Creating New Living Space — over 2,000 SF | $300.00 plus $15.00 for each additional 100 SF | — |
| All Other Electrical Work (by valuation) — $1.00 to $2,000.00 | $100.00 | — |
| All Other Electrical Work (by valuation) — over $2,000.00 | $200.00 plus $10.00 for each additional $1,000.00 of value | — |
| Temporary Construction Meter | $85.00 | — |
| Permanent Meter Inspection | $85.00 | — |
| Electrical Plan Review (Residential and Non-Residential) | 65% of Electrical Permit Fee | — |
| Electrical Re-Inspection Fee | $85.00 | — |
Plumbing Permit (Water Line/Sewer Repair, Backflow, Water Heater)
VerifiedRequired for water/sewer line repair, backflow devices, and hot water heater installation/replacement in Eaton. Governed by the 2024 IPC as adopted by Ordinance No. 664. Most standalone residential plumbing work is billed via the Town's flat 'Over the Counter One-Stop' fee schedule rather than a dedicated plumbing valuation table.
Verified 2026-07-06 · Source
Requirements
- Counter Building Permit (Over-the-Counter application) covers Water Line repair/replacement, Backflow, and Hot Water Heater work on a single form
- Licensed plumbing contractor information, or Town contractor registration for homeowner-performed work
- Backflow Permit (commercial or multi-unit) requires annual renewal
Required documents
- RequiredCounter Building Permit Application (Over-the-Counter)Covers Water Line and Hot Water Heater work
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Hot Water Heater (Over-the-Counter One-Stop) | $125.00 | Town of Eaton Fee Schedule, Over the Counter One-Stop Fees, p.2 |
| Water and Sewer Repair Inspection (Over-the-Counter permit) | $50.00 | — |
| Back Flow Permit Fee (Commercial or Multi Units) | $75.00 yearly | — |
| Sprinkler System Permit — Potable Water Only | $15.00 | — |
| Water Tap — 5/8" x 3/4" | $17,159.00 | Scales up to $438,437.00 for a 6-inch tap; Town of Eaton Fee Schedule, Water Taps, p.5 |
| Sewer Tap — 3/4" | $3,000.00 | Scales up to $101,914.00 for a 6-inch tap |
Mechanical / HVAC Permit (Furnace, Air Conditioning, Gas Line, Gas Fireplace)
VerifiedRequired for furnace replacement, air conditioning installation, gas line, and gas fireplace work in Eaton. Governed by the 2024 IMC/IFGC as adopted by Ordinance No. 664. Billed via the Town's flat 'Over the Counter One-Stop' fee schedule.
Verified 2026-07-06 · Source
Requirements
- Counter Building Permit (Over-the-Counter application) covers Furnace/AC, Gas Fireplace, and Gas Line work, with fields for BTU rating and AC tonnage
- Licensed mechanical contractor information, or Town contractor registration for homeowner-performed work
- Gas Meter/Gas Test permit required for new gas line work
Required documents
- RequiredCounter Building Permit Application (Over-the-Counter)Covers Furnace/AC, Gas Fireplace, Gas Line
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Air Conditioning (Over-the-Counter One-Stop) | $125.00 | Town of Eaton Fee Schedule, Over the Counter One-Stop Fees, p.2 |
| Furnace Replacement (Over-the-Counter One-Stop) | $125.00 | — |
| Gas Meter/Gas Test (Over-the-Counter One-Stop) | $125.00 | — |
Roofing Permit (Re-Roof)
VerifiedRequired for re-roofing work in Eaton, governed by Chapter 9 (Sec. R901-R908) of the 2024 IRC as adopted, plus the Town's own dedicated Roofing Regulations handout and a locally amended Class-4 impact-resistant shingle requirement.
Verified 2026-07-06 · Source
Requirements
- Building Permit shall be posted on the house prior to starting work
- Roofing Contractor must carry $100,000 combined single limit liability insurance; certificate of insurance (with limits, policy number, insurer name, effective/expiration dates) submitted at time of application, with an endorsement requiring 10-day advance written notice to the Town before cancellation
- Re-roofing performed per Chapter 9 of the 2024 IRC: ice barrier required from the lowest roof edges to at least 24 inches inside the exterior wall line; all existing roofing materials must be torn off down to the deck (one-layer overlay rarely permitted); materials must meet 2024 IRC fire classification and wind-resistance standards; drip edge required at eaves and gables
- Asphalt shingles must be Class 4 impact resistant, tested to UL2218, installed per manufacturer instructions — a local amendment to IRC R905.2.4
- Replace damaged roof vents, b-vents, and roof jacks; add roof vents as needed to comply with 2024 IRC Sec. 806 (Roof Ventilation)
- Secured ladder required on-site for all inspections (Code Reference R109.3)
- Repair or replacement of less than 1 square (100 sq ft) of shingles does NOT require a building permit, per both the Roofing Regulations handout and Ordinance No. 664's IRC Sec. 105.2/R105.2 exemption amendment
Required documents
- RequiredCounter Building Permit Application (Over-the-Counter)Re-Roof field captures number of squares
- RequiredCertificate of Insurance$100,000 combined single limit, naming the Town of Eaton, with 10-day cancellation notice endorsement
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Re-Roof (Over-the-Counter One-Stop) | $125.00 | Town of Eaton Fee Schedule, Over the Counter One-Stop Fees, p.2 |
Residential/Commercial Solar Permit
VerifiedRequired for new solar panel installation in Eaton, whether residential or commercial. Billed on the Town's valuation-based electrical schedule with distinct flat fees by system size, and reviewed under the Colorado Model Electric and Solar Ready Code and 2023 NEC Articles 690/705 as locally adopted.
Verified 2026-07-06 · Source
Requirements
- Layout plan showing panel placement on all structures, indicating path of travel and minimum pathway widths
- Engineered structural plan or letter (engineer's stamp) approving design, location, and installation of panels on the roof, stating roof load and wind load
- Detailed framing plans for any additional framing required by the engineer; a final engineer's letter of inspection may be required prior to final approval
- Equipment details/spec sheets for all equipment to be installed; all equipment must be listed and labeled per UL 1703
- Electrical one-line diagram showing all disconnecting means, wiring, wire sizes, piping/routes/sizes, conduit routes, grounding details, panel schedules, and connection details in accordance with NEC Article 690 and 705
- Labeling examples and locations per NEC 690
- Ground-mounted systems require a site plan with setbacks and engineered foundation documents
- Zoning approval required; Fire approval required for commercial systems (check with local fire district); HOA approval may also be required
Required documents
- RequiredSolar Permit Application (via CommunityCore)
- RequiredEngineered Structural Plan/LetterStamped, stating roof load and wind load
- RequiredElectrical One-Line DiagramNEC Article 690/705 compliant
- RequiredEquipment Spec SheetsUL 1703-listed and labeled equipment
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Solar Installation | $500.00 | Town of Eaton Fee Schedule, Electrical Permit Fees, p.2 |
| Commercial Solar Installation < 2MW | $1,000.00 | — |
| Commercial Solar Installation > 2MW | $1,000.00 plus non-residential electrical plan review | — |
EV Charger / EVSE Permit (Billed as General Electrical Work)
VerifiedRequired for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Eaton. The Town has no dedicated EV-charger fee line item, application form, or ordinance distinct from the Colorado HB24-1173 EV-charger-permitting statute's requirements — Eaton's own population (approx. 6,000 per Census QuickFacts) is below the 10,000-population threshold that makes a municipality a 'covered municipality' under HB24-1173 (Electric Vehicle Charging System Permits Act, effective Aug. 7, 2024), so the Town is not required to adopt the Colorado Energy Office's model EV-charger permitting code or a dedicated objective-standards ordinance. An EV charger circuit is billed under the Town's general 'All Other Electrical Work (by valuation)' fee tier on the same Fee Schedule used for other electrical work not tied to new living space, and reviewed under the 2023 NEC Article 625 (Electric Vehicle Power Transfer System) as adopted by Ordinance No. 664.
Verified 2026-07-20 · Source
Requirements
- Electrical Permit application (via the Residential Building Permit / Commercial Permit / Counter Building Permit forms, which each include an Electrical Contractor section) submitted through CommunityCore
- Licensed electrical contractor information, or the Town's contractor registration for homeowner-performed work
- Electrical plan review required for all electrical permits (residential and non-residential)
- No dedicated EV-charger checklist, model-code adoption, or 3-business-day HB24-1173 notification commitment was found published by the Town — Eaton is below the 10,000-population 'covered municipality' threshold that triggers HB24-1173's requirements
Required documents
- RequiredElectrical Permit Application (CommunityCore)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| All Other Electrical Work (by valuation) — $1.00 to $2,000.00 | $100.00 | Town of Eaton Fee Schedule, Electrical Permit Fees, p.2 — the general valuation-based tier that governs an EV charger/EVSE circuit, since it is not new living space and no dedicated EV line item exists |
| All Other Electrical Work (by valuation) — over $2,000.00 | $200.00 plus $10.00 for each additional $1,000.00 of value | — |
| Electrical Plan Review (Residential and Non-Residential) | 65% of Electrical Permit Fee | — |
| Electrical Re-Inspection Fee | $85.00 | — |
Demolition Permit
VerifiedRequired for demolition of a structure in Eaton, billed as a flat fee under the Town's Over-the-Counter One-Stop schedule.
Verified 2026-07-06 · Source
Requirements
- Counter Building Permit (Over-the-Counter application) with description of work and intended use
- Compliance with all Town rules/restrictions for construction/demolition activity
Required documents
- RequiredCounter Building Permit Application (Over-the-Counter)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition (Over-the-Counter One-Stop) | $125.00 | Town of Eaton Fee Schedule, Over the Counter One-Stop Fees, p.2 |
Fence Permit
VerifiedRequired for fences exceeding 6 feet in height in Eaton (fences 6 feet or under are exempt from permit per a local amendment to IBC/IRC Sec. 105.2). No dedicated fence project page, standalone fee line item, or review timeline beyond the general exemption threshold and the general building valuation fee table was found published.
Verified 2026-07-06 · Source
Requirements
- Fences not over 6 feet high are exempt from permit, per Ordinance No. 664's amendment to IBC/IRC Sec. 105.2 Exception #2
- Swimming pool barriers of any height are explicitly NOT exempt from permit, per the same amendment
- Fences over 6 feet require a permit; no dedicated fence application form or fee line item beyond the general building valuation table was found published
Required documents
- RequiredResidential Building Permit or Counter Building Permit ApplicationNo fence-specific form exists; use the general application forms
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (general valuation table, Appendix L 2018 IRC per current Fee Schedule) | Based on provided labor/material cost or current ICC BVD table | No fence-specific flat fee was found published in the Town's Fee Schedule; billed under the same valuation-based residential construction table as other building permits |
| Residential Admin Fee | $50.00 | — |
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eaton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.