This is PermitBase’s published record for Mead as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Mead building permits

Verified

Mead, Colorado — as published 2026-07-06.

Verified 2026-07-06 · Source

Codes adopted

2024 International Building Code (IBC) — adopted by Town of Mead Ordinance No. 1092, per the Town's own Building Codes page (townofmead.org/building/page/building-codes)2024 International Residential Code (IRC) — adopted by Ordinance No. 10922024 International Mechanical Code (IMC) — adopted by Ordinance No. 10922024 International Plumbing Code (IPC) — adopted by Ordinance No. 10922024 National Electrical Code (NEC) — adopted by Ordinance No. 10922024 International Fuel Gas Code (IFGC) — adopted by Ordinance No. 10922024 International Energy Conservation Code (IECC) — adopted by Ordinance No. 10922024 International Property Maintenance Code (IPMC) — adopted by Ordinance No. 10922024 International Existing Building Code (IEBC) — adopted by Ordinance No. 10922024 International Swimming Pool and Spa Code (ISPSC) — adopted by Ordinance No. 10922021 International Fire Code (IFC) — adopted by Ordinance No. 1036 (older edition than the 2024 suite; not updated alongside the other 2024-edition codes as of this verification)Weld County Code Concerning On-Site Waste-Water Treatment System Regulations, Chapter 30 — adopted by Ordinance No. 892Source: Town of Mead Building Codes page (table of Current Building Code / Edition Year / Ordinance Number), https://www.townofmead.org/building/page/building-codes

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for new single-family homes and similar new residential construction in the Town of Mead. Reviewed under the 2024 IRC/IBC as adopted by Ordinance No. 1092. Plan review and permit administration are performed by SAFEbuilt Colorado under contract to the Town; all applications are submitted through the CommunityConnect online portal.

Verified 2026-07-06 · Source

Requirements

  • Plans must comply with the 2024 IRC/IBC as adopted by Ordinance No. 1092
  • Application must be submitted online via the CommunityConnect Portal — paper applications are not accepted
  • Project valuation is calculated using the most current International Code Council (ICC) valuation data to determine the Building Permit Fee Schedule tier
  • Administrative Permitting Fee applies (covers plot/site plan review and CO inspections): $300 for new residential
  • General Town of Mead business license required for the performing contractor (the Town does not require a separate contractor trade license, but does require a $30 annual business license)

Required documents

  • RequiredBuilding Permit Application (CommunityConnect Portal)Submitted online; paper applications are no longer accepted
  • RequiredSite PlanPlot/site plan showing lot dimensions and proposed structure, reviewed under the Administrative Permitting Fee
  • RequiredConstruction PlansFull plan set for plan review by SAFEbuilt Colorado

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation $1 to $1,000$44.56Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.12; valuation calculated using most current ICC valuation data
Building Permit Fee — valuation $99,001 to $100,000$1,142.81
Building Permit Fee — valuation $100,001 to $500,000$1,142.81 for the first $100,000 plus $6.44 for each additional $1,000 or fraction thereof
Building Permit Fee — valuation $1,000,001 and up$6,450.06 for the first $1,000,000 plus $3.62 for each additional $1,000 or fraction thereof
Plan Review Fee65% of the Building Permit Fee
Administrative Permitting Fee (new residential)$300Covers plot/site plan review and Certificate of Occupancy inspections
Development Impact Fee — Single Family (detached)$17,319 totalMunicipal Facilities $5,560 + Police $634 + Parks/Open Space $3,430 + Storm Drainage/Street $7,695; adjusted annually each Jan. 1 per MMC § 4-6-60(d)

Residential Addition / Remodel Permit

Verified

Required for additions, basement finishes, decks/patio covers, garages, carports, and interior remodels involving structural or wall changes in the Town of Mead. Reviewed under the 2024 IRC as adopted by Ordinance No. 1092.

Verified 2026-07-06 · Source

Requirements

  • Permit required for: building additions or alterations; decks, patio/deck covers, garages and carports; hot tubs, spas and pools; adding, removing, or moving exterior or interior walls; window replacement (non-like-for-like); basement finishes
  • Storage sheds on residential lots that are 120 square feet or smaller, 8 feet or less in height, located in the rear yard, and compliant with accessory-structure setbacks/lot coverage do NOT require a permit
  • Flatwork (patios, sidewalks, driveways) generally does not require a permit, but the Building Division recommends confirming specific code requirements first
  • Application must be submitted online via the CommunityConnect Portal
  • Administrative Permitting Fee and Planning review fee may apply depending on project scope

Required documents

  • RequiredBuilding Permit Application (CommunityConnect Portal)Submitted online; paper applications are not accepted
  • RequiredSite Plan / Floor PlanShowing scope of addition or remodel and connection to the existing structure

Fee schedule

Fee typeAmountNotes
Building Permit Fee (same valuation-based schedule as new construction)$44.56 minimum, scaling per the valuation tiersTown of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.12-13
Plan Review Fee65% of the Building Permit Fee
Planning review (plot/site plan, use, etc.) fee$50

Electrical Permit

Verified

Required for electrical wiring, service, and system modifications in the Town of Mead. Governed by the 2024 NEC as adopted by Ordinance No. 1092. Electrical fees are calculated according to the State of Colorado Electrical Board's fee schedule rather than Mead's own valuation table.

Verified 2026-07-06 · Source

Requirements

  • Permit required for adding electrical wiring, per the Town's 'Do I Need A Building Permit?' page
  • Governed by the 2024 NEC as adopted by Ordinance No. 1092
  • Electrical fees are calculated according to the most current version of the State of Colorado Electrical Board fee schedule, plus or minus 15%, per the Town's Comprehensive Fee Schedule
  • General Town of Mead business license required for the performing electrical contractor (no separate Town trade license required)
  • Application must be submitted online via the CommunityConnect Portal

Required documents

  • RequiredElectrical Permit Application (CommunityConnect Portal)Submitted online; paper applications are not accepted

Fee schedule

Fee typeAmountNotes
Electrical FeesCalculated according to the most current State of Colorado Electrical Board fee schedule (+/-15%)Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11 — Mead does not publish its own flat electrical fee table; it ties the fee to the state board's schedule
Reinspection Fee$75

Plumbing Permit

Verified

Required for plumbing modifications, water/sewer line work, and lawn sprinkler system installation in the Town of Mead. Governed by the 2024 IPC as adopted by Ordinance No. 1092. Water heater replacement and lawn sprinkler installation are categorized as One-Stop (over-the-counter) permits.

Verified 2026-07-06 · Source

Requirements

  • Permit required for: making any change to water lines; adding or replacing a water heater (including tankless); installing a lawn sprinkler system; water/sewer line repair or replacement
  • Water Heater, Water/Sewer Line Repair/Replacement, and Lawn Sprinkler are listed among the Town's One-Stop Permits (over-the-counter, building permit application still required)
  • Governed by the 2024 IPC as adopted by Ordinance No. 1092
  • General Town of Mead business license required for the performing contractor

Required documents

  • RequiredPlumbing/One-Stop Permit Application (CommunityConnect Portal)Submitted online under the applicable One-Stop Permit type or standard building permit application

Fee schedule

Fee typeAmountNotes
Water Heater Replacement (One-Stop Permit)$60Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11, Single Stop Permit Fees
Lawn Sprinkler System (One-Stop Permit)$60
Gas service/line replacement$65
Sewer service/line replacement$65
Water service/line replacement$65
Administrative Processing Fee (Single Stop Permits)$50
Reinspection Fee$75

Mechanical / HVAC Permit

Verified

Required for furnace, air conditioning, and gas fireplace installation or replacement in the Town of Mead. Governed by the 2024 IMC and IFGC as adopted by Ordinance No. 1092. Furnace/AC replacement is categorized as a flat-fee One-Stop Permit.

Verified 2026-07-06 · Source

Requirements

  • Permit required for: adding or replacing a furnace; installing or replacing fireplaces, wood burning stoves, or gas logs; adding or replacing an air conditioner
  • Furnace Installation, Air Conditioning System, and Gas Fireplace are listed among the Town's One-Stop Permits
  • A Gas Line/Plumbing Form and one-line plan is required when installing or changing gas lines for furnaces, fireplaces, or other gas appliances — plan review is necessary for all service installations
  • Governed by the 2024 IMC and IFGC as adopted by Ordinance No. 1092
  • General Town of Mead business license required for the performing contractor

Required documents

  • RequiredMechanical/One-Stop Permit Application (CommunityConnect Portal)Submitted online under the applicable One-Stop Permit type
  • RequiredGas Line/Plumbing Form and one-line planRequired specifically for new or modified gas lines (furnaces, gas ranges, tankless water heaters, fireplaces, outdoor grills); plan review required for all service installations

Fee schedule

Fee typeAmountNotes
Furnace/Air Conditioner Replacement (One-Stop Permit)$70Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11, Single Stop Permit Fees
Administrative Processing Fee (Single Stop Permits)$50
Reinspection Fee$75

Roofing Permit (Reroof)

Verified

Required for re-roofing in the Town of Mead. Governed by the 2024 IBC/IRC roofing provisions as adopted by Ordinance No. 1092. Roofing is categorized as a flat-fee One-Stop Permit.

Verified 2026-07-06 · Source

Requirements

  • Permit required for 're-roofing', per the Town's 'Do I Need A Building Permit?' page
  • Roof/Reroof is listed among the Town's One-Stop Permits with a flat fee
  • General Town of Mead business license required for the performing contractor

Required documents

  • RequiredRoofing/One-Stop Permit Application (CommunityConnect Portal)Submitted online under the Roof/Reroof One-Stop Permit type

Fee schedule

Fee typeAmountNotes
Roof/Reroof (One-Stop Permit)$60Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11, Single Stop Permit Fees
Administrative Processing Fee (Single Stop Permits)$50
Reinspection Fee$75

Solar PV Permit

Verified

Required for photovoltaic solar system installation in the Town of Mead. Governed by the 2024 IBC/IRC and 2024 NEC as adopted by Ordinance No. 1092. PV Solar Systems are explicitly listed as requiring a standard building permit (not a One-Stop Permit).

Verified 2026-07-06 · Source

Requirements

  • PV Solar Systems are explicitly listed as requiring a permit on the Town's 'Do I Need A Building Permit?' page
  • Not listed among the Town's One-Stop Permits — solar is processed as a standard building permit requiring plan review
  • Governed by the 2024 NEC as adopted for electrical scope, and the 2024 IBC/IRC for structural/roof-mounting scope
  • General Town of Mead business license required for the performing contractor

Required documents

  • RequiredBuilding Permit Application (CommunityConnect Portal)Submitted online with plans for structural mounting and electrical interconnection

Fee schedule

Fee typeAmountNotes
Building Permit Fee (general valuation-based schedule)$44.56 minimum, scaling per the valuation tiersNo solar-specific flat fee was found published; PV systems are billed under the same valuation-based Building Permit Fee Schedule as other standard building permits, plus the standard 65% Plan Review Fee
Plan Review Fee65% of the Building Permit Fee

Demolition Permit

Verified

Required for demolition of structures in the Town of Mead, carrying a flat published fee.

Verified 2026-07-06 · Source

Requirements

  • Demolitions are explicitly listed as requiring a permit on the Town's 'Do I Need A Building Permit?' page
  • General Town of Mead business license required for the performing contractor

Required documents

  • RequiredDemolition Permit Application (CommunityConnect Portal)Submitted online

Fee schedule

Fee typeAmountNotes
Demolition$50Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11 — flat fee, not valuation-based

Fence Permit

Verified

Required for fences over six feet in height in the Town of Mead, per the Town's Permit Types page. Fences six feet or under do not require a permit but are subject to height and material restrictions.

Verified 2026-07-06 · Source

Requirements

  • A building permit is required for any person, authorized agent, or business wishing to construct, alter, or move any fence over six (6) feet in height; the permit must be obtained before construction begins
  • No fence permit is required for fences six (6) feet or less in height
  • Fences located on a side yard line in the front yard must be no more than forty-eight (48) inches (4 feet) high, except where required for demonstrated unique security purposes
  • Fences and walls must not be solid, except for retaining walls
  • Necessary maintenance (staining, replacing pickets/hardware) does not require a fence permit, provided the fence type, height, and location are unchanged

Required documents

  • RequiredFence Permit Application (CommunityConnect Portal)Submitted online for fences over 6 feet in height

Fee schedule

Fee typeAmountNotes
Fence permit (6 feet and over)$50Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11 — flat fee

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mead building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-07) →View current record →All versions →

Permalink: /colorado/weld-county/mead/as-of/2026-07-06/

Snapshot date: 2026-07-06

Commit: 07095f3

Reproducible from PermitBase’s version-controlled dataset, commit 07095f3.