Mead building permits
VerifiedDepartment contacts, adopted codes, permit types, fees, and gotchas for Mead, Colorado.
Last verified 2026-07-06 · Source · Embed this page’s badge · Version history
Building department
- Address
- Mead Town Hall, 441 Third Street, Mead, CO 80542 (SAFEbuilt Colorado office: 11409 Business Park Circle, Suite 350, Firestone, CO 80504)
- Phone
- 970.535.4477 (Town Building Division) / 970.545.3555 (SAFEbuilt Building Official Tim Moroney) / 303.774.1388 (SAFEbuilt Colorado main line)
- Office hours
- Monday-Friday, 8 a.m. to 5 p.m. (Building Division contact hours, per townofmead.org/building); Mead Town Hall itself is open 8 a.m. to 4:30 p.m. Monday through Friday
- Website
- Official site
- Permit portal
- Apply online at Mead's portal
Inspection guide
See how inspections work in Mead — sequence, scheduling & re-inspection fees.
Codes adopted
Colorado has no statewide-mandated building code edition. Under the Colorado Constitution's home-rule provisions (art. XX, home rule for municipalities since 1902; home rule for counties since 1970), building codes and zoning are an enumerated home-rule charter power, so cities and counties adopt and amend their own construction codes independently — predominantly the I-Codes, with editions and local amendments varying by jurisdiction. The one statewide floor is for energy: HB22-1362 (2022) created the Energy Code Board (jointly appointed by the Colorado Energy Office and the Department of Local Affairs) and requires that, on or after July 1, 2023 and before July 1, 2026, any municipality or county that adopts or updates a building code must adopt and enforce an energy code achieving performance equivalent to or better than the 2021 IECC together with the board's Model Electric Ready and Solar Ready Code (which includes electric-ready, EV-ready, and solar-ready provisions); from July 1, 2026 onward the floor shifts to the board's Model Low Energy and Carbon Code or an equivalent. Electrical and plumbing permitting defaults to the Colorado State Electrical Board and State Plumbing Board (within DORA's Division of Professions and Occupations) — the state issues permits and inspects statewide except in counties/jurisdictions that operate their own certified Electrical or Plumbing Inspection Program, in which case the local program has authority instead. Always confirm the currently adopted code edition, local amendments, and inspection authority (state board vs. local program) with the specific jurisdiction before submitting plans.
- 2024 International Building Code (IBC) — adopted by Town of Mead Ordinance No. 1092, per the Town's own Building Codes page (townofmead.org/building/page/building-codes)
- 2024 International Residential Code (IRC) — adopted by Ordinance No. 1092
- 2024 International Mechanical Code (IMC) — adopted by Ordinance No. 1092
- 2024 International Plumbing Code (IPC) — adopted by Ordinance No. 1092
- 2024 National Electrical Code (NEC) — adopted by Ordinance No. 1092
- 2024 International Fuel Gas Code (IFGC) — adopted by Ordinance No. 1092
- 2024 International Energy Conservation Code (IECC) — adopted by Ordinance No. 1092
- 2024 International Property Maintenance Code (IPMC) — adopted by Ordinance No. 1092
- 2024 International Existing Building Code (IEBC) — adopted by Ordinance No. 1092
- 2024 International Swimming Pool and Spa Code (ISPSC) — adopted by Ordinance No. 1092
- 2021 International Fire Code (IFC) — adopted by Ordinance No. 1036 (an older edition than the 2024 suite; not updated alongside the other 2024-edition codes)
- Weld County Code Concerning On-Site Waste-Water Treatment System Regulations, Chapter 30 — adopted by Ordinance No. 892
- Source: Town of Mead Building Codes page (table of Current Building Code / Edition Year / Ordinance Number), https://www.townofmead.org/building/page/building-codes
Permit types & fees
Residential Building Permit (New Construction)
Required for new single-family homes and similar new residential construction in the Town of Mead. Reviewed under the 2024 IRC/IBC as adopted by Ordinance No. 1092. Plan review and permit administration are performed by SAFEbuilt Colorado under contract to the Town; all applications are submitted through the CommunityConnect online portal.
From$44.56Residential Addition / Remodel Permit
Required for additions, basement finishes, decks/patio covers, garages, carports, and interior remodels involving structural or wall changes in the Town of Mead. Reviewed under the 2024 IRC as adopted by Ordinance No. 1092.
From$44.56valuation-basedElectrical Permit
Required for electrical wiring, service, and system modifications in the Town of Mead. Governed by the 2024 NEC as adopted by Ordinance No. 1092. Electrical fees are calculated according to the State of Colorado Electrical Board's fee schedule rather than Mead's own valuation table.
See fee schedulePlumbing Permit
Required for plumbing modifications, water/sewer line work, and lawn sprinkler system installation in the Town of Mead. Governed by the 2024 IPC as adopted by Ordinance No. 1092. Water heater replacement and lawn sprinkler installation are categorized as One-Stop (over-the-counter) permits.
From$60Mechanical / HVAC Permit
Required for furnace, air conditioning, and gas fireplace installation or replacement in the Town of Mead. Governed by the 2024 IMC and IFGC as adopted by Ordinance No. 1092. Furnace/AC replacement is categorized as a flat-fee One-Stop Permit.
From$70Roofing Permit (Reroof)
Required for re-roofing in the Town of Mead. Governed by the 2024 IBC/IRC roofing provisions as adopted by Ordinance No. 1092. Roofing is categorized as a flat-fee One-Stop Permit.
From$60Solar PV Permit
Required for photovoltaic solar system installation in the Town of Mead. Governed by the 2024 IBC/IRC and 2024 NEC as adopted by Ordinance No. 1092. PV Solar Systems are explicitly listed as requiring a standard building permit (not a One-Stop Permit).
From$44.56valuation-basedDemolition Permit
Required for demolition of structures in the Town of Mead, carrying a flat published fee.
$50Fence Permit
Required for fences over six feet in height in the Town of Mead, per the Town's Permit Types page. Fences six feet or under do not require a permit but are subject to height and material restrictions.
$50EV Charger / EVSE Permit
The Town of Mead has no separate permit type or fee line item for EV charging station (EVSE) installation. A Level 1/Level 2 EV charging circuit is electrical work, governed by the 2024 NEC as adopted by Ordinance No. 1092, and is billed the same way as any other electrical work in Mead: per the most current State of Colorado Electrical Board fee schedule, plus or minus 15% (Colorado Revised Statutes Article 23, Section 12-23-117, which caps local electrical-inspection surcharges statewide at 15% above the State Board's own schedule and bars any other local electrical fee). Mead's population is below the 10,000-resident threshold that triggers Colorado HB24-1173's mandatory EV-permitting-process requirements for covered municipalities.
From$2,000valuation-basedCommercial Building Permit (New Construction / Tenant Improvement)
Required to construct, expand, alter, or repair any structure used for commercial purposes in the Town of Mead — from a new office or retail facility down to adding a wall or a few outlets in an existing tenant space — and for converting an existing residence to a commercial use such as an office. Reviewed under the 2024 IBC suite as adopted by Ordinance No. 1092. Plan review and permit administration are performed by SAFEbuilt Colorado under contract to the Town; all applications are submitted through the CommunityConnect online portal. Every commercial permit application must include a Mountain View Fire Rescue District plan review application.
From$44.56Sign Permit
A Sign Permit Application must be completed by any person, authorized agent, or business wishing to erect, install, or place any banner or sign in the Town of Mead, per Town Code Section 16.7.40 (Sign Permits).
See fee scheduleFire Sprinkler / Fire Alarm System Permit
Fire protection for Mead is provided by Mountain View Fire Rescue (MVFR/MVFPD, 6328 Monarch Park Place, Niwot, CO 80503, (303) 772-0710, plans@mvfpd.org), a special district serving 184 square miles including Mead, Dacono, Del Camino, Niwot, Erie, and unincorporated Boulder/Weld counties. MVFR's Fire Prevention Division publishes a Fee Schedule (Fire Prevention Division) confirming that review of installation/modification plans for fire protection and life-safety systems — including fire alarm systems, automatic fire-extinguishing systems, and standpipe systems — is billed based on the total valuation of the work, with a doubled fee if work begins before approval is granted. General plan review/consultation and revision fees run $85.00/hr (minimum charges apply), and re-inspection of a failed inspection is $125.00/hr.
From$85.00Change of Use / Change of Occupancy
The Town of Mead requires a commercial building permit and inspection for all new businesses, to verify zoning and building code compliance — a real, City-confirmed requirement, though the Town does not appear to publish a standalone 'change of use' application distinct from this general commercial building permit process.
See fee schedule
Mead's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Mead yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Mead lands. Privacy.
New residential construction activity
New privately-owned residential construction onlyHousing units authorized by building permits for new privately-owned residential construction — this is not total permit volume (no commercial permits or remodels).
- Latest month (2026-07)
- 4units
4 buildings · $1.9M valuation
- Trailing 12 months
- 81units
12 of 12 months reported · #37 in Colorado coverage by units
- Year to date (2026 YTD through 2026-07)
- 42units
42 buildings · $22M valuation
7 month(s) reported to Census
- Full year 2025
- 88units
88 buildings · $40.9M valuation
Source: U.S. Census Bureau, Building Permits Survey (BPS), 2026-07 vintage. Census survey data — separate from the permit-requirements verification above. All Colorado building activity
Tips & gotchas
- Mead's Building Division is administered under contract by SAFEbuilt Colorado; the Building Official is Tim Moroney (tmoroney@safebuilt.com, 970.545.3555), and inspection requests route to firestone-building@safebuilt.com or 303.774.0454. The Town's own Permit Technician, Ana Bohl, handles portal/administrative questions at 970.805.4197.
- All permit applications — including One-Stop Permits — must be submitted through the CommunityConnect online portal; paper applications have not been accepted since January 27, 2021.
- The Town does not require its own contractor trade license, but does require a general $30 annual Town of Mead business license for anyone conducting business (including contractors) within Town limits.
- Development Impact Fees are a substantial addition to the cost of new residential construction ($17,319 for a detached single-family home as of the June 1, 2026 fee schedule) and are adjusted every January 1 based on a 5-year construction-cost-index formula — budget for the current-year rate rather than a prior year's figure.
- The Town's adopted code suite is mostly the 2024 I-Codes (via Ordinance No. 1092), but the International Fire Code is still the 2021 edition (Ordinance No. 1036) — do not assume every adopted code shares the same 2024 edition year.
- No jurisdiction-published numeric plan-review or permit-issuance turnaround time exists anywhere on townofmead.org or in the Comprehensive Fee Schedule; every permit type in this record reflects that genuine gap rather than an invented figure.