Roofing Permit (Reroof) in Mead, Colorado

Required for re-roofing in the Town of Mead. Governed by the 2024 IBC/IRC roofing provisions as adopted by Ordinance No. 1092. Roofing is categorized as a flat-fee One-Stop Permit.

Verified 2026-07-06 · Source

When you need this permit

  • Permit required for 're-roofing', per the Town's 'Do I Need A Building Permit?' page
  • Roof/Reroof is listed among the Town's One-Stop Permits with a flat fee
  • General Town of Mead business license required for the performing contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Roof/Reroof (One-Stop Permit)Town of Mead Comprehensive Fee Schedule, effective June 1, 2026, p.11, Single Stop Permit Fees
$60
Administrative Processing Fee (Single Stop Permits)
$50
Reinspection Fee
$75

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Reroof) permit actually take in Mead?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Completed roof covering verified against approved plans and applicable code

See the full Mead inspection guide — scheduling & re-inspection fees →

Tips

  • Reroofing in Mead is a flat $60 One-Stop Permit fee (plus the $50 Administrative Processing Fee), not a valuation-based fee.
  • Siding replacement is a separate One-Stop line item ($70) from roofing — apply under the correct permit type.

Frequently asked questions

Yes. Re-roofing is explicitly listed as requiring a permit on the Town's 'Do I Need A Building Permit?' page and is processed as a flat-fee ($60) One-Stop Permit.

In Mead, the published Roof/Reroof (One-Stop Permit) is: $60. Additional published fees: Administrative Processing Fee (Single Stop Permits) — $50; Reinspection Fee — $75. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Mead does not publish a plan-review timeline for this permit. Contact Town of Mead Building Division (building administration contracted to SAFEbuilt Colorado) at 970.535.4477 (Town Building Division) / 970.545.3555 (SAFEbuilt Building Official Tim Moroney) / 303.774.1388 (SAFEbuilt Colorado main line) for current turnaround.

You'll need: Roofing/One-Stop Permit Application (CommunityConnect Portal). See the required-documents checklist on this page for details on each.

Mead requires 1 inspection(s) for a roofing permit (reroof), in order: Final Inspection. Schedule each through Town of Mead Building Division (building administration contracted to SAFEbuilt Colorado) (970.535.4477 (Town Building Division) / 970.545.3555 (SAFEbuilt Building Official Tim Moroney) / 303.774.1388 (SAFEbuilt Colorado main line)).

Apply through Town of Mead Building Division (building administration contracted to SAFEbuilt Colorado) at Mead Town Hall, 441 Third Street, Mead, CO 80542 (SAFEbuilt Colorado office: 11409 Business Park Circle, Suite 350, Firestone, CO 80504). Phone: 970.535.4477 (Town Building Division) / 970.545.3555 (SAFEbuilt Building Official Tim Moroney) / 303.774.1388 (SAFEbuilt Colorado main line), email: tmoroney@safebuilt.com (SAFEbuilt Building Official Tim Moroney); firestone-building@safebuilt.com (SAFEbuilt Inspection Requests); safebuiltcoloradoplanreview@safebuilt.com (SAFEbuilt Plan Review re-submittals). Office hours: Monday-Friday, 8 a.m. to 5 p.m. (Building Division contact hours, per townofmead.org/building); Mead Town Hall itself is open 8 a.m. to 4:30 p.m. Monday through Friday. Official information: https://www.townofmead.org/building.

Mead, Colorado has adopted: 2024 International Building Code (IBC) — adopted by Town of Mead Ordinance No. 1092, per the Town's own Building Codes page (townofmead.org/building/page/building-codes); 2024 International Residential Code (IRC) — adopted by Ordinance No. 1092; 2024 International Mechanical Code (IMC) — adopted by Ordinance No. 1092; 2024 International Plumbing Code (IPC) — adopted by Ordinance No. 1092; 2024 National Electrical Code (NEC) — adopted by Ordinance No. 1092; 2024 International Fuel Gas Code (IFGC) — adopted by Ordinance No. 1092; 2024 International Energy Conservation Code (IECC) — adopted by Ordinance No. 1092; 2024 International Property Maintenance Code (IPMC) — adopted by Ordinance No. 1092; 2024 International Existing Building Code (IEBC) — adopted by Ordinance No. 1092; 2024 International Swimming Pool and Spa Code (ISPSC) — adopted by Ordinance No. 1092; 2021 International Fire Code (IFC) — adopted by Ordinance No. 1036 (older edition than the 2024 suite; not updated alongside the other 2024-edition codes as of this verification); Weld County Code Concerning On-Site Waste-Water Treatment System Regulations, Chapter 30 — adopted by Ordinance No. 892; Source: Town of Mead Building Codes page (table of Current Building Code / Edition Year / Ordinance Number), https://www.townofmead.org/building/page/building-codes. Local amendments apply — see the Mead overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mead building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.