EV Charger / EVSE Permit — Mead, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.townofmead.org/media/42471
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Mead, Colorado
The Town of Mead has no separate permit type or fee line item for EV charging station (EVSE) installation. A Level 1/Level 2 EV charging circuit is electrical work, governed by the 2024 NEC as adopted by Ordinance No. 1092, and is billed the same way as any other electrical work in Mead: per the most current State of Colorado Electrical Board fee schedule, plus or minus 15% (Colorado Revised Statutes Article 23, Section 12-23-117, which caps local electrical-inspection surcharges statewide at 15% above the State Board's own schedule and bars any other local electrical fee). Mead's population is below the 10,000-resident threshold that triggers Colorado HB24-1173's mandatory EV-permitting-process requirements for covered municipalities.
Verified 2026-07-20 · Source
When you need this permit
- Permit required for the EV charger circuit/panel work, per the Town's 'Do I Need A Building Permit?' page listing 'adding electrical wiring' as requiring a permit
- Governed by the 2024 NEC as adopted by Ordinance No. 1092
- Electrical fees are calculated per the most current State of Colorado Electrical Board fee schedule (+/-15%), since C.R.S. § 12-23-117 bars Colorado municipalities from imposing any other electrical-permit fee or charge
- General Town of Mead business license required for the performing electrical contractor
- Application must be submitted online via the CommunityConnect Portal
- As a municipality with population under Colorado HB24-1173's 10,000-resident threshold, Mead is not a jurisdiction the statute mandates to adopt the state's model EV charging permitting code or a 3-business-day decision timeline — no evidence was found that Mead has voluntarily opted in
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring and panel/circuit work inspected before concealment
- 2
Final Inspection
Charger circuit installed, devices installed, system energized
See the full Mead inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated EV-charger permit or fee category in Mead — apply through the standard Electrical Permit process on the CommunityConnect Portal.
- Colorado law (C.R.S. § 12-23-117) caps what any municipality, including Mead, can charge for electrical permits at 15% above the State Electrical Board's own schedule, and bars charging any other electrical fee — so Mead's fee is fundamentally a state-set figure, not a locally invented one.
- Mead's small population (well under Colorado's 10,000-resident HB24-1173 threshold) means the Town is not statutorily required to offer the state's expedited EV-charging permit timeline — confirm current practice directly with the Building Division before assuming an expedited review applies.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mead building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mead
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →