Mead building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Mead, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Mead Town Hall, 441 Third Street, Mead, CO 80542 (SAFEbuilt Colorado office: 11409 Business Park Circle, Suite 350, Firestone, CO 80504)
- Phone
- 970.535.4477 (Town Building Division) / 970.545.3555 (SAFEbuilt Building Official Tim Moroney) / 303.774.1388 (SAFEbuilt Colorado main line)
- Office hours
- Monday-Friday, 8 a.m. to 5 p.m. (Building Division contact hours, per townofmead.org/building); Mead Town Hall itself is open 8 a.m. to 4:30 p.m. Monday through Friday
- Website
- Official site
Published scheduling rules
- Mead's Building Division is administered under contract by SAFEbuilt Colorado; the Building Official is Tim Moroney (tmoroney@safebuilt.com, 970.545.3555), and inspection requests route to firestone-building@safebuilt.com or 303.774.0454. The Town's own Permit Technician, Ana Bohl, handles portal/administrative questions at 970.805.4197. (General)
Inspection sequence
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings)
Before concrete pour, if applicable
- 2
Framing
Framing and connection to existing structure
- 3
Rough Electrical/Plumbing/Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical/Plumbing/Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes; required before Certificate of Occupancy
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Wiring and panel/circuit work inspected before concealment
- 2
Final Inspection
Charger circuit installed, devices installed, system energized
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Equipment
Equipment installation and gas line connections before concealment
- 2
Final Inspection
Equipment operational; combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Before concealment — pipe slope, materials, cleanouts
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Solar PV Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final Inspection
Racking, roof penetrations, and electrical connections verified
Final inspection only: Demolition Permit, Fence Permit, Roofing Permit (Reroof)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mead building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.