Sandpoint building permits

Verified

Sandpoint, Idaho — as published 2026-07-04.

Verified 2026-07-13 · Source

Codes adopted

IMPORTANT JURISDICTIONAL NOTE: Sandpoint is a NOTABLE EXCEPTION inside Bonner County. Bonner County itself has adopted NO building code for unincorporated county land (confirmed no-program county, same category as WY Fremont County and NV Eureka County) — the county's own 'Building Location Permit' (BLP) is a zoning/setback/land-use permit only, administered by the Bonner County Planning Department, and is NOT a building-code permit (source: Bonner County Building Location Permit page, bonnercountyid.gov/building-location-permit, and the county's own 'Do I Need a Permit?' brochure, which lists 'Bonner County Planning Department' separately from 'Sandpoint Planning & Building Department' under 'Local Planning & Building Departments,' with construction/electrical/plumbing/HVAC permits routed to the State of Idaho DOPL rather than to the county). Sandpoint is the one incorporated city INSIDE Bonner County that maintains its own dedicated building department, building official, and locally-administered permit process under the International Building Code family — this City building-code requirement applies ONLY inside Sandpoint city limits. Anywhere else in Bonner County (unincorporated land) has no local building-code requirement beyond Idaho's statewide minimums administered by DOPL for the regulated trades. Source: Bonner County 'Do I Need a Permit?' brochure (bonnercountyid.gov/media/Planning/Application%20Information/BLP/Do%20I%20Need%20a%20Permit%20Brochure%2009.12.23.pdf), listing 'Sandpoint Planning & Building Department, 1123 Lake St., Sandpoint, ID 83864, 208-263-3158' as a distinct entry from 'Bonner County Planning Department, 1500 Hwy 2, Sandpoint, ID 83864, 208-265-1458' under the brochure's 'Local Planning & Building Departments' section.Idaho Building Code Act, Idaho Code Title 39, Chapter 41: establishes a mandatory statewide building code adopted by the Idaho Building Code Board, administered locally by cities/counties that choose to adopt and enforce it per Idaho Code 39-4116. The state's currently adopted cycle (2021 International Codes family) took effect statewide January 1, 2022. Source: Idaho Building Code Act, Idaho Code Title 39 Ch. 41, legislature.idaho.gov/statutesrules/idstat/title39/t39ch41/City of Sandpoint's own Building Permit Application form (rev. 202601) states the form 'is intended to be used for buildings that are constructed or altered per International Building Code (IBC)' and that construction must be 'in accordance with [all] building codes adopted by the City of Sandpoint,' directing applicants to 'the City of Sandpoint website under ‘Codes’ within Title 8' of City Code for the complete locally-adopted code list. Source: City of Sandpoint Building Permit Application (PDF, rev. 202601), sandpointidaho.gov/media/17816City of Sandpoint's own Residential Construction Checklist states explicitly: 'Any construction following under the 2018 IRC' — confirming the 2018 International Residential Code is the locally-adopted residential code edition as of this review (NOTE: this is one cycle behind the current 2021 statewide-mandated cycle referenced on the Idaho Building Code Act page; the City's own published checklist has not been updated to reference the newer cycle as of this review — flagged here rather than assumed). Source: City of Sandpoint Residential Construction Checklist (PDF), sandpointidaho.gov/media/19366Sandpoint City Code Title 8, 'Building Regulations' (codified via Ordinance No. 1436, enacted/effective 2/18/2026 per the Municode Library codification note), is the City's locally-adopted building-code chapter; full itemized code-edition text (specific IBC/IRC/IECC/IMC/IFGC sections and any local amendments) is hosted on Municode's JavaScript-rendered library platform (library.municode.com/id/sandpoint/codes/code_of_ordinances?nodeId=TIT8BURE) and could not be extracted as machine-readable text in this review; the City's own Building Permit Application PDF (above) is the primary source actually used here for the general 'City has adopted the IBC/IRC family under Title 8' fact.Electrical, plumbing, and mechanical/HVAC trade permitting in Idaho is primarily administered directly by the Idaho Division of Occupational and Professional Licenses (DOPL), Division of Building Safety (208-334-3950 / 208-334-3233), in jurisdictions that have not assumed local authority. The City of Sandpoint's own published 'Permit Submittal' / Building Applications page lists only a Building Permit Application, a Mechanical Permit Application, and a Fire Alarm/Sprinkler Application as City-issued forms — NO separate City-issued Electrical or Plumbing permit application is published, consistent with DOPL retaining direct electrical and plumbing permitting/inspection jurisdiction in Sandpoint (the City issues Building and Mechanical/HVAC permits locally; Electrical and Plumbing work is permitted through DOPL). This could not be triple-confirmed against DOPL's own jurisdiction chart (referenced by DOPL's Electrical FAQ as a PDF chart of jurisdiction by geography, but a direct working link to that chart was not found in this review) — flagged rather than asserted with full certainty; the inference is based on the City's own silence on Electrical/Plumbing applications plus DOPL's own FAQ language that permit requirements 'vary widely' by whether a city/county has 'assumed jurisdiction.' Source: City of Sandpoint Building Applications / Permit Submittal page, sandpointidaho.gov/building/page/building-permit-forms; DOPL Electrical FAQ, dopl.idaho.gov/ele/ele-faqs/; Bonner County 'Do I Need a Permit?' brochure, bonnercountyid.gov/media/Planning/Application%20Information/BLP/Do%20I%20Need%20a%20Permit%20Brochure%2009.12.23.pdf

Permit types & fees

Residential Building Permit (New Single-Family Construction)

Verified

Required for new single-family residential construction within Sandpoint city limits, governed by the City's locally-adopted 2018 IRC (per the City's own published Residential Construction Checklist) plus City Design Criteria and Title 8/Title 9 City Code requirements. Applications are submitted online through the BS&A permit portal (bsaonline.com), with the printed Building Permit Application PDF attached to the submission.

Verified 2026-07-04 · Source

Requirements

  • Any construction falling under the 2018 IRC requires this permit path (per the City's own Residential Construction Checklist)
  • Contractors must hold an active City of Sandpoint business license and be registered with the State of Idaho
  • Complete project submittals only are accepted for review; incomplete packages are rejected outright
  • Required submittal documents: Permit Application, Owner Authorization Form (if applicant is not the owner of record), full architectural drawing set (cover/title sheet, site plan, elevations, floor/egress plans, foundation plan, floor/roof framing plans, sections/details/schedules, demolition plan if applicable), landscape drawings, Dark Sky Compliance documentation, structural calculations (if applicable), ResCheck or other IECC energy-code compliance documentation, fire sprinkler/alarm contractor contact information (if applicable), Sidewalk Ordinance Compliance note (per Ord. 1370, Title 7 Ch. 3) as applicable, and a Utility Plan
  • After completeness review is approved, the applicant receives a Plan Review Invoice (plan check fees only); once paid, the compliance/code review is assigned and takes 15 business days to complete
  • If a Plan Check Letter is issued (comments/corrections), the applicant must resubmit addressing all comments before re-review
  • Once all reviews are approved, a Final Permit Invoice is issued indicating the permit packet is ready for pickup (takes a few additional days beyond the 15-business-day review — the permit is not ready the same day reviews are completed)
  • Permit application deemed abandoned 180 days after filing if not pursued in good faith or issued (one 90-day extension available with justifiable cause, in writing); an issued permit is deemed abandoned 180 days after issuance if work is not pursued in good faith

Required documents

  • RequiredBuilding Permit ApplicationCity of Sandpoint Building Permit Application (PDF, rev. 202601); must be attached to the BS&A online submission or included with an in-person application
  • OptionalOwner Authorization FormRequired if the applicant is not the property owner of record
  • RequiredArchitectural Drawing SetCover/title sheet (project address, legal description, sheet index, scope of work, applicable codes, construction type, project team contacts), site plan (north arrow, property/lot lines, structure locations, setbacks, finished floor elevations, adjacent streets/utilities), floor plan(s) with egress, foundation plan, floor/roof framing plans, sections/details/schedules, and demolition plan if applicable
  • RequiredLandscape Drawings
  • RequiredDark Sky Compliance Documentation
  • RequiredResCheck or Other IECC Energy Code Compliance Documentation
  • OptionalStructural CalculationsRequired if applicable to the scope of work
  • RequiredUtility Plan

Fee schedule

Fee typeAmountNotes
Building Fee/Valuation — $0 to $2,000 of value$61.10City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $2,001 to $25,000 of value$86.02 for the first $2,000 plus $16.29 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $25,001 to $50,000 of value$460.69 for the first $25,000 plus $8.15 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $50,001 to $100,000 of value$751.69 for the first $50,000 plus $8.15 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $100,001 to $500,000 of value$1,159.19 for the first $100,000 plus $6.52 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $500,001 to $1,000,000 of value$3,767.19 for the first $500,000 plus $5.52 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Building Fee/Valuation — $1,000,001 and over$6,527.19 for the first $1,000,000 plus $4.25 per additional $1,000City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Minimum Building Permit Fee$174.60Applies if the calculated valuation-based fee is less than $172.75; includes 1 standard/single inspection per phase. City of Sandpoint Fee Schedule, effective 8/16/2023 (Resolution 23-63)
Standard Plan Check Fee65% of building permit feeUp to two completeness reviews included. City of Sandpoint Fee Schedule (Res 02-44, incorporated into current schedule effective 8/16/2023)
Zoning Review Fee10% of building permit fee, in addition to the Building Plan Check FeeCity of Sandpoint Fee Schedule, effective 10/1/2020 (Resolution 20-39)
Plan Check, New Single Family (7,999 SF or less), if prepared/stamped by a registered/licensed professional25% of building permit feeCity of Sandpoint Fee Schedule, effective 10/1/2020 (Resolution 20-39)
Impact Fee — Single Family 0-3 bedrooms (Outside Downtown URA)$3,895.00 per housing unit (Total Impact Fee, all components combined)City of Sandpoint Fee Schedule, effective 2/1/2012 (Resolution 11-55); lower rate of $3,417.00 applies inside the Downtown Urban Renewal Area

Building-Permit-Exempt Work (Residential and Commercial)

Verified

The City of Sandpoint publishes a specific list of residential and commercial work exempt from a building permit requirement, though exemption does not authorize work in violation of currently adopted City codes and ordinances.

Verified 2026-07-04 · Source

Requirements

  • RESIDENTIAL exemptions: one-story detached accessory structures (sheds, playhouses) up to 200 sq. ft.; fences not over 7 feet high; retaining walls not over 4 feet high (footing to top) unless supporting a surcharge; water tanks on grade up to 5,000 gallons (height:diameter ratio not exceeding 2:1); sidewalks and driveways; painting/papering/tiling/carpeting/cabinets/countertops and similar finish work; prefabricated swimming pools not greater than 4 feet deep; swings/playground equipment; window awnings projecting not more than 54 inches without additional support; decks not exceeding 200 sq. ft., not more than 30 inches above grade, not attached to a dwelling, and not serving a required IRC R311.4 exit door; flagpoles
  • RESIDENTIAL mechanical exemptions: portable heating/cooking/clothes-drying appliances; minor part replacement not altering equipment approval/safety; portable fuel-cell appliances not connected to fixed piping/power grid; portable ventilation appliances; steam/hot/chilled water piping within already-regulated equipment; portable evaporative coolers; self-contained refrigeration systems with 10 lbs or less of refrigerant or actuated by 1 HP or less motors
  • COMMERCIAL exemptions differ slightly: accessory structures up to 120 sq. ft. (vs. 200 sq. ft. residential); sidewalks/driveways not more than 30 inches above grade and not over a basement/story below or part of an accessible route; temporary motion picture/TV/theater stage sets; prefabricated pools accessory to Group R3 less than 24 inches deep, 5,000 gallons max, entirely above ground; shade cloth structures for nursery/agricultural purposes; window awnings in Group R3/U occupancies; nonfixed/movable fixtures/cases/racks/counters/partitions not over 5'9" tall
  • EMERGENCY REPAIRS: where replacements/repairs must be performed in an emergency, the permit application must be submitted within the next working business day
  • ORDINARY REPAIRS (lamp replacement, connecting approved portable equipment to approved permanently-installed receptacles) do not require a permit, but this exemption excludes cutting/removing structural beams or load-bearing supports, changes to required egress, or work affecting standpipes/water supply/sewer/drainage/gas/electric wiring/other health-and-safety-affecting systems

Required documents

  • OptionalWhen is a Building Permit Required? (handout)City of Sandpoint Infrastructure and Development Services handout listing all residential/commercial exemptions

Fee schedule

Fee typeAmountNotes

Mechanical / HVAC Permit

Verified

Required for HVAC and gas-fired appliance installation/alteration/replacement within Sandpoint city limits. The City issues Mechanical Permits directly (a Mechanical Permit Application is published on the City's own Building Applications page), billed per the City's own itemized mechanical fee schedule.

Verified 2026-07-04 · Source

Requirements

  • A Mechanical Permit Application (separate from the general Building Permit Application) must be submitted for HVAC/mechanical/gas-fired-appliance work
  • Residential Base Permit fee plus a per-hour Plan Check/Technical Service Fee applies
  • Itemized per-appliance/per-duct/per-outlet fee schedule applies for residential work; commercial/industrial work is billed as a percentage of total system job value
  • Manual S, J, and D review fee required when installing the primary heating/cooling system in a NEW single- or multi-family dwelling

Required documents

  • RequiredMechanical Permit ApplicationPublished on the City of Sandpoint Building Applications / Permit Submittal page

Fee schedule

Fee typeAmountNotes
Residential Base Permit$100.00City of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45)
Plan Check or Technical Service Fee$65.00 per hourCity of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45)
Appliances (furnace, A/C, heat pump, evaporative cooler, unit heater, space heater, boiler not supplying potable water, pool heater, mini-split, free-standing gas/solid-fuel stove, gas fireplace, HRV/ERV or similar comfort-conditioning appliance)$30 for the first appliance + $15 for each additional applianceCity of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45); includes associated ducts and flues
Exhaust duct or ventilation duct (dryer, range hood, bath fan, crawl space exhaust, similar exhaust ducts or ventilation duct)$15 for the first duct + $5 for each additional ductCity of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45)
Fuel Gas Piping$5.00 per appliance outletCity of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45)
Hydronic System$5.00 per zoneCity of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45); does not include boiler, billed separately
Manual S, J, & D Review$25.00Required when installing the primary heating/cooling system in a NEW single- or multi-family dwelling. City of Sandpoint Fee Schedule, effective 10/1/2021 (Resolution 21-45)
Commercial/Industrial — job value up to $10,000Total cost of system x 0.02 + $60City of Sandpoint Fee Schedule, effective 10/1/2020 (Resolution 20-39)
Commercial/Industrial — job value $10,001-$100,000Total cost of system - $10,000 x 0.01 + $260City of Sandpoint Fee Schedule, effective 10/1/2020 (Resolution 20-39)
Commercial/Industrial — job value $100,001 or moreTotal cost of system - $100,000 x 0.005 + $1,160City of Sandpoint Fee Schedule, effective 10/1/2020 (Resolution 20-39)

Electrical and Plumbing Permits (State DOPL Jurisdiction)

Verified

Unlike Coeur d'Alene (which issues its own Electrical and Plumbing permits directly), the City of Sandpoint's own published Building Applications page lists only a Building Permit Application, a Mechanical Permit Application, and a Fire Alarm/Sprinkler Application as City-issued forms — no City-issued Electrical or Plumbing permit application is published. Electrical wiring and plumbing work in Sandpoint is permitted through the Idaho Division of Occupational and Professional Licenses (DOPL), Division of Building Safety, which retains direct construction-permit jurisdiction for electrical, plumbing, and HVAC systems in jurisdictions that have not assumed local authority.

Verified 2026-07-13 · Source

Requirements

  • Construction permits for electrical wiring and plumbing work are obtained through the State of Idaho (Division of Building Safety, DBS, part of the Division of Occupational and Professional Licenses / DOPL), not the City of Sandpoint
  • Electricians and plumbers must hold current State of Idaho electrical/plumbing licenses issued through DOPL
  • DOPL permits generally expire 365 days from purchase date and may be renewed for one additional year for a $65 renewal fee (per DOPL's general permit-duration policy)
  • CONFIRMED 2026-07-13 (uncertainty flag resolved via real-browser re-check): the City of Sandpoint's own 'Permit Types' handout (Infrastructure and Development Services, linked from the Building department's Frequently Asked Questions page) states explicitly and directly, without qualification: 'ELECTRICAL — Electrical Permits are issued through the State of Idaho Division of Building Safety (DBS). For more information, please go to https://dbs.idaho.gov/programs/electrical/' and 'PLUMBING — Plumbing Permits are required for sewer and water service installation or repairs on private property and for plumbing new construction. These permits are issued through the State of Idaho Division of Building Safety (DBS).' dbs.idaho.gov redirects to dopl.idaho.gov (Division of Building Safety is a program within DOPL). This is now a directly-stated City fact, not an inference from the absence of a City-published application form. UPDATE 2026-07-16 (link-liveness re-check): re-fetched the City's Permit Types PDF live this session (HTTP 200, text unchanged — the quoted 'ELECTRICAL'/'PLUMBING' language above is still exactly what the City's own document says, confirming no drift in the underlying fact). However, the City's own cited URL, https://dbs.idaho.gov/programs/electrical/, is now a dead deep link: it returns HTTP 200 but silently redirects to the dopl.idaho.gov homepage rather than any electrical-specific page (DOPL absorbed the former Division of Building Safety and old dbs.idaho.gov deep links do not carry forward). The City's own PDF has not been updated to reflect this and still prints the dead URL verbatim. Live, content-verified successor fetched and confirmed 2026-07-16: https://dopl.idaho.gov/ele/ele-permits-and-inspections/ (titled 'Permits and Inspections' under 'Idaho Electrical Board,' listing Contractor Electrical Permit Application, Homeowner Electrical Permit Application, Permit Extension Request, and Permit Transfer Application — consistent with DOPL directly issuing electrical permits, the same fact the City's handout asserts).

Required documents

    Fee schedule

    Fee typeAmountNotes

    Solar Photovoltaic (PV) Permit

    Verified

    Required for installing a rooftop or ground-mount photovoltaic system within Sandpoint city limits. TWO separate permits apply: a City of Sandpoint Building Permit for the structural/roof-mount work (valuation-based, no dedicated solar line item on the City's own Fee Schedule) and a State of Idaho DOPL Electrical Permit for the PV electrical installation (DOPL, not the City, issues electrical permits in Sandpoint, per the City's own 'Permit Types' handout), which DOES publish a dedicated Solar/Renewable Energy fee formula.

    Verified 2026-07-20 · Source

    Requirements

    • City of Sandpoint Building Permit required for the structural/roof-mount component; reviewed under the same valuation-based Building Fee/Valuation table used for all other building work — no solar-specific fee line found on the City's Fee Schedule (effective 8/21/2024, Res 24-061)
    • State of Idaho DOPL Electrical Permit required separately for the PV system's electrical installation — purchased online at dbs.idaho.gov (redirects to dopl.idaho.gov); NOT issued by the City of Sandpoint (confirmed on this jurisdiction's electrical-plumbing-permit-dopl entry)
    • Solar/Renewable Energy box must be checked on the DOPL Electrical Permit Worksheet, with total system cost entered as the Job Value Amount
    • Grid-Connected Renewable Energy systems require a plan-check permit number from DOPL FIRST (1-800-955-3044) before the installation permit can be purchased
    • Building Plan Check Fee (65% of the building permit fee) and Zoning Review (10% of the building permit fee, in addition to Plan Check) apply to the City-side building permit

    Required documents

    • RequiredCity of Sandpoint Building Permit Application
    • RequiredDOPL Homeowner or Contractor Electrical Permit Application and WorksheetSeparate state-issued application for the PV electrical work, with the Solar/Renewable Energy fee worksheet

    Fee schedule

    Fee typeAmountNotes
    City Building Permit — valuation $0-$2,000$64.76 for the first $1,300, plus $3.68 per additional $100City of Sandpoint Fee Schedule (eff. 10/1/2024, Res 24-061), 'Building Fee/Valuation' table; no dedicated solar line item
    City Building Permit — valuation $2,001-$25,000$90.52 for the first $2,000, plus $16.84 per additional $1,000
    City Building Permit — valuation $25,001-$50,000$477.84 for the first $25,000, plus $12.04 per additional $1,000
    City Building Permit — valuation $50,001-$100,000$778.84 for the first $50,000, plus $8.43 per additional $1,000
    City Building Permit — Minimum Building Permit Fee$180.54 (applies if the calculated valuation-based fee is lower)
    Building Plan Check Fee (standard, up to two reviews)65% of the building permit fee
    Zoning Review10% of the building permit fee, in addition to Building Plan Check
    State of Idaho DOPL Electrical Permit — Solar/Renewable Energy (up to $10,000 system cost)(Total cost of electrical system x 0.02) + $60DOPL Electrical Permit Worksheet (Fee Schedule), 'Other Installations including Solar/Renewable Energy' section — statewide formula, same as used elsewhere in Idaho where DOPL (not the local jurisdiction) issues electrical permits
    State of Idaho DOPL Electrical Permit — Solar/Renewable Energy ($10,001-$100,000 system cost)((Total cost of electrical system - $10,000) x 0.01) + $260
    State of Idaho DOPL Electrical Permit — Solar/Renewable Energy (over $100,001 system cost)((Total cost of electrical system - $100,000) x 0.005) + $1,160

    EV Charger / EVSE Permit

    Verified

    Required for installing an electric vehicle charging station (Level 2 or DC fast charger) within Sandpoint city limits. As with electrical work generally (see this jurisdiction's electrical-plumbing-permit-dopl entry), the electrical installation is a State of Idaho DOPL permit, not a City of Sandpoint permit — the City's own 'Permit Types' handout confirms Electrical Permits are issued through the State of Idaho Division of Building Safety (DBS), part of DOPL. DOPL's Electrical Permit Worksheet has no dedicated EV-charger/EVSE fee line; the installation is billed under the same 'Other Installations including Solar/Renewable Energy' cost-based tier documented in this file's solar-pv-permit entry, since that is DOPL's general bucket for installation types not separately itemized elsewhere on the worksheet. A separate City of Sandpoint Building Permit would only be required if the installation involves new structural work (e.g., a new carport or canopy) — a standalone circuit/charger-mount to an existing structure would not trigger the City's building permit process.

    Verified 2026-07-20 · Source

    Requirements

    • State of Idaho DOPL electrical permit required for the EV charger's electrical installation (dedicated circuit, any panel work) — purchased online at dbs.idaho.gov (redirects to dopl.idaho.gov); NOT issued by the City of Sandpoint
    • Homeowner permit available only for work the property owner personally performs on their own primary/secondary residence, not for rental or commercial use; otherwise a licensed electrical contractor must pull the permit
    • No dedicated 'EV Charger'/'EVSE' checkbox exists on the DOPL Electrical Permit Worksheet; the installation is entered under the 'Other Installations' cost-based fee tier, with the total cost of the electrical work entered as the Job Value Amount
    • A separate City of Sandpoint Building Permit (valuation-based, per the general Building Fee/Valuation table) would only apply if the EV charger installation includes new structural work (e.g., a new carport/canopy) — confirm with the City's Building department (208-263-3423) whether a given installation triggers this
    • Idaho state law (2023) prohibits local governments from mandating EV charging infrastructure in new construction and preempts local EV-infrastructure ordinances — the City of Sandpoint has no local EV-specific permitting mandate beyond the standard DOPL electrical permit

    Required documents

    • RequiredDOPL Homeowner or Contractor Electrical Permit ApplicationSame application referenced in this file's solar-pv-permit entry; must be accompanied by the DOPL Electrical Permit Worksheet (Fee Schedule) to calculate and transfer the total fee for the EV charger circuit under the 'Other Installations' tier

    Fee schedule

    Fee typeAmountNotes
    State of Idaho DOPL Electrical Permit — Other Installations (up to $10,000 system cost)(Total cost of electrical work x 0.02) + $60DOPL Electrical Permit Worksheet (Fee Schedule), 'Other Installations including Solar/Renewable Energy' section — same formula documented in this file's solar-pv-permit entry; no separate EV-charger line item exists, so an EV charger circuit is billed under this general tier
    State of Idaho DOPL Electrical Permit — Other Installations ($10,001-$100,000 system cost)((Total cost of electrical work - $10,000) x 0.01) + $260
    City of Sandpoint Building Permit (only if new structural work is involved, e.g. a new carport/canopy)Follows the general City Building Fee/Valuation table (e.g., $64.76 for the first $1,300 of valuation, plus $3.68 per additional $100; $180.54 minimum)Not applicable to a standalone EV charger circuit added to an existing structure; only triggered if new structural work accompanies the installation. No EV-specific fee line exists on the City's Fee Schedule.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-13.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandpoint building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    View current record →All versions →

    Permalink: /idaho/bonner-county/sandpoint/as-of/2026-07-04/

    Snapshot date: 2026-07-04

    Commit: b5eab4a

    Reproducible from PermitBase’s version-controlled dataset, commit b5eab4a.