Skip to main content
PermitBase

Middleton building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Middleton, Idaho.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
1103 W Main St, Middleton, ID 83644
Phone
(208) 585-3133
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • Request inspections through the CitizenServe online portal before 4:00 PM for next-business-day scheduling (per Middleton's electrical/plumbing/mechanical permit forms; confirm whether the same cutoff applies to building inspections by calling the inspection line at (208) 585-5805). (New Residential Building Permit)
  • Inspections must be requested through the CitizenServe portal before 4:00 PM for next-day scheduling (Electrical Permit)
  • Inspections must be requested through the CitizenServe portal before 4:00 PM for next-day scheduling (Solar PV Permit)
  • Inspections must be requested through the CitizenServe portal before 4:00 PM for next-day scheduling (EV Charger / EVSE Permit)
  • Same-day building inspections are not offered; inspection requests submitted before 4:00 PM in the CitizenServe portal are scheduled for the next business day. (Tenant Improvement (TI) Permit)

Inspection sequence

Applies to: New Commercial Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour

  2. 2

    Underground / Rough-In (Electrical, Mechanical, Plumbing)

    Trade rough-in inspections, requested separately by each trade contractor before walls/slab close

  3. 3

    Framing / Structural

    Structural building sections, fire-rated wall/floor-ceiling assemblies, and penetration firestopping per the approved plan set

  4. 4

    Final Building

    All work complete per approved plans; required before Certificate of Occupancy is issued

Applies to: New Residential Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing and rough-in trades complete, before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation installed per Idaho Energy Conservation Code before drywall

  4. 4

    Final

    All work complete per approved plans

Applies to: Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping

  2. 2

    Rough-In / Equipment

    HVAC equipment, ductwork, and gas lines before walls closed

  3. 3

    Final

    Equipment operational, venting and combustion air verified

Applies to: Solar PV Permit

  1. 1

    Framing/Structural

    Racking and roof-penetration/structural attachment inspection

  2. 2

    Rough Electrical

    Wiring installed, before walls closed, per the 2023 NEC

  3. 3

    Final

    All devices installed and operational; system energized and verified

Applies to: Tenant Improvement (TI) Permit

  1. 1

    Rough-In (Electrical, Mechanical, Plumbing)

    Trade rough-in inspections for any new wiring, ductwork, or piping, requested separately by each trade contractor before walls close

  2. 2

    Framing / Fire-Rated Assemblies

    Interior wall framing and any fire-rated assemblies or penetration firestopping per the approved plan set, if the scope involves interior demising-wall or corridor work

  3. 3

    Final Building

    All work complete per approved plans; a site inspection by Building, Fire, and (for food service) Southwest District Health is required before a Certificate of Occupancy is issued

Applies to: Accessory Structure Permit

  1. 1

    Foundation / Footings

    Before concrete pour, if applicable

  2. 2

    Final

    Structure complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Final

    All devices installed and operational per 2023 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Final

    Charger circuit installed and operational per 2023 NEC

Applies to: Plumbing Permit

  1. 1

    Underground / Rough-In

    Before concrete pour or wall closure — verify pipe slope, materials, cleanouts

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified

Re-inspection fees

New Residential Building PermitReinspection — Building, second notice of correction for same item · City Fee Schedule Res. 508-24
$75.00
Electrical PermitRequest inspection / re-inspection / technical service · City Fee Schedule Res. 526-25, Attachment B — Electrical Permit form (rev. 8/1/2024), item 13 Request inspection — re-inspections — technical service.
$65.00 minimum plus $65.00 per hour or portion thereof in excess of one hour, including travel to and from job location
Plumbing PermitRequest inspection / re-inspection / technical service · City Fee Schedule Res. 526-25, Attachment C — Plumbing Permit form (rev. 8/1/2024), item 9 Request Inspections — re-inspections — technical service.
$65.00 minimum plus $65.00 per hour or portion thereof in excess of one hour, including travel
Mechanical / HVAC PermitRequest inspection / re-inspection / technical service · City Fee Schedule Res. 526-25, Attachment D — Mechanical Permit form (rev. 8/1/2024), item 7 Request inspections — re-inspections — technical service.
$65.00 minimum plus $65.00 per hour or portion thereof in excess of one hour, including travel
EV Charger / EVSE PermitRequest inspection / re-inspection / technical service · City Fee Schedule Res. 526-25, Attachment B — Electrical Permit form (rev. 8/1/2024), item 13 Request inspection — re-inspections — technical service.
$65.00 minimum plus $65.00 per hour or portion thereof in excess of one hour, including travel to and from job location
New Commercial Building PermitReinspection — Building, second notice of correction for same item · City Fee Schedule Res. 508-24
$75.00
Tenant Improvement (TI) PermitReinspection — Building, second notice of correction for same item · City Fee Schedule Res. 508-24
$75.00

Middleton building permits

Get alerts for Middleton

We'll email you when Middleton's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.