This is PermitBase’s published record for Moscow as of 2026-08-25. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Moscow building permits

Verified

Moscow, Idaho — as published 2026-08-25.

Verified 2026-07-04 · Source

Codes adopted

The City of Moscow independently administers and issues its own building permits within Moscow city limits through its Building Safety Division, part of the Community Development Department — this is a distinct office from the Latah County Planning & Building Department (522 South Adams Street, Moscow, ID), confirmed by the City's own Homeowner's Guide to Construction Permits and Inspections, which lists 'Latah County Planning/Building, (208) 883-7220' as a separate entry in its Useful Telephone Numbers page, distinct from the City's own Community Development line. Source: City of Moscow Homeowner's Guide to Construction Permits and Inspections (Building Division, Justin Goodwin CBO), https://www.ci.moscow.id.us/DocumentCenter/View/21221/City-of-Moscow-Project-Process-PDF, page 19International Building Code (IBC), locally adopted and administered by the City of Moscow — specific edition year not published on the City's Construction Regulations index page as of 2026-07-04; the page lists 'International Building Code' as Chapter 01 of the City's adopted code chapters without stating the edition. Source: City of Moscow Construction Regulations page, https://www.ci.moscow.id.us/244/Construction-RegulationsInternational Residential Code (IRC), locally adopted and administered by the City of Moscow (Chapter 16 of the City's adopted code chapters); specific edition year not published on the Construction Regulations index page. Source: City of Moscow Construction Regulations pageUniform Plumbing Code (UPC), locally adopted (Chapter 02 of the City's adopted code chapters) — notably the Uniform Plumbing Code rather than the International Plumbing Code; specific edition year not published on the index page. Source: City of Moscow Construction Regulations pageNational Electrical Code (NEC), locally adopted (Chapter 03 of the City's adopted code chapters); specific edition year not published on the index page. Source: City of Moscow Construction Regulations pageInternational Fuel Gas Code (IFGC), locally adopted (Chapter 04 of the City's adopted code chapters). Source: City of Moscow Construction Regulations pageInternational Mechanical Code (IMC), locally adopted (Chapter 10 of the City's adopted code chapters). Source: City of Moscow Construction Regulations pageInternational Existing Building Code (IEBC), locally adopted (Chapter 12 of the City's adopted code chapters). Source: City of Moscow Construction Regulations pageInternational Property Maintenance Code (IPMC), locally adopted (Chapter 13 of the City's adopted code chapters). Source: City of Moscow Construction Regulations pageInternational Energy Conservation Code (IECC), locally adopted (Chapter 15 of the City's adopted code chapters); the City separately publishes an Energy Conservation Plan Review Supplement. Source: City of Moscow Construction Regulations page and Plan Review Information page, https://www.ci.moscow.id.us/256/Plan-Review-InformationIdaho Building Code Act (Idaho Code Title 39, Chapter 41) makes building code standards a matter of statewide concern; local governments that issue building permits and perform code enforcement (such as the City of Moscow) must adopt the International Building Code and Idaho Residential Code as amended by the Idaho Building Code Board through negotiated rulemaking. Source: Idaho Legislature, Idaho Code Title 39 Chapter 41 (39-4116), https://legislature.idaho.gov/statutesrules/idstat/title39/t39ch41/The City of Moscow's Construction Regulations index page (ci.moscow.id.us/244/Construction-Regulations) lists adopted code chapters by title only (Building, Plumbing, Electrical, Fuel Gas, Mechanical, Existing Building, Property Maintenance, Energy Conservation, Residential) without publishing the specific edition years for any of them. Specific edition years are omitted here rather than assumed to match a neighboring jurisdiction's editions; the City's Municipal Code chapter text would state the exact editions and local amendment sections, so check there or with the Building Department before designing to a particular edition.

Permit types & fees

Residential Building Permit (New Single-Family Dwelling / Addition)

Verified

Required for new one- and two-family dwelling construction and additions within Moscow city limits, administered by the City of Moscow Building Safety Division. Building Permit Fees are based on ICC Building Valuations (February issue of the Building Safety Journal) on a bracketed fee table, with a separate Plan Review Fee for projects valued over $10,000.

Verified 2026-07-04 · Source

Requirements

  • Site/plot plan required with all building permit applications (except simple re-roof permits), showing property lines, all structures, street, driveway, sidewalk, and location of proposed work
  • Floor plans showing all door/window sizes and locations, room dimensions and uses
  • For new dwellings/additions: foundation plan, floor framing plan, roof framing plan, electrical plan (meter, switch, outlet, and light locations), and two sets of wet-stamped structural/truss calculations if required
  • Two complete paper sets of plans (or one electronic set, followed by two stamped paper sets after electronic approval) submitted to the Community Development Office
  • Contractor must be registered with the State of Idaho; name and registration number required on the application
  • Plan Review Fee (65% of Building Permit Fee, or 40% for duplicate plans) applies to projects over $10,000 in valuation; a $500 Plan Review Deposit is credited toward this fee

Required documents

  • RequiredBuilding Permit ApplicationCity of Moscow application specifying scope of work, floor area, and contact for plan corrections; submitted to the Community Development Office, 504 S. Washington Street
  • RequiredSite/Plot PlanOverhead view of the entire property showing property lines, structures, street, driveway, sidewalk, and proposed work location
  • RequiredConstruction Drawings (Floor, Foundation, Framing, Roof, Electrical Plans)Required for new dwellings and additions; complexity scales with project size

Fee schedule

Fee typeAmountNotes
Total Valuation $1.00 to $2,000 (Fee Amount for First $500)$27.50Plus $3.50 for each additional $100 or fraction thereof to and including $2,000. City of Moscow FY2026 Fee Schedule, Schedule C, page 5
Total Valuation $2,001 to $25,000 (Fee Amount for First $2,000)$79.50Plus $14.50 for each additional $1,000 or fraction thereof, to and including $25,000. City of Moscow FY2026 Fee Schedule
Total Valuation $25,001 to $50,000 (Fee Amount for First $25,000)$413.00Plus $10.50 for each additional $1,000 or fraction thereof, to and including $50,000. City of Moscow FY2026 Fee Schedule
Total Valuation $50,001 to $100,000 (Fee Amount for First $50,000)$675.50Plus $7.50 for each additional $1,000 or fraction thereof to and including $100,000. City of Moscow FY2026 Fee Schedule
Total Valuation $100,001 and up (Fee Amount for First $100,000)$1,050.50Plus $6.00 for each additional $1,000 or fraction thereof. City of Moscow FY2026 Fee Schedule
Permit Issuance Fee$32.75Charged with all permits except flat-fee, Commercial, and Institutional permits. City of Moscow FY2026 Fee Schedule, page 6
Decks (per square foot addition to base ICC valuation)$15.75Per square foot. City of Moscow FY2026 Fee Schedule, page 5
Plan Review Fee (projects over $10,000 in valuation)65% of the Building Permit Fee (40% for duplicate plans)City of Moscow FY2026 Fee Schedule, page 6
Plan Review Deposit$500.00Credited toward the Plan Review Fee. City of Moscow FY2026 Fee Schedule, page 6
No Permit (failure to obtain permit before commencing work)Fee equal to the Building Permit FeeCity of Moscow FY2026 Fee Schedule, page 6

Electrical Permit

Verified

Required for electrical installation, alteration, service change-out, or new circuit work within Moscow city limits, administered by the City of Moscow Building Safety Division under the locally adopted National Electrical Code (NEC).

Verified 2026-07-04 · Source

Requirements

  • Electrical permit required for service change-outs, circuit extensions/additions, and new residential electrical service and wiring
  • New residential (single- and two-family only) electrical service and wiring is fee-assessed per square foot
  • Commercial electrical work (including multi-family dwellings, fraternities/sororities, and mobile park distribution wiring/pedestals) is fee-assessed on a contract-price bracket table
  • Permit Issuance Fee charged with all permits except flat-fee, Commercial, and Institutional permits

Required documents

  • RequiredElectrical Permit ApplicationSubmitted to the City of Moscow Community Development Office, 504 S. Washington Street

Fee schedule

Fee typeAmountNotes
Electrical Service Change Out$73.75City of Moscow FY2026 Fee Schedule, Schedule C, page 7
Extension or Addition of up to 6 Circuits$48.00City of Moscow FY2026 Fee Schedule
Extension or Addition of More Than 6 Circuits$73.75City of Moscow FY2026 Fee Schedule
Electric Furnaces, Heat Pumps, Air Conditioners, Unit Space Heaters, Ventilation Fans$8.75Per appliance. City of Moscow FY2026 Fee Schedule
Domestic Water Pumps$36.25City of Moscow FY2026 Fee Schedule
Commercial Contract Price $0 - $2,000$31.75Plus 4% of contract price up to $2,000. Includes multi-family dwellings, fraternities/sororities, distribution wiring/pedestals for mobile parks. City of Moscow FY2026 Fee Schedule
Commercial Contract Price $2,001 - $10,000$117.25Plus 3% of contract price over $2,000. City of Moscow FY2026 Fee Schedule
Commercial Contract Price $10,001 - $100,000$374.75Plus 2% of contract price over $10,000. City of Moscow FY2026 Fee Schedule
Commercial Contract Price Over $100,001$2,303.00Plus 1% of contract price over $100,000. City of Moscow FY2026 Fee Schedule
Permit Issuance Fee$32.75City of Moscow FY2026 Fee Schedule, page 8
Temporary Service$23.25City of Moscow FY2026 Fee Schedule, page 8
New Dwelling Unit Electrical Service and Wiring (Single/Two Family)$0.13Per square foot. City of Moscow FY2026 Fee Schedule, page 8
Electric Furnaces and Unit Space Heaters (new residential)$6.25Per appliance. City of Moscow FY2026 Fee Schedule, page 8

Gas / Mechanical Permit

Verified

Required for gas and mechanical/HVAC installation, alteration, or repair within Moscow city limits, administered by the City of Moscow Building Safety Division. Commercial gas/mechanical work is fee-assessed on the same contract-price bracket table as electrical; residential gas-fueled appliance installs are billed by BTU rating.

Verified 2026-07-04 · Source

Requirements

  • Gas/Mechanical permit required for air handlers, appliance vent installation/relocation/replacement, gas piping to fixtures/appliances, heating/refrigeration/cooling repairs and alterations, ventilation fans, and wood/pellet stoves
  • Residential installs of gas-fueled furnaces, water heaters, boilers, fireplaces, and unit/space heaters are billed per appliance by BTU rating (0-180 thousand BTU vs. 181+ thousand BTU)
  • Commercial gas/mechanical work (including multi-family dwellings, fraternities/sororities) is fee-assessed on the contract-price bracket table

Required documents

  • RequiredGas/Mechanical Permit ApplicationSubmitted to the City of Moscow Community Development Office, 504 S. Washington Street

Fee schedule

Fee typeAmountNotes
Commercial Contract Price $0 - $2,000$31.75Plus 4% of contract price up to $2,000. City of Moscow FY2026 Fee Schedule, Schedule C, page 9
Commercial Contract Price $2,001 - $10,000$117.25Plus 3% of contract price over $2,000. City of Moscow FY2026 Fee Schedule
Commercial Contract Price $10,001 - $100,000$374.75Plus 2% of contract price over $10,000. City of Moscow FY2026 Fee Schedule
Commercial Contract Price Over $100,000$2,303.00Plus 1% of contract price over $100,000. City of Moscow FY2026 Fee Schedule
Air Handlers$20.25Per each air-handling unit, including ducts attached thereto. City of Moscow FY2026 Fee Schedule
Installation, Relocation or Replacement of Appliance Vent (not included in an appliance permit)$12.75Each. City of Moscow FY2026 Fee Schedule
Gas Piping - Fixture or Appliance Outlets$10.50Per outlet. City of Moscow FY2026 Fee Schedule
Permit Issuance Fee$32.75City of Moscow FY2026 Fee Schedule
Repair, Alteration, or Addition to Heating/Refrigeration/Cooling Appliance$26.75Each. City of Moscow FY2026 Fee Schedule
Ventilation Fan Connected to a Single Duct$12.75Each. City of Moscow FY2026 Fee Schedule
Wood / Pellet Stoves$23.25Each. City of Moscow FY2026 Fee Schedule
Residential Gas-Fueled Furnace/Water Heater/Boiler/Fireplace/Unit or Space Heater, 0-180 Thousand BTU$39.25Per appliance. City of Moscow FY2026 Fee Schedule
Residential Gas-Fueled Furnace/Water Heater/Boiler/Fireplace/Unit or Space Heater, 181+ Thousand BTU$49.00Per appliance. City of Moscow FY2026 Fee Schedule

Electric Vehicle (EV) Charger Permit

Verified

Moscow publishes no distinct EV-charger permit type or fee line — confirmed against the Building Safety Division page and the City of Moscow FY2026 Fee Schedule, neither of which contains an EV-charger/EVSE entry. A new circuit or outlet installed to serve a residential EV charger is fee-assessed under the general Electrical Permit's 'Extension or Addition of Circuits' category (a new dedicated EV circuit is typically one circuit, billed at the 'up to 6 circuits' rate); a panel/service upgrade for a higher-amperage Level 2 charger would instead fall under the Electrical Service Change Out fee.

Verified 2026-07-20 · Source

Requirements

  • A new circuit or outlet for an EV charger requires an Electrical Permit under the City's locally adopted National Electrical Code (NEC)
  • Fee-assessed under the 'Extension or Addition of up to 6 Circuits' category for a typical single dedicated EV charger circuit
  • A panel/service upgrade (e.g., to support a Level 2 charger) is instead fee-assessed under the Electrical Service Change Out category
  • Submitted to the City of Moscow Community Development Office, 504 S. Washington Street
  • Permit Issuance Fee charged in addition to the circuit/service fee, except for flat-fee, Commercial, and Institutional permits

Required documents

  • RequiredElectrical Permit ApplicationSubmitted to the City of Moscow Community Development Office; describe scope as new circuit/outlet or service change-out for EV charging

Fee schedule

Fee typeAmountNotes
Extension or Addition of up to 6 Circuits (applies to a typical new EV charger circuit)$48.00City of Moscow FY2026 Fee Schedule, Schedule C — no distinct EV-charger fee line exists; this is the general fee category a new dedicated circuit falls under
Electrical Service Change Out (applies if a panel/service upgrade is needed for a Level 2 charger)$73.75City of Moscow FY2026 Fee Schedule, Schedule C, page 7
Permit Issuance Fee$32.75City of Moscow FY2026 Fee Schedule, page 8

Demolition Permit

Verified

Required for demolition of structures within Moscow city limits, administered by the City of Moscow Building Safety Division, with distinct flat fees for Simple (non-structural alterations) versus Complex (structural or complete building demolition) demolitions.

Verified 2026-07-04 · Source

Requirements

  • Simple Demolition applies to non-structural alterations
  • Complex Demolition applies to structural alterations or complete building demolition

Required documents

  • RequiredDemolition Permit ApplicationSubmitted to the City of Moscow Community Development Office, 504 S. Washington Street

Fee schedule

Fee typeAmountNotes
Simple Demolition (Non-Structural Alterations)$69.50City of Moscow FY2026 Fee Schedule, Schedule C, page 6
Complex Demolition (Structural or Complete Building Demolition)$295.50City of Moscow FY2026 Fee Schedule

Re-Roofing Permit

Verified

Required for re-roofing of residential structures (up to 4 units) within Moscow city limits; commercial re-roofs require a full Building Permit rather than this flat-fee category.

Verified 2026-07-04 · Source

Requirements

  • Residential re-roofing (structures up to 4 units) uses the flat Re-Roofing Permit fee
  • Commercial re-roofs require a full Building Permit (valuation-based fee table applies instead)

Required documents

  • RequiredRe-Roofing Permit ApplicationSubmitted to the City of Moscow Community Development Office; simple re-roof permits are exempt from the site-plan requirement per the Homeowner's Guide

Fee schedule

Fee typeAmountNotes
Re-Roofing Permit (Residential Structures up to 4 Units)$71.50Commercial re-roofs require full Building Permit. City of Moscow FY2026 Fee Schedule, Schedule C, page 6
Permit Issuance Fee$32.75City of Moscow FY2026 Fee Schedule

Residential Solar Photovoltaic (PV) Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems within Moscow city limits. Moscow has no dedicated solar/PV permit application or fee line — solar installations are billed under the City's standard valuation-based Building Permit fee table (for the array/mounting/structural work) and the standard Electrical Permit fee table (for the electrical interconnection), administered by the Building Safety Division under the locally adopted IBC/IRC and NEC.

Verified 2026-07-20 · Source

Requirements

  • Building Permit required for the array mounting/structural work, submitted to the Community Development Office, 504 S. Washington Street, or online via PermitTrax
  • Electrical Permit required for the PV system wiring and interconnection, under the locally adopted National Electrical Code (NEC)
  • Site/plot plan required showing the location of the proposed array on the structure or lot
  • Contractor must be registered with the State of Idaho; registration number required on the application
  • No dedicated Solar Permit Application or expedited solar-specific review track is published by the City of Moscow as of 2026-07-19 — solar/PV work is processed as a standard Building + Electrical Permit combination

Required documents

  • RequiredBuilding Permit ApplicationCity of Moscow application; used for solar array/mounting/structural scope since there is no dedicated solar application
  • RequiredElectrical Permit ApplicationCovers the PV system wiring and utility interconnection
  • RequiredSite/Plot PlanShows the array location on the structure or lot

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based)Per the Total Valuation bracket table (e.g., $79.50 for $2,001-$25,000, plus $14.50 per additional $1,000)No solar-specific fee line found; billed under the same ICC-valuation Building Permit table as other construction. City of Moscow FY2026 Fee Schedule, Schedule C, page 5
Electrical Permit Fee (interconnection wiring)Per the Electrical Permit fee table (e.g., Extension/Addition of up to 6 Circuits $48.00, or Commercial contract-price bracket for larger systems)No solar-specific electrical fee line found. City of Moscow FY2026 Fee Schedule, Schedule C, page 7
Permit Issuance Fee$32.75Charged with all permits except flat-fee, Commercial, and Institutional permits. City of Moscow FY2026 Fee Schedule
Plan Review Fee (projects over $10,000 in valuation)65% of the Building Permit Fee (40% for duplicate plans)Applies if total project valuation exceeds $10,000. City of Moscow FY2026 Fee Schedule, page 6

Commercial Building Permit (New Construction)

Verified

Required for new commercial and multi-family building construction within Moscow city limits. There is no separate 'commercial permit' application — Moscow uses the same city-wide Permit Application (a checkbox distinguishes 'Commercial/Multi-Family Residential' from 'Residential (1 & 2 Family)') and the same ICC-valuation-based Building Permit Fee table used for residential permits, but requires larger plan sheets, additional site/civil/landscape/accessibility/energy documentation per the City's Minimum Plan Submittal Guidelines for Multi-Family and Commercial Plans, and carries its own, longer plan-review timeline ('Commercial New', under 15 business days for first review) on the City's Permit Processing Time Frames table.

Verified 2026-08-02 · Source

Requirements

  • Permit Application (city-wide Building Safety form) with 'Commercial/Multi-Family Residential' project type checked, nature of work marked 'New', and trade-contractor registration numbers listed
  • Plans submitted electronically or as five (5) sets of paper plans, on sheets 18"x24" minimum (24"x36" recommended) — larger than the 11"x17" minimum required for One & Two Family projects
  • Plans signed by the preparer; wet-stamped and signed by a licensed architect or engineer registered in Idaho when required
  • Site/civil plans: property lines and setbacks, utility/sewer/fire-hydrant locations, a parking plan with tabulation of existing/proposed/required spaces, and dimensions of all architectural projections
  • General notes on the plans covering occupancy classification, construction type, zoning district, parcel number/legal description, applicable codes, building height, and whether fire sprinklers will be installed
  • Structural plans and, when deviating from conventional code provisions, wet-stamped structural calculations
  • Accessibility plans showing compliance for accessible/adaptable units, accessible parking, accessible routes and building entrances, and accessible interior features (restrooms, drinking fountains, counters)
  • A complete, dimensioned landscape design (required for all new Multi-Family/Commercial construction)
  • An International Energy Conservation Code (IECC) compliance checklist with energy calculations
  • Stormwater management plan required when new impervious surface totals 5,000 sq ft or more
  • A geotechnical report may be required; shoring plans/calculations required for excavations over 4 feet deep or that remove lateral support from an adjacent structure, property, or right-of-way
  • Separate permits required for electrical, mechanical, plumbing, fire sprinklers (State of Idaho Fire Marshal approved), fire alarm system, grading, demolition, retaining walls, right-of-way use, driveway aprons, floodplain development, and signs
  • Contractor must be registered with the State of Idaho; registration number required on the application
  • Certificate of Occupancy (with Life Safety Inspections) required before the completed building may be occupied

Required documents

  • RequiredBuilding Permit Application (Full Permit)City-wide Community Development permit application; 'Commercial/Multi-Family Residential' project-type box checked, submitted to 504 S. Washington Street or online via PermitTrax
  • RequiredSite/Civil PlansProperty lines, setbacks, utilities, parking tabulation, fire hydrant locations, and public improvements, per the Minimum Plan Submittal Guidelines for Multi-Family and Commercial Plans
  • RequiredStructural, Floor, and Exterior Elevation PlansDimensioned plans for each floor/roof level; cross-sections in at least two orthogonal directions; wet-stamped structural calculations if deviating from conventional code provisions
  • RequiredLandscape PlanComplete, dimensioned landscape design; required for all new Multi-Family/Commercial construction
  • RequiredIECC Energy Conservation ChecklistVerifies compliance with the locally adopted International Energy Conservation Code; computer or point-method calculations
  • OptionalStormwater Management PlanRequired when the project creates 5,000 sq ft or more of new impervious surface; must show drainage patterns, drainage devices, and erosion/sediment control

Fee schedule

Fee typeAmountNotes
Total Valuation $1.00 to $2,000 (Fee Amount for First $500)$27.50Same ICC-valuation-based Building Permit Fee table applies to both residential and commercial construction. Plus $3.50 for each additional $100 or fraction thereof to and including $2,000. City of Moscow FY2026 Fee Schedule, Schedule C, page 5
Total Valuation $2,001 to $25,000 (Fee Amount for First $2,000)$79.50Plus $14.50 for each additional $1,000 or fraction thereof, to and including $25,000. City of Moscow FY2026 Fee Schedule
Total Valuation $25,001 to $50,000 (Fee Amount for First $25,000)$413.00Plus $10.50 for each additional $1,000 or fraction thereof, to and including $50,000. City of Moscow FY2026 Fee Schedule
Total Valuation $50,001 to $100,000 (Fee Amount for First $50,000)$675.50Plus $7.50 for each additional $1,000 or fraction thereof to and including $100,000. City of Moscow FY2026 Fee Schedule
Total Valuation $100,001 and up (Fee Amount for First $100,000)$1,050.50Plus $6.00 for each additional $1,000 or fraction thereof. City of Moscow FY2026 Fee Schedule
Permit Issuance FeeNot charged on Commercial permitsThe FY2026 Fee Schedule states the $32.75 Permit Issuance Fee is 'Charged With all Permits Except Flat Fee and Commercial and Institutional Permits' — Commercial building permits are exempt from this separate line item. City of Moscow FY2026 Fee Schedule, Schedule C, page 6
Plan Review Fee (projects over $10,000 in valuation, excluding Commercial Windows, Doors and Roofs)65% of the Building Permit Fee (40% for duplicate plans)City of Moscow FY2026 Fee Schedule, page 6
Plan Review Deposit$500.00Credited toward the Plan Review Fee. City of Moscow FY2026 Fee Schedule, page 6
Certificate of Occupancy (Existing Commercial Buildings, Includes Life Safety Inspections)$79.00Also printed as 'Occupancy Permit $79.00' directly on the City's Change of Occupancy Application form; required before a new or altered commercial space may be occupied. City of Moscow FY2026 Fee Schedule, Schedule C, page 6
Multi-Family/Commercial Site Plan Review or Parking Lot Development/Modification Review$148.50Plus $5.90 per parking space. City of Moscow FY2026 Fee Schedule, Schedule C, page 11
Engineering Inspection (Subdivision, PUD, Commercial, and Multi-Family Residential)1.25% of Public Improvement Construction Cost as Verified by CityCity of Moscow FY2026 Fee Schedule, Schedule C, page 8
Fire Sprinkler Inspection and Plan Review (if fire sprinklers are installed)$142.75Plus $2.00 per sprinkler head. City of Moscow FY2026 Fee Schedule, Schedule C, page 12

Commercial Tenant Improvement / Alteration Permit

Verified

Moscow does not publish a distinct 'Tenant Improvement' permit product, application, or fee line — confirmed against the City's Permit Application (a single form used for all project types), the FY2026 Fee Schedule, and the Minimum Plan Submittal Guidelines for Multi-Family and Commercial Plans. TI/remodel work inside an existing commercial building is processed as a standard Building Permit (Nature of Work: 'Remodel'), billed on the same ICC-valuation-based fee table as new construction, and classified for review-timeline purposes as either 'Commercial Non-Structural Alteration' or 'Commercial Structural Alteration' depending on scope. If the tenant or the use of the space is changing, a separate Change of Occupancy Application (with its own $79.00 Occupancy Permit fee) is also required.

Verified 2026-08-02 · Source

Requirements

  • Building Permit Application (city-wide form) with 'Commercial/Multi-Family Residential' project type checked and 'Remodel' checked under Nature of Work
  • Floor plans identifying the existing and intended use of every affected room, with door/window schedules and a legend distinguishing existing from new construction
  • General notes addressing occupancy classification, construction type, applicable codes, and whether fire sprinklers are affected
  • Structural plans and wet-stamped structural calculations required only when the scope includes structural alterations (e.g., removal or modification of load-bearing walls or other structural elements)
  • Accessibility-plan compliance (accessible routes, restrooms, and building features) applies to commercial alteration projects per the Minimum Plan Submittal Guidelines for Multi-Family and Commercial Plans
  • If the tenant or the permitted use of the space is changing, a separate Change of Occupancy Application must be submitted and approved by Zoning, Building, and Fire before the space may legally be occupied under the new use
  • Fire Alarm/Sprinkler System permits are separate (State of Idaho Fire Marshal approved) if the TI scope affects fire-protection systems
  • Contractor must be registered with the State of Idaho; registration number required on the application

Required documents

  • RequiredBuilding Permit Application (Full Permit)Same city-wide application used for new commercial construction, with 'Remodel' checked as the Nature of Work
  • OptionalChange of Occupancy ApplicationRequired only if the tenant or the use/occupancy classification of the space is changing; requires Zoning, Building, and Fire sign-off before issuance; carries its own $79.00 Occupancy Permit fee
  • RequiredFloor Plans (Existing and Proposed)Identifies existing vs. new construction and the existing/intended use of every affected room
  • OptionalStructural Plans/CalculationsRequired only if the scope includes structural alterations; must be wet-stamped by a licensed architect or engineer registered in Idaho

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based)Per the Total Valuation bracket table (e.g., $79.50 for $2,001-$25,000, plus $14.50 per additional $1,000)Same ICC-valuation-based Building Permit Fee table used for new commercial construction and residential permits; no separate TI fee line exists. City of Moscow FY2026 Fee Schedule, Schedule C, page 5
Permit Issuance FeeNot charged on Commercial permitsCity of Moscow FY2026 Fee Schedule, Schedule C, page 6
Plan Review Fee (projects over $10,000 in valuation, excluding Commercial Windows, Doors and Roofs)65% of the Building Permit Fee (40% for duplicate plans)City of Moscow FY2026 Fee Schedule, page 6
Occupancy Permit / Certificate of Occupancy (Existing Commercial Buildings, Includes Life Safety Inspections)$79.00Confirmed both in the FY2026 Fee Schedule, Schedule C, page 6, and printed directly on the City's Change of Occupancy Application form ('Occupancy Permit $79.00'); applies when the tenant or use of an existing commercial building changes

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Moscow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-08-02)Later version (2026-09-02) →View current record →All versions →

Permalink: /idaho/latah-county/moscow/as-of/2026-08-25/

Snapshot date: 2026-08-25

Commit: 4e9b2b0

Reproducible from PermitBase’s version-controlled dataset, commit 4e9b2b0.