Skip to main content
PermitBase

You are viewing the permanent link for the record currently in effect, published 2026-07-07.

Malad City building permits

Malad City, Idaho — as published 2026-07-07.

Reviewed 2026-07-08 · Source

Codes adopted

2018 International Building Code (IBC), as adopted by the State of Idaho / Idaho Building Code Board, with any amendments made through the negotiated rulemaking process2020 Idaho Residential Code (based on the 2018 International Residential Code, amended by the Idaho Building Code Board)2020 Idaho Energy Conservation Code (based on the 2018 International Energy Conservation Code, amended by the Idaho Building Code Board)2018 Idaho Existing Building Code (based on the 2018 International Existing Building Code, amended by the Idaho Building Code Board)Malad City Ordinance No. 484 (adopted December 9, 2020) — the ordinance that formally adopts the above codes as the official building codes of the City of Malad

Permit types & fees

Residential Building Permit (New Construction / Addition / Accessory)

Required for new single-family residential construction, additions, and accessory structures within Malad City limits. Issued by the City of Malad under Ordinance No. 484, which adopts the 2018 IBC, 2020 Idaho Residential Code, 2020 Idaho Energy Conservation Code, and 2018 Idaho Existing Building Code as the City's official building codes. Architect and engineering drawings are required with every application.

Reviewed 2026-07-08 · Source

Requirements

  • Architect & engineering drawings are required for all residential permit applications (stated on the application form itself)
  • Applicant must state Idaho Contractor's Number or claim an exemption per Idaho Code 54-5209 / 54-5205
  • Class of work must be identified: New, Addition, or Accessory
  • Type of structure (masonry, wood frame, log, metal) and square footage by floor/area must be itemized on the application
  • Wood stove/fireplace installation must be disclosed on the application
  • Water and sewer approval are required sign-offs on the same permit form before final approval

Required documents

  • RequiredPermit Application Form for Residential Construction (City of Malad)Official City of Malad residential building permit application; requires owner, contractor, structure type, and square-footage-by-area detail
  • RequiredArchitect & Engineering DrawingsRequired for every residential submission per the application form header
  • RequiredIdaho Contractor Registration Number (or stated exemption)Per Idaho Code 54-5209 / 54-5205, contractor's registration number or claimed exemption must be provided

Fee schedule

Fee typeAmountNotes
Residential Building Permit FeeDetermined case-by-case based on project valuation and square footage; entered manually on the permit application by the City ("Building Permit Fee ____" / "Approved / Disapproved" sign-off by the Building Inspector and City Superintendent)No standalone published valuation-based fee table (e.g., a Table 1-A) could be located on the City of Malad website, in Malad City Council budget documents, in Ordinance 484, or in Oneida County's published Planning & Zoning fee schedule (which covers only P&Z land-use fees, not building permits). The City's FY2023-24 budget shows a dedicated "Licenses & Permits" General Fund revenue line ($13,500 projected) and a dedicated "Building Inspector" expense line ($35,000 projected), confirming the City independently budgets for and collects building permit revenue, but does not itemize a per-project fee table. Idaho DOPL's fee tables apply only to jurisdictions where the state administers permitting by default (i.e., where no local government has opted in) — Malad has opted in via Ordinance 484, so the state fee table is not the applicable schedule here. Applicants should confirm the exact fee with the City at (208) 766-4160 before applying. 2026-07-23 re-chase (new avenues, still no fee table found): checked the City's live Documents & Forms and Licenses & Permits pages (no new PDFs beyond those already cited), the Services and City Government pages (no fee-schedule link), 10 months of City Council agendas/minutes Aug. 2025-Jun. 2026 including the Aug. 13, 2025 and Sept. 3, 2025 FY2025-26 budget-adoption meetings (no fee-resolution or building-permit-fee line item mentioned in any), confirmed Malad's code is not hosted on Sterling Codifiers, Municode, or American Legal Publishing (no codified fee appendix exists to check), and confirmed the Wayback Machine holds only one archived snapshot of the Licenses & Permits page (Dec. 11, 2023), matching current content with no fee table. No new recovery avenue remains short of a direct call to (208) 766-4160; gap persists.

Solar PV Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems within Malad City limits. The structural/racking scope is permitted by the City of Malad under Ordinance No. 484 (the same case-by-case-fee building permit process used for other residential/commercial construction); the electrical interconnection is separately permitted and inspected by the State of Idaho Division of Occupational and Professional Licenses (DOPL), since Malad City has not independently certified its own electrical program.

Verified 2026-07-20 · Source

Requirements

  • Structural/racking mounting work requires a City of Malad building permit application under Ordinance No. 484, with architect & engineering drawings required per the City's standard residential/commercial permit application requirements
  • Electrical interconnection (wiring, inverter, grid tie-in) requires a separate State of Idaho electrical permit issued by DOPL, not the City — consistent with Malad having no independently certified local electrical program (the City's own building permit application forms contain no electrical-fee schedule of their own)
  • Grid-connected renewable energy systems require a State plan-check permit number prior to purchasing the State electrical installation permit, per DOPL's own homeowner electrical permit process
  • Applicant must state an Idaho Contractor's Number or claim an exemption per Idaho Code 54-5209 / 54-5205 on the City building permit application

Required documents

  • RequiredPermit Application Form for Residential Construction (City of Malad)City of Malad building permit application for the structural/racking mounting scope
  • RequiredArchitect & Engineering DrawingsRequired for every residential submission per the City's application form header
  • RequiredState of Idaho Electrical Permit Application (Homeowner or Contractor)Separate application filed with DOPL (dopl.idaho.gov) for the electrical/interconnection portion of the solar installation

Fee schedule

Fee typeAmountNotes
City Building Permit Fee (structural/racking scope)No standalone published valuation-based fee table exists for Malad City building permits of any kind, including solar — determined case-by-case by the City (Building Inspector / City Superintendent) and entered manually on the application, consistent with the general residential-building-permit entry in this file. Confirm the exact fee with the City at (208) 766-4160 before applying.
State of Idaho Electrical Permit — grid-connected renewable energy (electrical/interconnection scope)Up to $10,000 system cost: (cost x 0.02) + $60. $10,001-$100,000: ((cost - $10,000) x 0.01) + $260. Over $100,001: ((cost - $100,000) x 0.005) + $1,160Idaho DOPL Electrical Permit Worksheet (Homeowner), 'Other Installations including Solar/Renewable Energy' table, revised 8/17/2022 — the same statewide fee formula documented for other Idaho jurisdictions in this corpus (e.g., Ketchum) that lack their own certified electrical program. Grid-connected systems additionally require a State plan-check permit number before the installation permit can be purchased.

EV Charger / EVSE Permit

Verified

Installing a Level 1/Level 2 EV charging circuit in Malad City is purely electrical work. Because Malad City has not independently certified its own electrical program (the same situation documented in this file's solar-pv-permit entry), the electrical permit is issued directly by the State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City — no separate City permit applies unless the installation also involves structural/panel-enclosure work. No EV-charger-specific line item exists on DOPL's published fee worksheet; a charger circuit added to an existing home is billed under DOPL's general 'Existing Residence' branch-circuit fee.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required from the State of Idaho DOPL for the EV charger circuit/panel work — obtained via dbs.idaho.gov (all permits purchased online as of January 1, 2023)
  • Homeowners performing their own work on a primary/secondary residence may use DOPL's Homeowner Permit process; otherwise a licensed electrical contractor must pull the permit
  • No City of Malad building permit applies to a stand-alone EV charger circuit with no structural scope; if the installation is part of a larger project involving new construction or an addition, the City's residential-building-permit process under Ordinance No. 484 would also apply to that structural scope
  • All work must be inspected by DOPL's assigned state trade inspector for the Malad City area

Required documents

  • RequiredState of Idaho DOPL Electrical Permit Application (Homeowner or Contractor)Filed online at dbs.idaho.gov; no separate EV-charger-specific form exists

Fee schedule

Fee typeAmountNotes
DOPL Existing Residence — branch circuit addition$65.00 base fee (includes one circuit) plus $10.00 per additional branch circuit, up to the maximum of the corresponding square footage of the buildingIdaho DOPL Electrical Permit Worksheet (Homeowner), 'Existing Residence' category, revised 8/17/2022 — the applicable category for a typical EV charger circuit/subpanel added to an existing home; no EV-specific line item exists on the worksheet.
DOPL New Single Family Dwelling (if bundled with new construction)$130 (up to 1,500 sq ft) to $325 + $65 per additional 1,000 sq ft (over 4,500 sq ft), based on total living spaceIdaho DOPL Electrical Permit Worksheet — applies only if the EV charger circuit is part of a new single-family dwelling's electrical scope, not a stand-alone retrofit

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Malad City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →

Permalink: /idaho/oneida-county/malad/as-of/2026-07-07/

Snapshot date: 2026-07-07

Commit: fba9b32

Reproducible from PermitBase’s version-controlled dataset, commit fba9b32.