Inspection sequence, scheduling, and re-inspection fees for building permits in Great Falls, Montana.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
Civic Center, 2 Park Drive South, Room 112, P.O. Box 5021, Great Falls, MT 59403-5021
Phone
(406) 455-8430
Office hours
Mon-Fri 8:00 AM - 5:00 PM

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour, per geotechnical report and structural plans

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in before walls closed; separate trade permits required

  4. 4

    Blower Door Test

    Required for new construction prior to Certificate of Occupancy; must be performed by an approved third party

  5. 5

    Final

    All work complete, boulevard landscaping and driveways/sidewalks complete, Certificate of Occupancy issued

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing before wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in — separate trade permits required

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Fire Sprinkler / Alarm Permit

  1. 1

    Acceptance Test -- Fire Sprinkler

    Great Falls Fire Rescue verifies the installed sprinkler system; billed per inspection, minimum 3 inspections for systems with 100 heads or less

  2. 2

    Acceptance Test -- Fire Alarm

    Great Falls Fire Rescue verifies the installed alarm system; billed per inspection, minimum 2 inspections for 25,000 sq ft or less

  3. 3

    Acceptance Test -- Kitchen Hood / Suppression System

    Great Falls Fire Rescue verifies the installed hood or special suppression system; billed per inspection, minimum 1 inspection per project

Applies to: Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping

  2. 2

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed

  3. 3

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected, no leaks, proper venting

Applies to: Residential Addition / Alteration / Remodel Permit

  1. 1

    Framing / Structural

    After framing complete, before wall cover

  2. 2

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in — separate trade permits required

  3. 3

    Final

    All work complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    All devices installed, panel labeled, service energized

Applies to: Residential Rooftop Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, roof penetration sealing, and electrical interconnection verified

Applies to: Sign Permit

  1. 1

    Sign Electrical Inspection

    Required only if the sign includes electrical work outside the cabinet; performed under a separate Electrical Permit before sign placement

  2. 2

    Final Sign Inspection

    Verifies sign structure, placement, and (for freestanding signs/billboards) footings match the approved plans

Re-inspection fees

Residential Building Permit (New Construction)Re-inspection Fee · City of Great Falls Homeowner's Electrical/Plumbing/Mechanical Permit Application forms (Updated 3/2026) — this is the current re-inspection rate and supersedes the $62.62/hr figure in the 2018/2020 fee resolution, which has not been reissued as of this verification
$67.63 per hour, minimum 1-hour charge
Residential Addition / Alteration / Remodel PermitRe-inspection Fee · City of Great Falls Homeowner's Permit Application forms (Updated 3/2026)
$67.63 per hour, minimum 1-hour charge
Electrical PermitRe-inspection Fee · City of Great Falls Homeowner's Electrical Permit Application (Updated 3/2026) — current rate; supersedes the $62.62/hr figure in Resolution 10374
$67.63 per hour, minimum 1-hour charge
Plumbing PermitRe-inspection Fee · City of Great Falls Homeowner's Plumbing Permit Application (Updated 3/2026) — current rate; supersedes the $62.62/hr figure in Resolution 10374
$67.63 per hour, minimum 1-hour charge
Mechanical / HVAC PermitRe-inspection Fee · City of Great Falls Homeowner's Mechanical Permit Application (Updated 3/2026) — current rate; supersedes the $62.62/hr figure in Resolution 10374
$67.63 per hour, minimum 1-hour charge
EV Charger / Electric Vehicle Charging Station PermitRe-inspection Fee · City of Great Falls Homeowner's Electrical Permit Application (Updated 3/2026) -- current rate
$67.63 per hour, minimum 1-hour charge

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Great Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Great Falls building permits

Get alerts for Great Falls

We'll email you when Great Falls's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.