Great Falls building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Great Falls, Montana.
Verified 2026-07-02 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Civic Center, 2 Park Drive South, Room 112, P.O. Box 5021, Great Falls, MT 59403-5021
- Phone
- (406) 455-8430
- Office hours
- Mon-Fri 8:00 AM - 5:00 PM
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation / Footings
Before concrete pour, per geotechnical report and structural plans
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Electrical, plumbing, and mechanical rough-in before walls closed; separate trade permits required
- 4
Blower Door Test
Required for new construction prior to Certificate of Occupancy; must be performed by an approved third party
- 5
Final
All work complete, boulevard landscaping and driveways/sidewalks complete, Certificate of Occupancy issued
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings and foundation before concrete pour
- 2
Framing
Structural framing before wall cover
- 3
MEP Rough-In
Electrical, plumbing, mechanical rough-in — separate trade permits required
- 4
Final
All work complete, ready for occupancy
Applies to: Fire Sprinkler / Alarm Permit
- 1
Acceptance Test -- Fire Sprinkler
Great Falls Fire Rescue verifies the installed sprinkler system; billed per inspection, minimum 3 inspections for systems with 100 heads or less
- 2
Acceptance Test -- Fire Alarm
Great Falls Fire Rescue verifies the installed alarm system; billed per inspection, minimum 2 inspections for 25,000 sq ft or less
- 3
Acceptance Test -- Kitchen Hood / Suppression System
Great Falls Fire Rescue verifies the installed hood or special suppression system; billed per inspection, minimum 1 inspection per project
Applies to: Mechanical / HVAC Permit
- 1
Gas Piping Pressure Test
Required before concealing gas piping
- 2
Rough-In
Ductwork and mechanical equipment rough-in before walls closed
- 3
Final
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Underground / Slab Plumbing
Before concrete pour — pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected, no leaks, proper venting
Applies to: Residential Addition / Alteration / Remodel Permit
- 1
Framing / Structural
After framing complete, before wall cover
- 2
MEP Rough-In
Electrical, plumbing, mechanical rough-in — separate trade permits required
- 3
Final
All work complete per approved plans
Applies to: Electrical Permit
- 1
Rough-In
Wiring and conduit installed before walls closed
- 2
Final
All devices installed, panel labeled, service energized
Applies to: Residential Rooftop Solar PV Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, roof penetration sealing, and electrical interconnection verified
Applies to: Sign Permit
- 1
Sign Electrical Inspection
Required only if the sign includes electrical work outside the cabinet; performed under a separate Electrical Permit before sign placement
- 2
Final Sign Inspection
Verifies sign structure, placement, and (for freestanding signs/billboards) footings match the approved plans
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Great Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Great Falls building permits
Get alerts for Great Falls
We'll email you when Great Falls's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.