Kalispell building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Kalispell, Montana.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
201 1st Avenue East, Kalispell, MT 59901 (mailing: PO Box 1997, Kalispell, MT 59903)
Phone
(406) 758-7730
Office hours
Not published on the department page; phone (406) 758-7730 and email bldgdept@kalispell.com listed as primary contact methods

Published scheduling rules

  • Schedule inspections by emailing inspections@kalispell.com with the permit number or address, inspection type needed, and a contact name/phone number. Inspections must be scheduled 24-48 hours in advance; same-day inspections cannot be guaranteed. (Residential Building Permit (New Construction))
  • Schedule inspections by emailing inspections@kalispell.com 24-48 hours in advance; same-day inspections are not guaranteed. (Electrical Permit)
  • Schedule inspections by emailing inspections@kalispell.com 24-48 hours in advance; same-day inspections are not guaranteed. (Electric Vehicle (EV) Charger / EVSE Permit)
  • Schedule inspections by emailing inspections@kalispell.com with your permit number/address, inspection type, and contact info; inspections must be scheduled 24-48 hours in advance and same-day inspections are not guaranteed. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour

  2. 2

    Framing

    Structural framing before wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed — separate trade permits required

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Certificate of Occupancy / Change of Use Permit

  1. 1

    Building/Trade Final Inspections

    Building, plumbing, mechanical, electrical, accessibility, energy, and life-safety final inspection by the Building Department

  2. 2

    Fire/Life Safety Final

    Fire, sprinkler, fire alarm, and alternate suppression system final inspection by the Building/Fire division

  3. 3

    Zoning, Parks, Public Works & Fire Sign-off

    Parking, architectural review, outdoor lighting, floodplain, and signage/CUP/PUD conditions verified by Zoning; landscaping/park land verified by Parks; streets/drainage/utilities/right-of-way verified by Public Works; fire lanes/access/hydrants verified by Fire

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Rough-In / Underground

    Underground piping and rough sprinkler/alarm wiring inspected before concealment

  2. 2

    System Acceptance Test

    Full system acceptance test (flow test, alarm functional test) witnessed by the Building/Fire division before occupancy

  3. 3

    Final (Certificate of Occupancy sign-off)

    Building/Fire division confirms fire, sprinkler, alarm, and alternate suppression systems as part of the final Certificate of Occupancy sign-off

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Framing / Structural

    After framing complete, before wall cover

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in before walls closed — separate trade permits required

  3. 3

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    Final

    All work complete per approved plans

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough-In

    Circuit and conduit installed, before walls closed, if applicable

  2. 2

    Final

    Charger mounted, circuit labeled, and installation verified per the adopted 2020 NEC

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Final

    All devices installed, panel labeled, service energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough-In

    After pipes installed, before walls closed

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, electrical connections, and interconnection point verified

Final inspection only: Roofing Permit (Reroof), Sign Permit

Re-inspection fees

Residential Building Permit (New Construction)Re-inspection Fee · City of Kalispell Building Permit Fee Schedule, effective 09/04/2024
Cost plus 10% admin/overhead fee
Residential Building Permit (New Construction)Inspections Outside Normal Business Hours · City of Kalispell Building Permit Fee Schedule, effective 09/04/2024
$50.00 per re-inspection

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kalispell building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Kalispell building permits

Get alerts for Kalispell

We'll email you when Kalispell's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.