You are viewing the permanent link for the record currently in effect, published 2026-07-07.
Glasgow building permits
VerifiedGlasgow, Montana — as published 2026-07-07.
Verified 2026-07-03 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction / Addition / Alteration)
VerifiedRequired for new single-family home construction, additions, garages, decks over 2 feet high, and structural alterations within Glasgow city limits. Issued by the City of Glasgow Public Works/Building Codes Department under its DLI-certified local Building (B) program. Plans are reviewed against the code editions referenced in the City's own Building Permit Packet (2018 IRC/IBC/IMC/IEBC/IFGC/ISPSC, 2012 IECC, 2018 UPC — see codesAdopted note on a possible discrepancy with the state's newer 2021-cycle codes).
Verified 2026-07-03 · Source
Requirements
- Building Permit Application completed in full: owner, contractor, and architect/engineer contact information; class of work (new/addition/alteration/repair/mobile home); legal description (street address, lot, block, subdivision, zoning district); off-street parking spaces provided; change of occupancy if any; valuation of work and number of family units; type of construction (foundation, exterior walls, roof, interior walls)
- Minimum of TWO complete sets of plans required for residential remodel/garage projects; THREE complete sets required for residential new construction, per the Building Permit Application Instructions
- Required drawings: plot plan/site plan (scale not less than 1/4 inch = 1 foot, showing dimensions, north point, front/rear/side yards, walks/driveways/parking, steps/terraces/porches/fences/retaining walls, easements and setbacks, grading and drainage), construction/floor plan, exterior elevations (front, rear, both sides), and typical cross sections/wall sections (multiple sections required for a typical house, more for commercial)
- As of Ordinance No. 966 (effective July 27, 2020): property pins must be established and clearly visible before permit issuance for any new building project or any project that modifies an existing structure's footprint; the Building Inspector must witness the pins in place, or a licensed surveyor must establish them first
- Submitted roof truss diagrams must bear the seal of a Montana-licensed professional engineer
- All commercial plans for public buildings must be wet-stamped (each set original-stamped) by a Montana-licensed architect or engineer
- Projects within the designated 500-foot Critical Zone of the Glasgow/Cherry Creek/Milk River Levee require mandatory additional review by the U.S. Army Corps of Engineers before the City can issue an approved permit
- Offset/setback requirements are measured from the wall to the property line and are non-negotiable Zoning Code minimums; where a garage is accessed from an alley, the setback from the structure to the edge of the alley must be 20 feet
Required documents
- RequiredApplication for Building PermitCity of Glasgow form; submit to City of Glasgow, Department of Public Works, Building Codes, 319 3rd Street South, Glasgow, MT 59230, or electronically to codecompliance@cityofglasgowmt.com
- RequiredPlot Plan / Site PlanScale not less than 1/4 inch = 1 foot; shows dimensions, north point, yard dimensions, walks/driveways/parking, steps/terraces/porches/fences/retaining walls, easements, setbacks, grading and drainage
- RequiredConstruction/Floor Plan, Elevations, and Cross SectionsFloor plan of each floor/basement; exterior elevations (front, rear, both sides); typical cross sections/wall sections from footing to roof peak, showing construction materials, sizes, and spacing
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (all classes of work) | No fixed valuation-based fee schedule was found published on the City of Glasgow website, in the Building Permit Packet, or via the Municode-hosted Code of Ordinances (Municode returned an access error — library.municode.com/mt/glasgow — during direct verification attempts). The Demolition Permit form references City Code 'Sec. 8-117' for its own fee tiers, indicating Chapter 8 governs building-related fees, but the specific building-permit fee table/valuation schedule was not independently locatable online after exhausting the City's Building Permit Packet, Public Works Department page, ordinances page, and Municode. Left null per the zero-tolerance policy rather than estimated; applicants must contact the Building Codes Department at (406) 228-2476 ext. 8 or codecompliance@cityofglasgowmt.com for a current fee quote. |
Electrical Permit (State-Issued)
VerifiedBecause Glasgow is DLI-certified for Building only, electrical work anywhere within Glasgow city limits requires a Residential (or Commercial) Electrical Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Glasgow. Confirmed explicitly in the City's own Building Permit Packet: 'The City of Glasgow does not issue Electrical or Plumbing Permits... Electrical and Plumbing permits are obtained from the State of Montana Business Standards Division.'
Verified 2026-07-03 · Source
Requirements
- Application must be signed and dated by the licensed electrical contractor's person in charge
- Payment must be submitted with the application; incomplete applications are returned unprocessed
- Property address, county, and whether the job is inside city limits must be indicated
- Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431
Required documents
- RequiredApplication for Residential Electrical PermitMontana Building Codes Bureau statewide form (Rev. 12/22); mailed with payment to Building Codes Program, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Single Family Dwelling or Cabin — up to 200-amp service (includes meter base and attached garages if wired at the same time) | $200 | Montana Building Codes Bureau, Application for Residential Electrical Permit (Rev. 12/22) statewide fee schedule — applies to all non-electrically-certified Montana jurisdictions, including Glasgow |
| Single Family Dwelling or Cabin — 201 to 400-amp service | $380 | Application for Residential Electrical Permit (Rev. 12/22) |
| Single Family Dwelling or Cabin — 401 to 600-amp service | $600 | Application for Residential Electrical Permit (Rev. 12/22) |
| Single Family Dwelling or Cabin — 601-amp service and up | $800 | Application for Residential Electrical Permit (Rev. 12/22) |
| Residential Change of Service — exterior meter base & main disconnect only | $45 | Application for Residential Electrical Permit (Rev. 12/22) |
| Private Property Accessory Building — up to 200-amp panel | $80 | Application for Residential Electrical Permit (Rev. 12/22) |
| Request inspection, per hour | $60 (plus $30 per additional 30 minutes or fraction thereof in excess of one hour, plus travel time) | Application for Residential Electrical Permit (Rev. 12/22) |
Plumbing Permit (State-Issued, incl. Water Heater)
VerifiedBecause Glasgow is DLI-certified for Building only, plumbing work anywhere within Glasgow city limits — including water heater installation/replacement — requires a Plumbing Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Glasgow. Confirmed explicitly in the City's own Building Permit Packet.
Verified 2026-07-03 · Source
Requirements
- Application must be signed by the Master Plumber and include the Master Plumber License Number
- Property address, county, GEOCODE/parcel/lot/block, and whether the job is inside city limits must be indicated
- Type of Building, Type of Work, sewer service type (public/septic), and potable water source must be indicated
- Apply in accordance with Title 50, Chapter 60, Section 505, MCA and ARM 24.301.301 / 24.301.361
Required documents
- RequiredApplication for Plumbing Permit (BCP-1)Montana Building Codes Bureau statewide form (Rev. 10/2019); mailed with payment to Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Each NEW water heater (or replacement) | $25 | Montana Building Codes Bureau, Application for Plumbing Permit (BCP-1, Rev. 10/2019) statewide fee schedule — applies to all non-plumbing-certified jurisdictions, including Glasgow |
| Each plumbing fixture or trap | $10 per fixture/trap | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
| Each connection of building water supply to water service/public utility or private well | $20 | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
| Each connection of building drain to sewer system (public or septic) | $20 | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
| Repair or alteration of drainage or vent piping | $30 | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
| Gray water system, commercial or residential | $60 | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
| Each hose bibb, vacuum breaker, and/or backflow device | $6 | Application for Plumbing Permit (BCP-1, Rev. 10/2019) |
Mechanical / HVAC Permit (State-Issued)
VerifiedBecause Glasgow's DLI certification is Building (B) ONLY per the official DLI roster (no 'M' shown), this KB treats mechanical/HVAC work anywhere within Glasgow city limits as requiring a Mechanical Permit issued directly by the Montana DLI Building Codes Bureau in Helena. Note: the City's own Building Permit Packet contains conflicting language, at one point stating the City itself issues mechanical permits alongside building permits — see the codesAdopted discrepancy note. Applicants should confirm directly with the City (406-228-2476 ext. 8) which office to file with before submitting.
Verified 2026-07-03 · Source
Requirements
- Project Value must be provided; permit fee is calculated from the state's valuation-based fee schedule
- Type of Building and Type of Work must be indicated
- Boiler work requires a separate Boiler Permit form, not the Mechanical Permit
- Apply in accordance with Title 50, Chapter 60, Section 104, MCA and ARM 24.301.172
Required documents
- RequiredApplication for Mechanical Permit (BCP-1)Montana Building Codes Bureau statewide form (Rev. 06/2022); mailed with payment to Department of Labor and Industry / BCB, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mechanical Permit — project value $0-$10,000 | $48 for the first $1,000, plus $14 for each additional $1,000 or fraction thereof | Montana Building Codes Bureau, Application for Mechanical Permit (BCP-1, Rev. 06/2022) statewide fee schedule |
| Mechanical Permit — project value $10,001-$50,000 | $166 for the first $10,000, plus $9 for each additional $1,000 or fraction thereof | Application for Mechanical Permit (BCP-1, Rev. 06/2022) |
| Mechanical Permit — project value $50,001 or more | $514 for the first $50,000, plus $6 for each additional $1,000 or fraction thereof | Application for Mechanical Permit (BCP-1, Rev. 06/2022) |
Fencing Permit
VerifiedRequired for new fence/wall/hedge construction or installation, extensive repair, or additional runs of fencing over 10 feet in length within Glasgow city limits, per City Fence Ordinance No. 972 (originally required since July 15, 2015 under Ordinance No. 953). Issued by the City of Glasgow Public Works Department.
Verified 2026-07-03 · Source
Requirements
- Permit required for: new construction/installation of fencing on residential or commercial properties; rebuilding or extensive repair of existing fences; general repair replacing more than 20% of pickets/rails/surface boards/chain-link fabric or more than 2 posts on the same run; any new additional run of fencing over 10 feet added to existing fencing
- NOT required for: spot repair of occasional boards, repainting/staining of existing fences (under 20% of a given run); replacement of 2 existing posts in any given run
- Fences/walls/hedges up to 3 feet in height may be erected anywhere on a property, including within required clear-vision zones
- Fences/walls/hedges exceeding 3 feet must meet yard setback requirements and must NOT be located within the mapped clear-vision zones (Figures C3-1, C3-2, C3-3, varying by uncontrolled/semi-controlled/fully-controlled intersection type)
- No fence may be erected or maintained in a public right-of-way
- Permissible materials: wood, brick, concrete block, landscape block, split rail, chain-link, smooth wire, vinyl, ornamental iron. NOT permitted: railroad ties, wood pallets, tires, rubble, metal panels, barbed wire, salvaged materials (any unlisted material subject to Public Works Department review/approval)
- Finished side of the fence must face the outside of the property
- Fence installed exactly on a shared property line requires a written, notarized mutual-use agreement between both property owners, explicitly voidable if either property is sold, or the application will not be approved
- Owner/contractor must contact Montana 811 (Call Before You Dig) before any excavation for posts or footings
- Commercial, Unrestricted, and Industrial zoning districts have separate setback and material regulations (inquire with Public Works for commercial fencing)
Required documents
- RequiredApplication for Fence PermitCity of Glasgow form; submit in person to the City Clerk's Office or Public Works Department Office at 319 3rd Street South, Glasgow, MT 59230, by mail, or electronically to codecompliance@cityofglasgowmt.com
- RequiredSketch Plan of Proposed FencingDoes not need to be to scale, but must show the general shape of the lot, location of structures, location of the proposed fence, and correct distances from property lines or permanent infrastructure (back of sidewalk or edge of street pavement)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fence/wall/hedge permit fee | $5.00 | City of Glasgow Fencing Permit Packet: 'Before any fence permit is granted for installation of a fence, wall, or proposed screening shrubbery (hedge) the person(s) making the application for such permit shall pay to the City of Glasgow Public Works Department a fee for $5.00.' |
Demolition Permit
VerifiedRequired for demolition of any structure within Glasgow city limits. Issued by the City of Glasgow Office of Public Works. Requires documented utility disconnection and inspected removal of footings/foundations and sewer-line plugging before close-out.
Verified 2026-07-03 · Source
Requirements
- Demolition permit application must include address/location of demolition, legal description (lot, block, subdivision), owner and contractor contact information, and bonding certificate status
- City sewer lines must be plugged at the property line and inspected
- Footing and foundation must be removed and inspected
- Septic systems addressed per the form's septic line item (coordination with relevant health/septic authority implied)
- Utilities (electrical, gas, telephone, cable, sanitary sewer, water) must be disconnected/turned off, with each utility's disconnection signed and dated directly on the permit form before or upon demolition
- Permit fee must be paid (cash, check, or billed) to the Director of Public Works, Public Works Assistant, or City Clerk
Required documents
- RequiredDemolition Permit ApplicationCity of Glasgow Office of Public Works form; includes utility-disconnection sign-off lines and fee payment block
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit Fee — Residential | $50 | City of Glasgow Demolition Permit form, citing City Code Sec. 8-117 |
| Demolition Permit Fee — Commercial | $150-$500 | City of Glasgow Demolition Permit form, citing City Code Sec. 8-117; exact amount within this range determined by the City at issuance |
Accessory Structure / Deck Permit
VerifiedRequired for decks over 2 feet off the surrounding ground and for detached accessory buildings/sheds larger than 120 square feet (10'x12') within Glasgow city limits. Uses the same combined Application for Building Permit as new construction.
Verified 2026-07-03 · Source
Requirements
- Building permit required for: new construction of detached or attached garages/carports; decks over 2 feet off the surrounding ground; accessory buildings or sheds in excess of 120 square feet (10'x12')
- NOT required for detached accessory buildings/sheds that are 120 square feet or smaller
- Garage size is capped by lot size: under 7,000 sq ft lot allows up to 1,000 sq ft garage; 7,000-10,000 sq ft lot allows up to 1,200 sq ft; over 10,000 sq ft (contiguous if more than one lot) allows up to 1,600 sq ft maximum residential garage
- A detached garage closer than 10 feet to a residential or commercial building is treated as 'attached' and requires a firewall facing the building: no windows, solid wood or steel door with no window lights, interior wall covered with 5/8-inch sheetrock
- Setback/offset requirements measured from the wall to the property line apply in every zoning district and are non-negotiable; where access is from an alley, the setback from the structure to the edge of the alley must be 20 feet
- Ordinance No. 966 property-pin requirement applies: pins must be established and witnessed by the Building Inspector before permit issuance if the project modifies the structure's footprint
- Plot plan and construction plan/elevations required per the standard Building Permit Application Instructions (minimum 2 complete sets of plans for garages/remodel-scale projects)
Required documents
- RequiredApplication for Building PermitSame City of Glasgow form used for all new construction/alteration work, with 'New' or 'Addition' indicated for the accessory structure or deck
- RequiredPlot Plan and Construction PlanSite plan showing setbacks and structure location; construction/floor plan and typical cross-section for the deck or accessory structure
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (accessory structure/deck) | Same unresolved fee-schedule gap as the general Residential Building Permit — no fixed published fee table was locatable for Glasgow (City Building Permit Packet, Public Works page, and Municode all checked). Left null per the zero-tolerance policy; contact the Building Codes Department at (406) 228-2476 ext. 8 for a current quote. |
Solar Photovoltaic (PV) Permit
VerifiedRequired for installation of rooftop or ground-mount solar photovoltaic systems within Glasgow city limits. Requires a City Building Permit (structural/racking, issued by the City's own Code Compliance Officer) plus a State of Montana Electrical Permit (wiring/interconnection) -- Glasgow is city-certified for Building permits only; Electrical, Plumbing, and Mechanical permits within city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City.
Verified 2026-07-20 · Source
Requirements
- City Building Permit Packet submitted to the City's Code Compliance Officer for the structural/racking scope
- Electrical wiring/interconnection scope requires a State of Montana electrical permit application, not a City permit -- Glasgow is not electrically-certified
- Licensed electrical contractors apply for a standard electrical permit and select 'Solar' as the Alternative Energy Source on the state application form; non-electrician installers submit the state's Alternate Energy Permit instead, per the Montana Building Codes Bureau's Alternative Energy Information guidance
- State application must specify whether the solar installation is a Micro Inverter/AC Module System or a PV String System, and whether the system produces 90 or more volts of electricity
- Per the state Application for Residential Contractor Electrical Permit (Rev 6/24), a residential 'Alternative Energy' line item carries its own flat state fee, separate from the amperage-based service fees
Required documents
- RequiredCity Building Permit PacketCity of Glasgow application for the structural/racking scope
- RequiredMontana Application for Residential (or Commercial) Contractor Electrical PermitState of Montana Building Codes Bureau form; includes an Alternative Energy Source section (Solar/Wind/Hydro checkbox, system type, voltage)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| City Building Permit Fee (all classes of work) | No fixed valuation-based fee schedule was found published on the City of Glasgow website, in the Building Permit Packet, or via the Municode-hosted Code of Ordinances -- consistent with this corpus's existing residential-building-permit entry for Glasgow, which documents this same unresolved gap after exhausting the same sources. Contact the Building Codes Department at (406) 228-2476 ext. 8 for a current quote. | |
| State Electrical Permit -- Alternative Energy (residential, by licensed contractor) | $45 | Montana Building Codes Bureau, Application for Residential Contractor Electrical Permit (Rev 6/24), line item K 'Alternative Energy' -- applies statewide to any Montana jurisdiction (including Glasgow) not certified to issue its own electrical permits |
| State Electrical Permit -- Commercial (valuation-based, includes solar) | $45 for the 1st $500 plus 6% of balance (projects $0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,000-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+) | Montana Building Codes Bureau, Application for Commercial Electrical Permit (Rev 6/24) -- the same form has a dedicated Alternative Energy Source (Solar/Wind/Hydro) question set; fee is based on total electrical project value |
| State Electrical Permit -- Request Inspection | $60 per hour (plus $30 per additional 30 minutes, plus travel time) | Montana Building Codes Bureau electrical permit applications |
EV Charger / Electric Vehicle Charging Station Permit
VerifiedMontana has no dedicated EV-charger permit type or line item, and Glasgow is not electrically-certified, so installing a Level 2 (240V) home EV charger or EVSE within Glasgow city limits requires a State of Montana Electrical Permit issued directly by the DLI Building Codes Bureau, billed under the same general residential wiring/circuit line items used for any new dedicated circuit or service upgrade -- there is no separate 'EV charger' or 'EVSE' line item on the state's Residential Electrical Permit application. A City Building Permit is NOT required unless the installation also involves new structural work (e.g., a new carport/canopy). Re-chased 2026-07-20: directly downloaded and text-extracted the live State electrical permit PDF, confirming the $45/$70 additional-circuit lines and $200 up-to-200-amp service line are still current verbatim.
Verified 2026-07-20 · Source
Requirements
- Electrical work must be performed and the permit pulled by a Montana-licensed electrical contractor (LCO/UCO), per the Application for Residential Contractor Electrical Permit (Rev 6/24)
- If the EV charger is added as a new dedicated circuit to an existing panel with no service/panel change, this is billed under the form's 'Single Family Interior/Exterior Wire or Rewire' section, line H ('1 additional circuit or piece of equipment') or line G ('2-3 additional circuits or pieces of equipment') depending on scope
- If the installation requires a panel upgrade or new/upsized electrical service to support the charger's amperage draw, it is billed instead under the amperage-based 'Single Family Dwelling or Cabin' service tiers (A-D) rather than the additional-circuit lines
- The state application form has no Alternative-Energy-style checkbox or dedicated question set for EV chargers (unlike its Solar/Wind/Hydro section) -- EVSE is treated as ordinary residential branch-circuit wiring
- Job address, county, and whether the job is inside city limits must be indicated on the application; property owner and licensed electrical contractor information required
- A City of Glasgow Building Permit is required in addition if the EVSE is mounted on, or paired with, new structural construction (e.g., a new carport or accessory structure) per the City's general building-permit trigger list -- not required for a simple wall/pedestal-mounted charger on an existing structure
Required documents
- RequiredApplication for Residential (or Commercial) Contractor Electrical PermitMontana Building Codes Bureau statewide form (Rev 6/24); mailed with payment to Building Codes Program, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov/bcb
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| 1 additional circuit or piece of equipment (e.g., a single EV charger circuit added to an existing panel) | $45 | Montana Building Codes Bureau, Application for Residential Contractor Electrical Permit (Rev 6/24), line H -- no distinct 'EV charger'/'EVSE' line item exists on the state form; this is the general additional-circuit line an electrical contractor would use for a single new EV charger circuit, confirmed directly against the current fee schedule PDF. Confirm classification with the Building Codes Bureau, (406) 841-2056, before applying, since routing between lines G/H/service-tier depends on the specific scope of work. Re-confirmed live 2026-07-20 via direct PDF text extraction. |
| 2-3 additional circuits or pieces of equipment (e.g., EV charger plus other new circuits in the same job) | $70 | Application for Residential Contractor Electrical Permit (Rev 6/24), line G Re-confirmed live 2026-07-20 via direct PDF text extraction. |
| Single Family Dwelling or Cabin -- up to 200-amp service (if the EV charger install requires a new/upgraded service) | $200 | Application for Residential Contractor Electrical Permit (Rev 6/24), line A -- applies if a panel/service upgrade is needed to support charger load rather than a simple additional circuit Re-confirmed live 2026-07-20 via direct PDF text extraction. |
| Request Inspection, per hour | $60 (plus $30 per additional 30 minutes or fraction thereof, plus travel time) | Application for Residential Contractor Electrical Permit (Rev 6/24) Re-confirmed live 2026-07-20 via direct PDF text extraction. |
Sign Permit / Commercial Sign Standards
Glasgow does not publish a standalone, dedicated Sign Permit application or fee schedule -- checked the City's Public Works Department page, Building Permits page, Planning & Zoning page, Documents/Projects page, and the City-hosted zoning-district guideline PDFs (Zone 'A' and 'B' Residence Districts contain no sign language at all). The one substantive, currently-live source found is the City's 'Zone "C" Commercial District' guideline PDF, which sets numeric sign standards (size, height, placement, lighting) as part of its Design Standards for Retail/Service uses over 2,500 square feet (shopping centers/PUDs, reviewed as a conditional use by the Planning Board). The document is explicitly self-described as 'general guidelines only' and directs owners to 'consult the Public Works Department directly to review the current Zoning and Use Codes,' and states plainly it is 'not a substitute for a Building Permit, nor intended to function as a Building Permit.' A sign that itself constitutes erecting or altering a structure (e.g., a freestanding/pylon sign requiring its own footing) would fall under the City's general Application for Building Permit ('permit to erect/alter a structure ... located as shown on the accompanying plot plan'), the same combined form used for all other unlisted construction activity -- there is no sign-specific form.
Reviewed 2026-07-22 · Source
Requirements
- Per the Zone 'C' Commercial District Design Standards (applicable to Retail/Service uses over 2,500 sq ft reviewed as a conditional use): one protruding sign advertising the particular use of the property is permitted per use, not to exceed fifty (50) square feet in area, and not to exceed a height of thirty-five (35) feet
- Signs must not be located on public property or within the public right-of-way
- No sign, outdoor commercial advertising device, or lighting device may conflict with public traffic control devices or create lighting glare/focus/animation/flashing affecting adjacent residential districts; revolving beacons, fountain spot lights, strobe lights, and pogo/zip sticks not used for sign illumination and intended to attract attention are expressly prohibited
- These numeric standards are published only for the Zone 'C' Commercial District's over-2,500-sq-ft conditional-use category -- no equivalent published sign standard was found for Zone 'A'/'B' Residence Districts or for smaller (under 2,500 sq ft) accepted-use commercial buildings; confirm applicability for your specific property and use with Public Works before assuming these figures govern your sign
- If the sign installation itself requires erecting or altering a structure (footings, a freestanding pole/pylon structure, or attachment altering a building's framing), the general Application for Building Permit process applies, including its property-pin (Ordinance No. 966) and plan-submission requirements documented in this KB's residential-building-permit entry
- The City's own guideline document is explicitly advisory only ('general guidelines only ... may not cover specific zoning or use circumstances') and is not itself a permit or a substitute for one -- treat it as the operative published sign standard, not as proof a dedicated sign-permit product exists
Required documents
- OptionalApplication for Building Permit (if the sign involves erecting/altering a structure)Same City of Glasgow combined form used for all other construction not otherwise listed; no dedicated sign-permit application form was found published by the City
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign permit / sign-structure building permit fee | No dedicated sign-permit fee was found published anywhere on the City of Glasgow website, in the Zone 'C' Commercial District guideline PDF, the Building Permit Packet, or the Public Works Department page; Municode's Code of Ordinances remains inaccessible (JavaScript application shell only, consistent with the access failure already documented elsewhere in this file's other entries). If a sign triggers the general Building Permit process, it would be subject to the same unresolved valuation-based fee-schedule gap already documented on this jurisdiction's residential-building-permit entry. Left null per the zero-tolerance policy; contact the Building Codes Department at (406) 228-2476 ext. 8 for a current determination and quote. |
Fire Sprinkler / Fire Alarm Permit
Neither the City of Glasgow nor the State of Montana publishes a dedicated, standalone 'fire sprinkler permit' or 'fire alarm permit' product. Because Glasgow's DLI certification covers Building only (see codesAdopted), fire protection (sprinkler) system connections are billed under the State of Montana Plumbing Permit's fee schedule, which includes the line item 'Each lawn sprinkler, fire protection system, any meter, or backflow protection device -- $30' (directly confirmed against the live BCP-1, Rev. 10/2019 Application for Plumbing Permit PDF). Fire alarm systems are wired work with no dedicated line item on the State Electrical Permit forms; they are billed as ordinary new/additional circuit wiring under the same general electrical fee lines this KB already documents on the EV-charger-permit entry (e.g., the $45/$70 additional-circuit lines), following the identical pattern seen elsewhere in small, non-electrically-certified Montana jurisdictions this session. Separately, when a fire protection system is part of new construction, the City's own Building Permit Packet requires the design package to include a 'Fire protection system design concept adequate for shop drawing preparation by others' from a Montana-licensed design professional, reviewed as part of the City-issued Building Permit for the project. Glasgow's volunteer Fire Department (Fire Chief Brandon Brunelle) has no documented dedicated Fire Marshal/fire-prevention-bureau function, plan-review fee, or inspection fee of its own for these systems.
Reviewed 2026-07-22 · Source
Requirements
- Fire protection (sprinkler) system connections/devices: billed at $30 each under the State of Montana Application for Plumbing Permit (BCP-1, Rev. 10/2019) fee line 'Each lawn sprinkler, fire protection system, any meter, or backflow protection device'; application must be signed by a licensed Master Plumber with license number, since Glasgow is not plumbing-certified and plumbing permits are state-issued
- Fire alarm wiring: pulled by a Montana-licensed electrical contractor under the State Application for Residential (or Commercial) Contractor Electrical Permit; billed under the general additional-circuit or amperage-based service fee lines (there is no dedicated 'fire alarm' line item on the current, Rev 6/24 state electrical forms)
- New construction that includes a fire protection/suppression system: the City's own Building Permit Packet requires a 'Fire protection system design concept adequate for shop drawing preparation by others' from a Montana-licensed design professional as part of the plan submission for the City-issued Building Permit
- Businesses that sell, install, or service fire alarm or fire sprinkler/fire protection equipment in Montana must hold a license under the Montana Fire Protection License Program (business entity and/or individual endorsement), administered by the DLI Business Standards Division -- this is contractor licensing, not a per-project permit, and does not replace the state Plumbing/Electrical permits above
- No local Fire Marshal, fire-prevention bureau, or dedicated local plan-review/inspection fee is documented for Glasgow beyond the routing described above; confirm with the Building Codes Department, (406) 228-2476 ext. 8, whether any additional local sign-off applies to your specific project
Required documents
- RequiredApplication for Plumbing Permit (BCP-1)Montana Building Codes Bureau statewide form (Rev. 10/2019); used for the fire protection system/sprinkler connection fee line; mailed with payment to Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov
- OptionalApplication for Residential (or Commercial) Contractor Electrical PermitMontana Building Codes Bureau statewide form (Rev 6/24); used to bill fire alarm wiring as ordinary additional-circuit or service work
- OptionalCity Building Permit Packet (if part of new construction)City of Glasgow form; required when a fire protection system is a design element of new construction, triggering the design-professional fire-protection-system design requirement
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fire protection system (sprinkler) connection or device | $30 each | Montana Building Codes Bureau, Application for Plumbing Permit (BCP-1, Rev. 10/2019), fee line 'Each lawn sprinkler, fire protection system, any meter, or backflow protection device' -- confirmed by direct PDF text extraction of the current, live form; applies statewide to non-plumbing-certified jurisdictions including Glasgow |
| Fire alarm -- 1 additional circuit or piece of equipment | $45 | Montana Building Codes Bureau, Application for Residential Contractor Electrical Permit (Rev 6/24), line H -- no distinct 'fire alarm' line item exists on the state form; this is the general additional-circuit line, per the same routing already documented on this jurisdiction's ev-charger-permit entry |
| Fire alarm -- 2-3 additional circuits or pieces of equipment | $70 | Application for Residential Contractor Electrical Permit (Rev 6/24), line G |
| Request Inspection, per hour (electrical) | $60 (plus $30 per additional 30 minutes or fraction thereof, plus travel time) | Application for Residential Contractor Electrical Permit (Rev 6/24) |
| City Building Permit fee (if fire protection system is part of new construction) | Same unresolved fee-schedule gap already documented on this jurisdiction's residential-building-permit entry -- no fixed published fee table was locatable for Glasgow's City Building Permit. Left null per the zero-tolerance policy; contact the Building Codes Department at (406) 228-2476 ext. 8 for a current quote. |
Change of Use / Change of Occupancy (Certificate of Occupancy)
VerifiedGlasgow does not have a standalone Change of Use or Certificate of Occupancy application, product, or fee. A 'CHANGE OF OCCUPANCY FROM ____ TO ____ OCCUPANCY' field is built directly into the City's standard Application for Building Permit -- the same combined form used for all new construction, additions, and alterations -- confirmed by direct text extraction of the current, live Building Permit Packet PDF (page 6, Legal Description section of the application form). This means a change of use/occupancy in Glasgow is processed as a Building-Permit-class action through the Public Works/Building Codes Department, not through a separate certificate-of-occupancy office or process. Montana state law, MCA 50-60-107, separately establishes that 'a certificate of occupancy for a building constructed in accordance with the provisions of the state building code or county, city, or town building code must certify that the building conforms to the requirements of the building regulations applicable to it,' and that such a certificate, once issued, is binding and conclusive on all local agencies unless set aside by a court.
Verified 2026-07-22 · Source
Requirements
- File the standard Application for Building Permit, completing the 'CHANGE OF OCCUPANCY FROM ___ TO ___ OCCUPANCY' field in the Legal Description section, alongside standard owner/contractor/architect contact information and the class-of-work designation
- Same supporting materials as any other Building Permit application apply where relevant to the change (e.g., plot plan, construction/floor plan) if the change of occupancy involves any physical alteration; per MCA 50-60-107 the certificate must certify the building conforms to applicable building regulations for the new occupancy
- No separate change-of-use or certificate-of-occupancy fee, form, or office was found distinct from the general Building Permit process -- this KB's residential-building-permit entry documents the same unresolved fee-schedule gap that would apply here
- Because Glasgow is Building-certified but not Electrical/Plumbing-certified (see codesAdopted), a change of occupancy involving those trades would still require separate State DLI-issued Electrical/Plumbing permits per this KB's electrical-permit-state and plumbing-permit-state entries
Required documents
- RequiredApplication for Building PermitSame City of Glasgow combined form used for all new construction/alteration/addition work; includes a dedicated 'Change of Occupancy From/To' field in the Legal Description section -- there is no separate change-of-use or certificate-of-occupancy form
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (change of occupancy, processed via the standard Building Permit Application) | Same unresolved fee-schedule gap as the general Residential Building Permit entry in this file -- no fixed published fee table was locatable for Glasgow (City Building Permit Packet, Public Works page, and Municode all checked, Municode inaccessible as a JavaScript-only shell). Left null per the zero-tolerance policy; contact the Building Codes Department at (406) 228-2476 ext. 8 for a current quote. |
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glasgow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.