This is PermitBase’s published record for West Wendover as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
West Wendover building permits
VerifiedWest Wendover, Nevada — as published 2026-07-20.
Verified 2026-07-03 · Source
Codes adopted
Permit types & fees
Residential Building Permit (Single-Family, Two-Family, Manufactured Home — New Construction)
VerifiedRequired for new construction of single-family, two-family, and manufactured/mobile homes within West Wendover city limits, submitted to and reviewed in-house by the Community Development Department (Planning Desk) against the 2018 IRC/IBC as adopted by Resolution 2020-17.
Verified 2026-07-03 · Source
Requirements
- Building permit required for new single-family, two-family, or manufactured home construction within city limits, submitted to Community Development (Planning Desk) at West Wendover City Hall
- All permits must be obtained by a Nevada Licensed Contractor, except One or Two Family Dwellings, which may be obtained by the owner-occupant building for personal use (not for lease or resale)
- For new home construction, plans must be stamped and signed by a Nevada Licensed Architect (owner-builder) or by a Nevada Licensed Architect/Contractor (contractor-built)
- Completed Building Permit Application (both pages), drawing sets, and a plot plan showing setback compliance must be submitted
- Verification of property ownership required — the permit applicant must match the property owner of record with the Elko County Assessor/Recorder, or provide written owner authorization if a contractor is pulling the permit
- New residential construction must meet the landscaping requirements of Resolution 2004-18 as a condition of Certificate of Occupancy
- Applicants should check FEMA's Flood Map Service Center (msc.fema.gov/portal) for a FIRMette of the project area; some areas of the city (Sections 7, 8, 17 and 18 of Township 33N, Range 70E) are unmapped and treated as Zone D
- All contractors/sub-contractors must hold a Nevada Contractors Board license for their trade plus a City of West Wendover Business License
- Inspections require 24-hour advance notice to the Building Official or designee; work concealed prior to inspection may need to be re-opened
Required documents
- RequiredBuilding Permit ApplicationCity of West Wendover universal Building Permit Application (July 2020 version), both pages required, submitted in person to Community Development
- RequiredPlot PlanSite/plot plan showing setback compliance, submitted with the Building Permit Application
- RequiredConstruction Drawing SetsStamped/signed drawing sets per the Building Permit Application requirements (Nevada Licensed Architect for new home construction)
- OptionalFEMA FIRMetteFlood Insurance Rate Map excerpt for the project address, generated via the FEMA Flood Map Service Center
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee, Plan Check Fee, Water Impact Fee, Sewer Impact Fee (illustrative example only) | Example for a $200,000 valuation new single-family home: Building Permit Fee $1,553.75; Plan Check Fee $1,009.94; Water Impact Fee $3,715.58; Sewer Impact Fee $2,972.46; Total $9,251.73 | City of West Wendover SF/TF/MH Residential Building Permit Submittal Guide (January 2016) — explicitly stated as an illustrative example only ('no representation/guarantee made as fees are based on specific projects'); Show full citationHideCity of West Wendover SF/TF/MH Residential Building Permit Submittal Guide (January 2016) — explicitly stated as an illustrative example only ('no representation/guarantee made as fees are based on specific projects'); fees are calculated per-project using a Uniform Building Code valuation formula referencing the ICC Building Valuation Data table, not a fixed published fee schedule |
Residential Addition / Remodel / Accessory Structure Permit
VerifiedRequired for home remodels, additions, and additional structures (carports, porches, sheds, etc.) on single-family, two-family, and manufactured home properties in West Wendover. Structures 200 sq ft or less within side/rear setbacks may qualify for the Provisional Building Permit process instead of a standard permit.
Verified 2026-07-03 · Source
Requirements
- Completed Building Permit Application, drawing sets (or manufacturer brochures/purchase documents for prefabricated sheds/kits), and a plot plan showing setback compliance
- Verification of property ownership matching the Elko County Assessor/Recorder record, or written owner authorization if a contractor is pulling the permit
- Shed/accessory structures within side and rear yard setbacks, 200 sq ft or less, may instead use the Provisional Building Permit process (see separate permit type) — but standard permits remain required for additions/remodels affecting the primary structure
- All contractors/sub-contractors must hold a Nevada Contractors Board license for their trade plus a City of West Wendover Business License
Required documents
- RequiredBuilding Permit ApplicationCity of West Wendover universal Building Permit Application (July 2020 version)
- RequiredPlot PlanSite/plot plan showing setback compliance for the addition/remodel/accessory structure
- OptionalManufacturer DocumentationBrochures or purchase documents for prebuilt/kit-form sheds or accessory structures, where applicable
Fee schedule
| Fee type | Amount | Notes |
|---|
Provisional Building Permit (Temporary/Accessory Structures)
VerifiedCovers temporary accessory structures (e.g., sheds) up to 200 sq ft and 12 feet in height, placed within side and rear yard setbacks, potentially over public utility easements. Governed by West Wendover City Code 8-5A-6(C). Not available for front or exterior side yard setbacks; structures must not include permanent surface treatments.
Verified 2026-07-03 · Source
Requirements
- Structure limited to R-3 occupancy only, maximum 12 feet height, maximum 200 square feet, single story
- Not permitted within front or exterior side yard setbacks
- No permanent surface treatments (concrete pads, asphalt paving, affixed decking) allowed under this permit
- May require review of current or future use of public utility/access easements associated with the property; the City may or may not allow placement over an active/inactive easement
- Site plan (scale no less than 1/8" = 1'), structure design/specifications (installation/erection instructions or cut sheets for prefabricated structures, or detailed construction drawings if built on-site), and engineered drawings/calculations for anchoring or spot footings (stamped by a Nevada licensed Structural Engineer) required
- Permit may be revoked at any time by the City for non-compliance or to protect public utility access/operation
- All permit fees due and payable at time of Provisional Building Permit issuance
Required documents
- RequiredProvisional Building Permit ApplicationCity of West Wendover Provisional Building Permit Application (July 21, 2020), 3 pages, includes legal responsibility/indemnification clauses for placement over utility easements
- RequiredSite Plan DrawingScale no less than 1/8" = 1', showing lot lines, setbacks, existing structures, sidewalks, driveways, retaining walls, fences, utilities, and proposed structure size/location
- RequiredStructure Design and SpecificationsInstallation/erection instructions and cut sheets (prefabricated) or detailed construction drawings (site-built)
- OptionalEngineered Anchoring/Footing CalculationsStamped and signed by a Nevada licensed Structural Engineer or as otherwise required by Community Development
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Structure size 100 sq ft or less | $160.46 | City of West Wendover Provisional Building Permit Application, July 21, 2020 |
| Structure size 101 to 150 sq ft | $206.66 | City of West Wendover Provisional Building Permit Application, July 21, 2020 |
| Structure size 151 to 200 sq ft | $252.06 | City of West Wendover Provisional Building Permit Application, July 21, 2020 |
Commercial / Multi-Family Building Permit
VerifiedRequired for commercial and multi-family development projects in West Wendover. Follows a multi-stage process: conceptual approval, preliminary site plan approval, final site plan approval, and building construction plan review — the latter conducted by West Coast Code Consultants, Inc. (WC3), the City's third-party plan reviewer, in parallel with site plan approval.
Verified 2026-07-03 · Source
Requirements
- Conceptual plan submittal for City Staff/Engineering review and City Council approval — plans prepared by licensed architects/engineers
- Preliminary Site Plan submittal (site layout, landscaping, drainage/grading calculations, utilities, parking/signage, lighting, street access, building elevations, fire hydrant locations, FEMA flood zone determination) for City Staff/Engineering review and City Council approval
- Conditional Use Permit and/or Variance submittals if required by the project
- Final Site Plan approval by Staff/Engineering and City Council
- Building Construction Plans submitted to WC3 (third-party plan reviewer) for code-compliance review; can run in parallel with Site Plan review
- State Fire Marshal review of Fire Protection System Plans, also conducted by WC3 (fees paid directly to WC3 by the developer)
- State of Nevada Public Health Engineering review required if water/sewer service requirements apply
- Execution of bonding/service extension agreements as applicable, then issuance of Building Permit
- Large valuation projects (above $2 million) may require a non-refundable deposit of 50% of the Plan Check Fee before plan review begins
- Project valuation should not be less than the ICC's current Building Valuation Data (BVD) tabulated value
Required documents
- RequiredCommercial Building Application (WC3)West Coast Code Consultants commercial building application, submitted alongside PDF plan sets via email or FTP/DropBox to WC3
- RequiredBuilding Permit ApplicationCity of West Wendover universal Building Permit Application
- RequiredSite Plan and Construction DrawingsBuilding code analysis, site plan, floor/roof plans, exterior elevations, fire-rated construction details, mechanical/electrical drawings, specifications, structural calculations, geotechnical report(s), energy compliance report(s), HVAC load calculations
- OptionalFEMA FIRMetteFlood Insurance Rate Map excerpt for the project area
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee, Plan Check Fee, Water/Sewer Connection and other project-specific fees | Project-specific, based on valuation compared against ICC Building Valuation Data (BVD); no flat published fee schedule found | City of West Wendover Commercial Project Development Guide, September 2020 |
| Large-valuation plan check deposit (projects over $2,000,000 valuation) | Non-refundable deposit equal to 50% of the Plan Check Fee, due at permit application submittal before plan review commences | City of West Wendover Commercial Building Plan Review handout (WC3) and Commercial Project Development Guide, September 2020 |
Mobile Home Park Residence Permit
VerifiedRequired for moving (installation/removal) mobile/manufactured homes into or out of a Residential Mobile Home Park within West Wendover city limits, governed by West Wendover City Code Title 8, Chapter 5, Section (B) (RMH 1, 2, or 3 zoning) and the Nevada Division of Manufactured Housing.
Verified 2026-07-03 · Source
Requirements
- Mobile Home Moving (Installation, Removal) Application required for units located into a Residential Mobile Home Park within city limits
- Unit type, age, and configuration requirements vary by specific mobile home park — confirm with Community Development and the relevant park
- Any additions/alterations to a mobile home's structure (e.g., adding a carport) require a standard Residential Building Permit Application instead
- Mobile homes/manufactured homes and the parks themselves are governed by the Nevada Division of Manufactured Housing (mhd.nv.gov)
- Inspections for electrical grounding, utility connections, home electrical, and tie-downs are conducted by the City Building Official together with the Nevada Division of Manufactured Housing
Required documents
- RequiredMobile Home Moving (Installation, Removal) ApplicationCity of West Wendover application for locating a mobile/manufactured home into a Residential Mobile Home Park
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mobile Home Application Fee (flat fee) | $100.00 | City of West Wendover Residential Mobile Home (Mobile Home Park Residence) Permit Submittal Guide, January 2016 — due and payable at time of permit issuance |
Solar PV Installation (Building + Electrical Permit)
West Wendover has no dedicated solar-PV application, submittal guide, or flat fee line published among its Community Development handouts (Commercial Project Development Guide, Residential Building Permit Submittal Guide, or WC3 plan-review packages) — a rooftop or ground-mount solar photovoltaic installation is filed using the same Building Permit Application process as other construction, reviewed against the city's adopted 2018 IBC/IRC/IECC and 2017 NEC (Resolution No. 2020-17), with Building Permit and Plan Check fees calculated from project valuation against the ICC Building Valuation Data (BVD) table — the same general fee mechanism documented throughout this file for every permit type. Commercial-scale solar plan review would route through the city's third-party reviewer, West Coast Code Consultants (WC3), the same as other commercial building/fire-protection plans. Nevada NRS 278.580 authorizes local governments to accommodate solar/wind energy materials and technologies within their adopted building codes.
Reviewed 2026-07-20 · Source
Requirements
- Building permit required for the structural/racking component of a solar installation, submitted to Community Development (Planning Desk) at West Wendover City Hall, using the same Building Permit Application as other residential or commercial construction — no dedicated solar-only form was found published
- Electrical permit required for the PV interconnection, reviewed against the city's adopted 2017 NEC
- For a residential system on an owner-occupied one- or two-family dwelling, the owner may pull the permit personally (not requiring a Nevada Licensed Contractor) provided it is for personal use and not for lease or resale, per the city's general owner-builder exemption
- Commercial-scale solar plan review is submitted to West Coast Code Consultants (WC3), the city's third-party commercial plan reviewer, rather than reviewed entirely in-house — WC3 fees are paid directly by the developer/builder, separate from City-collected building-plan-review fees
- Building Permit Fee and Plan Check Fee are calculated by comparing declared project valuation against the current ICC Building Valuation Data (BVD) table — no separate flat solar fee schedule was found published
- NV Energy interconnection approval is required statewide before a grid-tied system can be energized, separate from and in addition to the city's building/electrical permit
Required documents
- RequiredBuilding Permit ApplicationSame general application used for other residential/commercial construction; no dedicated solar-only form is published
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee and Plan Check Fee — valuation-based (ICC BVD table) | Calculated from project valuation compared against the current ICC Building Valuation Data table | No separate flat published fee schedule document exists for any permit type at West Wendover, including solar; Show full citationHideNo separate flat published fee schedule document exists for any permit type at West Wendover, including solar; same 'project-specific, valuation-based' finding documented throughout this file. City of West Wendover Commercial Project Development Guide (September 2020) and SF/TF/MH Residential Building Permit Submittal Guide (January 2016). Re-chased 2026-07-20 specifically hunting for a percentage-of-valuation rate (the way several nearby jurisdictions publish, e.g. '1.0% of valuation'): both source PDFs (showpublisheddocument/2723 and /2707) return HTTP 403 to both WebFetch and browser-header curl, and neither has any Wayback Machine capture (CDX/availability API both empty) — genuinely inaccessible, not merely unfound. A general web search for a West Wendover fee resolution/percentage also returned nothing jurisdiction-specific. |
EV Charger Installation (Building + Electrical Permit)
VerifiedWest Wendover has no dedicated EV-charger/EVSE application, submittal guide, or flat fee line published among its Community Development handouts — an EV charging station (Level 2 or DC fast charger) is filed using the same Building Permit Application process as other construction, reviewed against the city's adopted 2018 IBC/IRC/IECC and 2017 NEC (Resolution No. 2020-17), with Building Permit and Plan Check fees (where a new structure/canopy or panel upgrade tied to a building addition is involved) calculated from project valuation against the ICC Building Valuation Data (BVD) table — the same general fee mechanism documented throughout this file for every permit type, including solar-pv-permit. Commercial-scale EV charging installations (e.g., a multi-port charging hub) would route through the city's third-party reviewer, West Coast Code Consultants (WC3), the same as other commercial building/electrical plans.
Verified 2026-07-20 · Source
Requirements
- Electrical permit required for the charger circuit/wiring/interconnection, submitted to Community Development (Planning Desk) at West Wendover City Hall, using the same Building Permit Application as other residential or commercial construction — no dedicated EV-charger-only form was found published
- Building permit additionally required if the installation includes a new canopy, carport, or structural mounting component
- For a residential charger on an owner-occupied one- or two-family dwelling, the owner may pull the permit personally (not requiring a Nevada Licensed Contractor) provided it is for personal use and not for lease or resale, per the city's general owner-builder exemption
- Commercial-scale EV charging installations are submitted to West Coast Code Consultants (WC3), the city's third-party commercial plan reviewer, rather than reviewed entirely in-house — WC3 fees are paid directly by the developer/builder, separate from City-collected building-plan-review fees
- Building Permit Fee and Plan Check Fee (where applicable) are calculated by comparing declared project valuation against the current ICC Building Valuation Data (BVD) table — no separate flat EV-charger fee schedule was found published
- NV Energy coordination/interconnection approval may be required for a service or panel upgrade tied to a Level 2 or DC fast charger installation, separate from and in addition to the city's building/electrical permit
Required documents
- RequiredBuilding Permit ApplicationSame general application used for other residential/commercial construction; no dedicated EV-charger-only form is published
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee and Plan Check Fee — valuation-based (ICC BVD table) | Calculated from project valuation compared against the current ICC Building Valuation Data table | No separate flat published fee schedule document exists for any permit type at West Wendover, including EV charging; Show full citationHideNo separate flat published fee schedule document exists for any permit type at West Wendover, including EV charging; same 'project-specific, valuation-based' finding documented throughout this file. City of West Wendover Commercial Project Development Guide (September 2020) and SF/TF/MH Residential Building Permit Submittal Guide (January 2016). Re-chased 2026-07-20: confirmed via the city's "Pay for Building Permits and Related Services" page (JavaScript-rendered, checked via a 2026-07-09 Wayback Machine snapshot) and repeated web/document searches that no separate percentage-of-valuation multiplier table or flat fee schedule is published anywhere on the city's site beyond the ICC BVD valuation mechanism already cited -- this is confirmed as the city's complete, real, and only published fee-setting mechanism for all permit types, not a gap in this session's research. |
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Wendover building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.