Yerington building permits

Verified

Yerington, Nevada — as published 2026-07-04.

Verified 2026-07-03 · Source

Codes adopted

Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. The only genuine statewide floor is the energy code, referenced through NRS 701.220, which directs the State Office of Energy to adopt and update energy-efficiency standards for new construction. Always confirm the specific adopted edition for the jurisdiction in question rather than assuming a uniform statewide code. Source: Nevada Legislature NRS Chapter 701 (State Office of Energy).International Building Code (IBC), 2018 Edition — adopted by the City of Yerington per Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025), cover sheet 'Building Codes Adopted by the City of Yerington.'International Residential Code (IRC), 2018 Edition — adopted by the City of Yerington per Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).International Existing Building Code (IEBC), 2018 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).International Energy Conservation Code (IECC), 2018 Edition — adopted by the City of Yerington (also satisfies the NRS 701.220 statewide energy floor). Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).Uniform Plumbing Code (UPC), 2018 Edition — adopted by the City of Yerington; Nevada jurisdictions commonly use the Uniform Plumbing Code rather than the International Plumbing Code. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).Uniform Mechanical Code (UMC), 2018 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).National Electrical Code (NEC), 2017 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).International Fire Code (IFC), 2012 Edition — adopted by the City of Yerington; commercial projects are additionally subject to review by the Mason Valley Fire District (775-463-2261), which requires its own separate application, plan submittal, and fee. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).2018 Northern Nevada Amendments (Northern Nevada Chapter of the International Code Council / NNICC) — incorporated by reference into the codes adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).The City of Yerington is a member of the International Code Council. Code adoption is referenced to Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for construction of a new single-family dwelling within Yerington city limits, reviewed against the 2018 IRC and 2018 Northern Nevada Amendments as adopted by the City of Yerington. All work must be completed by a contractor holding both a Nevada State Contractors Board license and a City of Yerington business license, unless the owner completes the project themselves under the Owner Builder Affidavit of Exemption.

Verified 2026-07-03 · Source

Requirements

  • All work must be completed by a licensed contractor holding a valid City of Yerington business license, unless the owner is performing the work themselves (requires the Owner Builder Affidavit of Exemption)
  • Plans must comply with the 2018 IRC, 2018 IECC, and 2018 Northern Nevada Amendments as adopted by the City of Yerington (Yerington City Code Title 1, Chapter 9)
  • Two sets of identical plans on 11x17-inch (tabloid) paper are required; homeowners performing their own work must draw and submit their own plans; the City cannot accept plans stamped only by an out-of-state licensed professional
  • A plot plan showing lot lines, existing structures, and project features is required for zoning and setback review
  • Tax Verification form must be signed by the Lyon County Clerk's Office (27 South Main Street) confirming property taxes are current before a permit can be issued
  • Applicant must acknowledge compliance with Yerington City Code Title 12 (flood zones) on the permit application
  • Fees are calculated from total project valuation (materials, labor, engineering, and other services, or the contractor's bid amount) using the City's Building Valuation Data Sheets; all fees must be paid before permit issuance

Required documents

  • RequiredBuilding Permit Application (PW106, Rev. 7, 06/2025)City of Yerington universal Commercial (IBC 2018) / Residential (IRC 2018) building permit application, covering contractor information, project valuation, and the 'For Office Use' fee/category checklist
  • RequiredTax Verification FormProperty tax statement signed by the Lyon County Clerk's Office certifying taxes are current on the subject APN; required before any permit is issued
  • OptionalOwner Builder Affidavit of ExemptionNevada State Contractors Board form required only if the property owner is self-performing work under the NRS 624.031(4) owner-builder exemption
  • RequiredConstruction Plans (2 sets, 11x17 tabloid)Site plan, foundation, framing, floor plan, and elevations consistent with the adopted 2018 IRC/IBC and Northern Nevada Amendments; must bear a Nevada-licensed design professional's stamp where required

Fee schedule

Fee typeAmountNotes
Building Permit FeeValuation-based; determined from the City of Yerington Building Valuation Data Sheets (most recent revision, maintained at the Building and Planning Department) using the 1997 Uniform Building Code Section 223 definition of 'Valuation'City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section — no flat published table; a specific dollar amount cannot be verified without the underlying Valuation Data Sheets, which are not posted online
Plan Check FeeValuation-based; see Building Permit FeeCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section

Residential Addition / Remodel Permit

Verified

Required for room additions, remodels, decks, and fences within Yerington city limits, using the same universal Building Permit Application as new construction. The application form includes dedicated checkbox categories for Addition, Deck, Fence, TI (Tenant Improvement), and Repair.

Verified 2026-07-03 · Source

Requirements

  • The universal Building Permit Application (PW106) is used, checking 'Addition,' 'Deck,' 'Fence,' 'TI,' or 'Repair' as applicable under the 'For Office Use' category block
  • Tax Verification form (Lyon County Clerk signature) is required before permit issuance, same as new construction
  • Plans must comply with the 2018 IRC/IEBC and 2018 Northern Nevada Amendments as adopted by the City of Yerington
  • Owner-Builder Affidavit of Exemption may be used if the owner is self-performing the work on their own residence

Required documents

  • RequiredBuilding Permit Application (PW106, Rev. 7, 06/2025)Check 'Addition,' 'Deck,' 'Fence,' 'Repair,' or 'TI' under the For Office Use category block
  • RequiredTax Verification FormSigned by the Lyon County Clerk's Office confirming taxes are current

Fee schedule

Fee typeAmountNotes
Building Permit FeeValuation-based; determined from the City of Yerington Building Valuation Data SheetsCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026) — no separate flat fee is published for additions/remodels/decks/fences; all are priced from the same valuation-based Building Permit Fee and Plan Check Fee as new construction

Electrical Permit

Verified

Required for electrical installation, alteration, or repair work in Yerington, governed by the 2017 National Electrical Code (NEC) as adopted by the City. Standalone electrical upgrades carry a dedicated inspection fee separate from the valuation-based building permit fee.

Verified 2026-07-03 · Source

Requirements

  • Electrical permit required for installation, alteration, or repair of wiring and electrical equipment, governed by the 2017 NEC as adopted by the City of Yerington
  • Apply via the universal Building Permit Application (PW106), checking the 'Electric' box under the For Office Use category block
  • Electrical Contractor section of the application (name, address, phone, NV Contractors License Number, Yerington Business License Number) must be completed; missing information will delay permit issuance
  • An Electrical Upgrade inspection carries its own dedicated $85.00 inspection fee, separate from the building permit/plan check fee

Required documents

  • RequiredBuilding Permit Application (Electric)Universal City of Yerington permit application; check 'Electric' under the For Office Use category block and complete the Electrical Contractor section

Fee schedule

Fee typeAmountNotes
Inspection Fee: Electrical Upgrade (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Re-inspection Fee (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Building Permit Fee (electrical work bundled into new construction/addition)Valuation-based; determined from the City's Building Valuation Data SheetsCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026) — no separate stand-alone per-fixture/per-unit electrical fee table is published; electrical work performed as part of new construction or an addition is priced through the single valuation-based Building Permit Fee

Plumbing Permit (Water Lateral / Sewer Lateral / Septic)

Verified

Required for plumbing installation, water/sewer lateral connections, and septic systems in Yerington, governed by the 2018 Uniform Plumbing Code (UPC) as adopted by the City. Standalone site-utility plumbing work (water lateral, sewer lateral, septic) has dedicated flat inspection fees.

Verified 2026-07-03 · Source

Requirements

  • Plumbing permit required for installation, alteration, or repair of plumbing fixtures, water heaters, gas piping, or sewer/water service lines, governed by the 2018 UPC as adopted by the City of Yerington
  • Apply via the universal Building Permit Application (PW106), checking 'Sewer,' 'Water,' 'Septic,' or 'Well' under the For Office Use category block as applicable
  • Plumbing Contractor section of the application (name, address, phone, NV Contractors License Number, Yerington Business License Number) must be completed
  • Sewer Lateral Service Permit and Water Lateral Service Permit are each their own dedicated $100.00 inspection fee; Septic Permit (new and replacement) is a dedicated $160.00 inspection fee
  • Commercial/industrial sewer fees and connection fees are determined using the Council-approved Uniform Plumbing Code Table 7.3 to calculate Sewer Fixture Units (SFU)

Required documents

  • RequiredBuilding Permit Application (Sewer/Water/Septic/Well)Universal City of Yerington permit application; check the applicable utility box(es) under the For Office Use category block

Fee schedule

Fee typeAmountNotes
Sewer Lateral Service Permit$100.00 per inspectionCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Water Lateral Service Permit$100.00 per inspectionCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Septic Permit (New and Replacement)$160.00 per inspectionCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Inspection Fee: Gas Pressure (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Commercial/Industrial Non-Metered Sewer, first 25 Sewer Fixture Units (SFU)$61.70City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Sewer section; each additional SFU is $2.10; SFU determined via Council-approved Uniform Plumbing Code Table 7.3
Commercial/Industrial Sewer Connection Fee, first 25 SFU$3,800.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Sewer section; each additional SFU is $195.00
4-inch or 6-inch Sewer Service Connection Fee (City Code 8-5-1 C)$3,800.00 eachCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Sewer section

Mechanical / HVAC Permit (Including Wood Stoves)

Verified

Required for furnace, HVAC, wood-stove, and pellet-stove installations in Yerington, governed by the 2018 Uniform Mechanical Code (UMC) as adopted by the City. Residential HVAC and wood-stove installations carry a dedicated flat inspection fee.

Verified 2026-07-03 · Source

Requirements

  • Mechanical/HVAC permit required for installation or relocation of furnaces, boilers, air handlers, ventilation systems, and wood/pellet stoves, governed by the 2018 UMC as adopted by the City of Yerington
  • Apply via the universal Building Permit Application (PW106), checking 'Gas' or 'Propane' under the For Office Use category block as applicable for fuel-fired equipment
  • HVAC Contractor section of the application (name, address, phone, NV Contractors License Number, Yerington Business License Number) must be completed
  • Residential HVAC Permit (including wood stoves) carries a dedicated flat $80.00 inspection fee
  • Changing from one fuel source to another requires a dedicated $85.00 inspection fee (City Code 9-1-1-C2)

Required documents

  • RequiredBuilding Permit Application (Gas/Propane/HVAC)Universal City of Yerington permit application; check 'Gas' or 'Propane' under the For Office Use category block and complete the HVAC Contractor section

Fee schedule

Fee typeAmountNotes
Residential HVAC Permit (Inc. Wood Stoves)$80.00 per inspectionCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Inspection Fee: Changing from One Fuel Source to Another (City Code 9-1-1-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Inspection Fee: Gas Pressure (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
Re-inspection Fee (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section

Re-Roofing Permit

Verified

Required for roof-covering replacement in Yerington, using the universal Building Permit Application's dedicated 'Re-Roof' checkbox category. Priced from the same valuation-based Building Permit Fee as other building work.

Verified 2026-07-03 · Source

Requirements

  • A building permit is required for roof-covering replacement, using the 'Re-Roof' category on the universal Building Permit Application (PW106)
  • Roofing materials and assemblies must comply with the adopted 2018 IRC/IBC and 2018 Northern Nevada Amendments
  • Fees are calculated from project valuation (materials, labor, and other services or the contractor's bid amount) using the City's Building Valuation Data Sheets

Required documents

  • RequiredBuilding Permit Application (Re-Roof)Universal City of Yerington permit application; check 'Re-Roof' under the For Office Use category block

Fee schedule

Fee typeAmountNotes
Building Permit FeeValuation-based; determined from the City of Yerington Building Valuation Data SheetsCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026) — no separate flat re-roof fee is published; re-roofing is priced through the same valuation-based Building Permit Fee and Plan Check Fee as new construction

Solar Photovoltaic (PV) Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Yerington. The City's own universal Building Permit Application (PW106) includes a dedicated 'SOLAR' checkbox as its own recognized project category (alongside New, Addition, Re-Roof, Electric, etc.), confirming the City treats solar as a distinct permit type. However, solar is billed through the same general ledger account (01-13-00-3117, 'Building Permit Fee') and the same valuation-based Building Permit Fee / Plan Check Fee used for other construction — the City's Fee Schedule contains no separate dollar-figure line item specific to solar.

Verified 2026-07-20 · Source

Requirements

  • Building permit required for the structural/racking portion, applied for via the universal Building Permit Application (PW106) by checking the 'SOLAR' box under the For Office Use category block
  • Governed by the 2018 IBC (commercial) / 2018 IRC (residential) as adopted by the City, per the application's own code-edition header
  • Electrical work (wiring/interconnection) governed by the 2017 NEC as adopted by the City — apply via the same universal application, additionally checking 'ELECTRIC' if not already covered by the SOLAR category, and completing the Electrical Contractor section (NV Contractors License Number, Yerington Business License Number)
  • A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy

Required documents

  • RequiredBuilding Permit Application (PW106) — SOLAR categoryUniversal City of Yerington permit application; check 'SOLAR' under the For Office Use category block
  • RequiredConstruction/Electrical PlansSite plan, roof/racking plan, and electrical one-line diagram, per the application's general submittal expectations

Fee schedule

Fee typeAmountNotes
Building Permit Fee (SOLAR category, GL 01-13-00-3117)Valuation-based; determined from the City's Building Valuation Data Sheets (not published online — located at the Building and Planning Department)City of Yerington Fee Schedule (Revision #33, revised 05/26/2026) directs Building Permit and Plan Check fees to the City's Building Valuation Data Sheets; no dedicated dollar-figure solar line item exists separate from this general valuation table, though SOLAR is its own checkbox category on the Building Permit Application (PW106) and is billed under the same GL code as the general Building Permit Fee
Plan Check Fee (GL 01-13-00-3117)Valuation-based, same account code as the Building Permit FeeCity of Yerington Building Permit Application (PW106, Rev. 6, 03/2021), For Office Use block
Inspection Fee: Electrical Upgrade (if applicable)$85.00City of Yerington Fee Schedule (Revision #33), Building Department section — same fee documented in this file's electrical-permit entry

EV Charger / Electric Vehicle Charging Station Permit

Verified

Yerington has no dedicated EV charger/EVSE permit category or fee line. Unlike solar, which the City's universal Building Permit Application (PW106) tracks as its own checkbox category ('SOLAR'), the application's category block has no separate 'EV' or 'ELECTRIC VEHICLE' checkbox — an EV charger installation is captured under the existing 'ELECTRIC' category, the same category used for any electrical work, and billed under the same GL 01-13-00-3117 valuation-based Building Permit/Plan Check fee mechanism (or the flat $85.00 Electrical Upgrade Inspection Fee under City Code 9-1-2-C2) documented in this file's electrical-permit entry. Confirmed via review of the City's Fee Schedule (Revision #33, revised 05/26/2026), which contains no line item for 'EV,' 'electric vehicle,' 'EVSE,' or 'charging station.' Re-verified 2026-07-20 via a direct live re-fetch of the same Revision #33 Fee Schedule PDF (unchanged, still current as of this review): 'Inspection Fee: Electrical Upgrade (9-1-2-C2) — $85.00 Each Inspection' and 'Re-inspection Fee (9-1-2-C2) — $85.00 Each Re-inspection' both confirmed live and unchanged.

Verified 2026-07-20 · Source

Requirements

  • Apply via the City's universal Building Permit Application (PW106), checking the 'ELECTRIC' category under the For Office Use block (no separate EV-specific checkbox exists)
  • Electrical work governed by the 2017 NEC as adopted by the City (Yerington City Code Title 1, Chapter 9); complete the Electrical Contractor section (NV Contractors License Number, Yerington Business License Number)
  • A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy
  • If the charger installation requires a panel/service upgrade, the $85.00 Electrical Upgrade Inspection Fee (City Code 9-1-2-C2) applies in addition to any base Building Permit Fee
  • Confirm with the Building Department (775-463-3511) whether a standalone EV charger circuit addition is billed as a flat inspection fee or the full valuation-based Building Permit Fee before applying

Required documents

  • RequiredBuilding Permit Application (PW106) — ELECTRIC categoryUniversal City of Yerington permit application; check 'ELECTRIC' under the For Office Use category block, since no EV-specific checkbox exists

Fee schedule

Fee typeAmountNotes
Inspection Fee: Electrical Upgrade (City Code 9-1-2-C2)$85.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section — same flat fee documented in this file's electrical-permit and solar-pv-permit entries; no dedicated EV-specific line item exists
Building Permit Fee (electrical work bundled into new construction/addition, valuation-based)Determined from the City's Building Valuation Data Sheets (not published online — located at the Building and Planning Department)City of Yerington Fee Schedule (Revision #33) — applies if the EV charger installation is billed under the general valuation-based mechanism rather than the flat Electrical Upgrade Inspection Fee

Sign Permit

Verified

Required for installation of a sign within Yerington city limits. The City's own universal Building Permit Application (PW106) includes a dedicated 'SIGN' checkbox as its own recognized project category (alongside New, Re-Roof, Solar, etc.), confirming the City treats sign installation as a distinct permit type. However, like solar, a sign permit is billed under the same general ledger account (01-13-00-3117) and the same valuation-based Building Permit Fee / Plan Check Fee used for other construction — the City's Fee Schedule (Revision #33, revised 05/26/2026) contains no separate dollar-figure line item specific to signs. A direct review of Yerington City Code Title 10 (Zoning Regulations) confirms 'SIGN' is only a generically defined term (10-1-3: 'Any advertising method by which a person, profession, business, commodity or fact is made known...'); the Title's 14 chapters (Chapter 1 Title/Purpose/Definitions through Chapter 14 Right To Farm) contain no standalone Signs chapter establishing district-specific sign standards, height/area limits, or a distinct sign-permit fee — sign regulation in Yerington's own codified ordinances is limited to this single definition.

Verified 2026-07-22 · Source

Requirements

  • Apply via the universal Building Permit Application (PW106), checking the 'SIGN' box under the For Office Use category block
  • Governed by the 2018 IBC (commercial) / 2018 IRC (residential) as adopted by the City per Yerington City Code 9-1-2, since no separate sign code chapter exists in Title 10 (Zoning Regulations)
  • A plot plan or drawing showing sign location, dimensions, and setback from property lines is required, consistent with the Building Permit Application's general plan-submittal requirements for zoning and setback review
  • Tax Verification form (Lyon County Clerk signature) required before permit issuance, same as any other building permit
  • All contractors and subcontractors must hold a valid City of Yerington business license and NV Contractors Board license before permit issuance

Required documents

  • RequiredBuilding Permit Application (PW106) — SIGN categoryUniversal City of Yerington permit application; check 'SIGN' under the For Office Use category block
  • RequiredSign Plan/DrawingDrawing showing sign dimensions, location on the lot, and structural attachment, used for zoning and setback review since no dedicated sign-code chapter exists
  • RequiredTax Verification FormSigned by the Lyon County Clerk's Office confirming taxes are current

Fee schedule

Fee typeAmountNotes
Building Permit Fee (SIGN category, GL 01-13-00-3117)Valuation-based; determined from the City's Building Valuation Data Sheets (not published online — located at the Building and Planning Department)City of Yerington Fee Schedule (Revision #33, revised 05/26/2026) directs Building Permit and Plan Check fees to the City's Building Valuation Data Sheets; no dedicated dollar-figure sign line item exists separate from this general valuation table, though SIGN is its own checkbox category on the Building Permit Application (PW106) and is billed under the same GL code as the general Building Permit Fee
Plan Check Fee (GL 01-13-00-3117)Valuation-based, same account code as the Building Permit FeeCity of Yerington Building Permit Application (PW106, Rev. 7, 06/2025), For Office Use block

Fire Sprinkler / Fire Alarm Permit (Mason Valley Fire District Review)

Yerington has no City-issued fire sprinkler or fire alarm permit, checkbox category, or fee line item of its own. Per the City's own universal Building Permit Application (PW106), Commercial Step 4 instructs applicants: 'Contact the Mason Valley Fire District at 775-463-2261 to find out if your project will be required to complete a fire review. The fire district will require a separate application and plan submittal in addition to a fee. The fire review must be completed and signed off before a city building permit can be issued.' Fire sprinkler/alarm plan review for property within Yerington city limits — not just unincorporated Lyon County — is therefore handled entirely outside the City's building-permit fee structure, by the Mason Valley Fire Protection District (also styled Yerington/Mason Valley Fire Protection District), an independent special district; this is the same arrangement documented for unincorporated Lyon County in lyon-county.json, confirming the City itself does not have a different arrangement. A live re-check of the District's own website (masonvalleyfire.org, checked 2026-07-22) shows only a single landing page with a tagline ('Protecting Lives and Property') and a generic name/email contact form — no fee schedule, plan-review application, or published timeline exists anywhere online for the District. Note: the City's own Fee Schedule (Revision #33) separately lists a '4" Fire Sprinkler Service — $5,000.00' and '5" and larger Fire Sprinkler Service — $7,500.00' line item under its Water utility section; this is a water-tap CONNECTION fee for the physical size of the water service line feeding a fire sprinkler system, billed by the City's Water Department — it is NOT a fire-sprinkler/alarm plan-review or permit fee, and must not be conflated with one.

Reviewed 2026-07-22 · Source

Requirements

  • Contact the Mason Valley Fire District directly at (775) 463-2261 to determine whether a proposed project requires fire plan review (per the City's own Building Permit Application, Commercial Step 4)
  • The Fire District requires its own separate application and plan submittal, in addition to its own fee, entirely independent of the City's Building Permit Application (PW106)
  • Fire District sign-off must be completed before the City will issue the underlying building permit
  • If the project also requires a new or upsized water service to feed a fire sprinkler system, a separate City of Yerington Fire Sprinkler Service connection fee applies ($5,000.00 for a 4-inch service, $7,500.00 for 5-inch or larger), per the City's Fee Schedule Water section — this is unrelated to the Fire District's own plan-review fee
  • Governed by the 2012 International Fire Code as adopted by the City of Yerington (Yerington City Code Title 1, Chapter 9), with plan review and enforcement delegated to the Mason Valley Fire District

Required documents

  • RequiredMason Valley Fire District Plan Review ApplicationA separate application required directly by the Fire District (775-463-2261); not part of the City's PW106 Building Permit Application and not published online
  • RequiredBuilding Permit Application (PW106)Underlying City building permit; for commercial work, cannot be issued until the Mason Valley Fire District review is signed off

Fee schedule

Fee typeAmountNotes
Mason Valley Fire District Plan Review/Permit FeeUnpublished — the City's own PW106 application confirms the Fire District requires 'a separate application and plan submittal in addition to a fee,' but no fee schedule is published on the District's website (masonvalleyfire.org, checked live 2026-07-22) or found anywhere else onlineGenuinely unpublished. Contact the Mason Valley Fire District directly at (775) 463-2261 for current cost — do not assume a figure
City of Yerington Fire Sprinkler Service Connection Fee (4-inch, water utility)$5,000.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Water section — a water-tap connection fee for the physical service line size, NOT a fire plan-review/permit fee
City of Yerington Fire Sprinkler Service Connection Fee (5-inch and larger, water utility)$7,500.00City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Water section — a water-tap connection fee for the physical service line size, NOT a fire plan-review/permit fee

Certificate of Occupancy (Change of Occupancy / Change of Use)

Yerington does not have a standalone change-of-use or certificate-of-occupancy permit application, checkbox category, or fee line item separate from the general Building Permit process. The City's own universal Building Permit Application (PW106) states directly: 'A PROJECT IS NOT COMPLETE UNTIL THE PERMIT FINAL IS SIGNED BY A CITY BUILDING OFFICIAL. THE BUILDING DEPARTMENT WILL RETAIN THE ORIGINAL BUILDING PERMIT ON FILE AND ISSUE A CERTIFICATE OF OCCUPANCY AS REQUIRED.' A Certificate of Occupancy is therefore issued as the final step of an underlying building permit (new construction, addition, TI, etc.) rather than as its own separately-applied-for, separately-fee'd product. Occupancy classification and change-of-occupancy requirements (e.g., when an existing building's use changes without accompanying new construction) are governed by the City's adopted 2018 International Building Code and 2018 International Existing Building Code (Yerington City Code 9-1-2), which the City has not further codified with any City-specific change-of-use application, checklist, or fee schedule of its own — Title 9 (Building Regulations) and Title 10 (Zoning Regulations) of the Yerington City Code contain no chapter dedicated to change of use or certificates of occupancy, and the Fee Schedule (Revision #33) contains no line item for either.

Reviewed 2026-07-22 · Source

Requirements

  • A Certificate of Occupancy is issued by the Building Department upon a signed-off Permit Final for an underlying building permit (e.g., new construction, addition, or tenant improvement) — 'as required,' per the City's own Building Permit Application (PW106)
  • For a change of occupancy classification without accompanying construction, the project is governed by the City's adopted 2018 International Building Code and 2018 International Existing Building Code (Yerington City Code 9-1-2); no separate City-published application or fee exists for this scenario — contact the Building Department at (775) 463-3511 to determine what triggers a new Building Permit Application (PW106) versus an administrative review
  • For commercial tenant improvements, the same universal Building Permit Application (PW106) is used, checking 'TI' under the For Office Use category block (see this file's residential-addition-remodel entry)
  • Standard prerequisites apply: Tax Verification form signed by the Lyon County Clerk's Office, and a current City of Yerington business license / NV Contractors Board license for any licensed contractor performing work

Required documents

  • RequiredBuilding Permit Application (PW106) — TI/New/Addition categoryNo separate change-of-use or Certificate of Occupancy application exists; the underlying project's Building Permit Application serves this function, with the CO issued upon Permit Final
  • OptionalTax Verification FormSigned by the Lyon County Clerk's Office confirming taxes are current; required whenever an underlying building permit is needed

Fee schedule

Fee typeAmountNotes
Building Permit Fee / Plan Check Fee (only if construction accompanies the change of use)Valuation-based; determined from the City's Building Valuation Data SheetsCity of Yerington Fee Schedule (Revision #33, revised 05/26/2026) — applies only if the change of use is accompanied by construction requiring a Building Permit Application; no standalone change-of-use or Certificate of Occupancy fee line item is published for a pure occupancy-classification change with no construction

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yerington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →

Permalink: /nevada/lyon-county/yerington/as-of/2026-07-04/

Snapshot date: 2026-07-04

Commit: bfcb452

Reproducible from PermitBase’s version-controlled dataset, commit bfcb452.