Inspection sequence, scheduling, and re-inspection fees for building permits in Carlsbad, New Mexico.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
114 S. Halagueno St., Carlsbad, NM 88220 (mailing: City Hall, 101 N. Halagueno St., Carlsbad, NM 88220)
Phone
(575) 885-1185
Office hours
City Hall: 8:00 AM-5:00 PM, Monday through Friday

Inspection sequence

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour -- pipe slope, materials, and cleanouts verified

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected, water heater and venting verified, no leaks

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete placement -- forms, reinforcing steel, and foundation depth verified

  2. 2

    Framing

    Structural framing, fire blocking, and bracing complete; rough electrical, plumbing, and mechanical inspections approved first

  3. 3

    Final

    Finish grading and building completion verified; final electrical, plumbing, and mechanical inspections conducted first

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, system energized and protections verified per the 2020 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    New circuit wiring and panel connections before walls are closed, if applicable

  2. 2

    Final

    Charger unit installed, panel labeled, system energized and protections verified per the 2020 NEC

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Pre-Test

    Full functional pre-test of the installed system per applicable NFPA standard, conducted by the installing contractor before Final Acceptance can be scheduled

  2. 2

    Final Acceptance Test

    Conducted by a State Fire Inspector (and, per the Fire Department's own stated practice, potentially also reviewed locally by the Carlsbad Fire Department's Fire Prevention Division) against the approved plans and test documentation

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational, venting and clearances verified

Applies to: Residential Addition / Alteration / Remodel Permit

  1. 1

    Framing / Rough-In

    Structural connections to the existing structure, and rough electrical/plumbing/mechanical if applicable

  2. 2

    Final

    Completed work verified against the approved permit scope

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Structural/Racking (Building Permit)

    Roof penetrations and mounting-system attachment verified per the approved building permit

  2. 2

    Final Electrical (Interconnection)

    Grid interconnection, grounding, and disconnects verified per the 2020 New Mexico Electrical Code (NMAC 14.10.4) before the system is energized

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Carlsbad building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Carlsbad building permits

Get alerts for Carlsbad

We'll email you when Carlsbad's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.