Skip to main content
PermitBase

This is PermitBase’s published record for Logan as of 2026-06-30. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Logan building permits

Verified

Logan, Utah — as published 2026-06-30.

Verified 2026-06-30 · Source

Codes adopted

2021 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective through June 30, 2026; Logan's own codes document (July 2023) confirms adoption2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); continues in force after July 1, 2026; Logan codes document (July 2023) confirms adoption2021 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective through June 30, 2026; Logan codes document (July 2023) confirms adoption2021 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective through June 30, 2026; Logan codes document (July 2023) confirms adoption2021 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective through June 30, 2026; Logan codes document (July 2023) confirms adoption2021 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective through June 30, 2026; Logan codes document (July 2023) confirms adoption2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); Logan codes document listed 2020 NEC (stale); statewide 2023 NEC governs2017 ICC A117.1 (Accessibility) — Logan City 'Current Building Codes & Engineering Design Requirements' (July 2023)NOTE: Effective July 1, 2026 — 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC replace the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026)

Permit types & fees

Residential Building Permit

Verified

Required for new residential construction, additions, structural alterations, and work requiring plan review under Logan Municipal Code Title 15 and the adopted 2021 IBC / 2021 IRC.

Verified 2026-06-30 · Source

Requirements

  • New single-family or multi-family residential construction
  • Additions or structural modifications (load-bearing wall removal, foundation work)
  • Conversion of non-habitable space to habitable space
  • Any work requiring plan review under Logan Municipal Code Title 15

Required documents

  • RequiredApplication for Residential PermitLogan City form (2026 edition); include address, parcel ID, project value, description of work, owner/contractor info, and signature
  • RequiredConstruction PlansComplete drawings to scale — site plan, floor plans, elevations, sections, and structural details. Plans are required at the time of submittal.
  • RequiredEnergy Code Compliance DocumentationREScheck or equivalent documentation demonstrating compliance with the 2021 IECC (2024 IECC effective July 1, 2026)
  • OptionalEngineered Truss PlansSealed truss layouts for new construction

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1.00–$500.00$50.00Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $501.00–$2,000.00$50.00 for the first $500, plus $4.00 for each additional $100 or fraction thereof, to and including $2,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $2,001.00–$25,000.00$110.00 for the first $2,000, plus $15.00 for each additional $1,000 or fraction thereof, to and including $25,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $25,001.00–$50,000.00$455.00 for the first $25,000, plus $11.00 for each additional $1,000 or fraction thereof, to and including $50,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $50,001.00–$100,000.00$730.00 for the first $50,000, plus $8.00 for each additional $1,000 or fraction thereof, to and including $100,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $100,001.00–$500,000.00$1,130.00 for the first $100,000, plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation $500,001.00–$1,000,000.00$3,730.00 for the first $500,000, plus $5.75 for each additional $1,000 or fraction thereof, to and including $1,000,000Logan City Building Permit Fees — Resolution No. 20-09
Building Permit — valuation over $1,000,000.00$6,605.00 for the first $1,000,000, plus $4.50 for each additional $1,000 or fraction thereofLogan City Building Permit Fees — Resolution No. 20-09
Residential Plan Check Fee0.1% of construction valuation (valuation × 0.001); minimum $15.00Logan City Building Permit Fees — Resolution No. 20-09. Example: $100,000 valuation → $100.00 plan check.
Electrical Permit (new construction / remodel)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09. Example: $1,050 building permit → $84 electrical.
Mechanical Permit (new construction / remodel)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Plumbing Permit (new construction / remodel)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection / After-Hours Inspection$50.00 per hour; minimum 2-hour charge for after-hoursLogan City Building Permit Fees — Resolution No. 20-09

Electrical Permit

Verified

Required for electrical work including panel upgrades, new circuits, rewiring, service changes, and new construction wiring in Logan. Governed by the 2023 NEC (adopted statewide by Utah Code § 15A-2-103(1)(g)).

Verified 2026-06-30 · Source

Requirements

  • New electrical circuits or wiring installations
  • Electrical panel upgrades or replacements
  • Service entrance changes
  • Adding or relocating outlets, switches, or fixtures
  • Generator or solar panel electrical connections

Required documents

  • RequiredElectrical, Plumbing, Mechanical Permit ApplicationLogan City form (Elec-Mech-Plumb Permit 2026); include scope of work and contractor license number
  • OptionalElectrical Plan / Single-Line DiagramRequired for service upgrades and new construction — panel schedule and circuit layout
  • OptionalContractor LicenseValid Utah electrical contractor license (Utah DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Electrical Permit — new construction or remodel (tied to building permit)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09. Example: $1,050 building permit → $84 electrical permit.
Electrical Service Change Permit (Residential — standalone)$50.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection Fee$50.00 per hourLogan City Building Permit Fees — Resolution No. 20-09

Plumbing Permit

Verified

Required for plumbing installations, alterations, and repairs including water heaters, re-pipes, and fixture additions in Logan. Governed by the 2021 IPC (2024 IPC effective July 1, 2026).

Verified 2026-06-30 · Source

Requirements

  • New plumbing fixture installations (sinks, toilets, showers)
  • Water heater installation or replacement
  • Water line or sewer line replacement or extension
  • Gas line installation or modification
  • Backflow prevention device installation

Required documents

  • RequiredElectrical, Plumbing, Mechanical Permit ApplicationLogan City form (Elec-Mech-Plumb Permit 2026); include scope of work and contractor license number
  • OptionalPlumbing PlanIsometric drawing showing fixture locations, pipe sizes, and drainage — required for larger projects
  • OptionalContractor LicenseValid Utah plumbing contractor license (Utah DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Plumbing Permit — new construction or remodel (tied to building permit)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09. Example: $1,050 building permit → $84 plumbing permit.
Gas Line Pressure Test Inspection Permit (standalone)$50.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection Fee$50.00 per hourLogan City Building Permit Fees — Resolution No. 20-09

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in Logan. Governed by the 2021 IMC (2024 IMC effective July 1, 2026).

Verified 2026-06-30 · Source

Requirements

  • Furnace or boiler installation or replacement
  • Air conditioning system installation or replacement
  • Ductwork installation or major modification
  • Evaporative cooler installation
  • Fireplace or wood-burning stove installation

Required documents

  • RequiredElectrical, Plumbing, Mechanical Permit ApplicationLogan City form (Elec-Mech-Plumb Permit 2026); include scope of work and contractor license number
  • OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, or heat pump

Fee schedule

Fee typeAmountNotes
Furnace and/or AC Replacement Permit (Residential — standalone)$50.00Logan City Building Permit Fees — Resolution No. 20-09
Mechanical Permit — new construction or remodel (tied to building permit)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09. Example: $1,050 building permit → $84 mechanical permit.
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection Fee$50.00 per hourLogan City Building Permit Fees — Resolution No. 20-09

Roofing Permit

Verified

Required for roof replacement and re-roofing in Logan. Logan's fee schedule lists a specific flat fee for residential re-roofing.

Verified 2026-06-30 · Source

Requirements

  • Complete roof replacement (tear-off and re-roof)
  • Overlay of new roofing over existing (where code allows)
  • Structural roof repairs or modifications
  • Changes to roofing material type

Required documents

  • RequiredResidential Permit ApplicationLogan City Application for Residential Permit (2026 edition); include scope of work, square footage, material specifications
  • OptionalContractor LicenseValid Utah roofing contractor license (Utah DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Re-Roofing Permit (Residential)$50.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection Fee$50.00 per hourLogan City Building Permit Fees — Resolution No. 20-09

Solar Panel Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Logan. Logan has a specific flat fee for residential solar (building division only), separate from any electrical permit.

Verified 2026-06-30 · Source

Requirements

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Battery storage system installation (requires separate electrical permit for wiring)
  • Electrical service upgrade for solar interconnection

Required documents

  • RequiredSolar Permit ApplicationLogan City Solar Permit Application (for battery installs only use 'Solar Battery Install Only' form; full solar PV via Light & Power portal — see tip)
  • RequiredSolar Site Plan / Roof PlanShowing panel placement, setbacks, and access pathways on the roof
  • RequiredElectrical Single-Line DiagramSystem wiring from panels to inverter to main panel and utility meter
  • RequiredStructural AnalysisRoof load calculation confirming the structure can support the panels
  • RequiredEquipment SpecificationsData sheets for panels, inverter, and racking system
  • OptionalInterconnection AgreementUtility approval for grid-tied systems (Logan City Light & Power)

Fee schedule

Fee typeAmountNotes
Solar Permit (Residential — Building Division only)$200.00Logan City Building Permit Fees — Resolution No. 20-09. Commercial solar is 'based on project value'.
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09

Water Heater Permit

Verified

Required for water heater installation, replacement, or conversion in Logan. Logan's fee schedule lists a specific flat fee for residential water heater permits.

Verified 2026-06-30 · Source

Requirements

  • Water heater replacement (including like-for-like swaps)
  • New water heater installation
  • Conversion from tank to tankless water heater
  • Gas line modification for water heater (may require separate gas line pressure test permit)

Required documents

  • RequiredElectrical, Plumbing, Mechanical Permit ApplicationLogan City form (Elec-Mech-Plumb Permit 2026); include water heater type, size, fuel source, and location
  • OptionalContractor LicenseValid Utah plumbing contractor license (Utah DOPL) if not owner-occupied

Fee schedule

Fee typeAmountNotes
Water Heater Permit (Residential)$50.00Logan City Building Permit Fees — Resolution No. 20-09
Gas Line Pressure Test Inspection Permit (if gas line work required)$50.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09
Re-inspection Fee$50.00 per hourLogan City Building Permit Fees — Resolution No. 20-09

Deck Permit

Verified

Required for new deck construction or structural modification of existing decks in Logan. Fees are valuation-based per the Logan building permit fee schedule.

Verified 2026-07-01 · Source

Requirements

  • New deck construction attached to or detached from the house
  • Decks more than 30 inches above grade
  • Structural modifications to existing decks
  • Adding or replacing a deck ledger

Required documents

  • RequiredApplication for Residential PermitLogan City form (2026 edition); include scope of work and project value
  • RequiredConstruction DrawingsFraming plan with beam/joist sizes, post locations, and footing details; ledger attachment detail per IRC R507.2 for attached decks
  • RequiredSite PlanShowing deck location, setbacks from property lines, and relationship to existing structure

Fee schedule

Fee typeAmountNotes
Building Permit (valuation-based)Per Logan City fee table by project valuation — see Residential Building Permit fees aboveAssessed on project valuation per Logan City's published Building Permit Fee Resolution No. 20-09 (cited fee table); minimum $50 for work up to $500 valuation. No separate flat deck fee exists — decks use the standard valuation-based building permit schedule.
Residential Plan Check Fee0.1% of construction valuation; minimum $15.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of building permit feeLogan City Building Permit Fees — Resolution No. 20-09

Basement Finish Permit

Verified

Required for finishing or remodeling an unfinished basement in Logan, including framing, electrical, plumbing, and mechanical work. Logan's website has a specific Residential Basement Finish Checklist.

Verified 2026-07-01 · Source

Requirements

  • Framing walls in an unfinished basement
  • Adding a bedroom (requires egress window)
  • Adding a bathroom (requires plumbing permit)
  • Electrical wiring for new rooms
  • Any structural modifications

Required documents

  • RequiredApplication for Residential PermitLogan City form (2026 edition); include project value covering all labor and materials
  • RequiredFloor PlanLayout showing room sizes, egress windows, and door locations — required per Logan Residential Basement Finish Checklist
  • RequiredElectrical PlanCircuit layout, panel capacity, smoke/CO detector locations
  • OptionalPlumbing PlanRequired if adding bathroom, wet bar, or utility sink

Fee schedule

Fee typeAmountNotes
Building Permit (valuation-based)Per Logan City fee table by project valuation — see Residential Building Permit fees aboveAssessed on project valuation per Logan City's published Building Permit Fee Resolution No. 20-09 (cited fee table) — same schedule as new residential construction.
Residential Plan Check Fee0.1% of construction valuation; minimum $15.00Logan City Building Permit Fees — Resolution No. 20-09
Electrical Permit8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Plumbing Permit (if applicable)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Mechanical Permit (if applicable)8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of building permit feeLogan City Building Permit Fees — Resolution No. 20-09

Accessory Dwelling Unit (ADU) Permit

Verified

Required for construction of an accessory dwelling unit on a residential property in Logan. The building permit fee is valuation-based; zoning eligibility must be confirmed with Logan Community Development before applying.

Verified 2026-07-01 · Source

Requirements

  • Property must be in an eligible residential zone — verify with Logan Community Development
  • ADU must meet minimum and maximum size requirements per Logan zoning code
  • Must comply with all setback requirements for the zone

Required documents

  • RequiredApplication for Residential PermitLogan City form (2026 edition); include full project value for all labor and materials
  • RequiredConstruction PlansFloor plan, elevations, sections, and structural details
  • RequiredSite PlanShowing ADU placement, setbacks, parking, and access
  • RequiredEnergy ComplianceREScheck or equivalent energy calculation

Fee schedule

Fee typeAmountNotes
Building Permit (valuation-based)Per Logan City fee table by project valuation — see Residential Building Permit fees aboveAssessed on project valuation per Logan City's published Building Permit Fee Resolution No. 20-09 (cited fee table). An ADU is new residential construction and is fee-assessed identically to the Residential Building Permit schedule — no separate ADU-specific fee line exists.
Residential Plan Check Fee0.1% of construction valuation; minimum $15.00Logan City Building Permit Fees — Resolution No. 20-09
Electrical Permit8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Plumbing Permit8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
Mechanical Permit8% of the Building Permit FeeLogan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of building permit feeLogan City Building Permit Fees — Resolution No. 20-09

Siding & Window Replacement Permit

Verified

Required for complete re-siding or window replacements that change opening sizes in Logan. Logan's fee schedule lists a specific flat fee for this permit type.

Verified 2026-06-30 · Source

Requirements

  • Complete re-siding of a structure or changing siding material type
  • Window or door replacement that changes the opening size (structural header change)
  • Adding new window or door openings

Required documents

  • RequiredResidential Permit ApplicationLogan City Application for Residential Permit (2026 edition); describe scope of work
  • OptionalContractor LicenseValid Utah contractor license (Utah DOPL) if not performed by homeowner

Fee schedule

Fee typeAmountNotes
Siding and/or Window Replacement Permit$50.00Logan City Building Permit Fees — Resolution No. 20-09
State Surcharge1% of permit feeLogan City Building Permit Fees — Resolution No. 20-09

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-06-27)Later version (2026-07-16) →View current record →All versions →

Permalink: /utah/cache-county/logan/as-of/2026-06-30/

Snapshot date: 2026-06-30

Commit: 9e5cbba