Skip to main content
PermitBase

This is PermitBase’s published record for Nibley as of 2026-07-08. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Nibley building permits

Verified

Nibley, Utah — as published 2026-07-08.

Verified 2026-07-08 · Source

Codes adopted

2021 International Residential Code (IRC) — Nibley City Building Department page states: 'Nibley is currently using the ICC Codes as amended by the state of Utah'; per Utah Code § 15A-2-103(1)(b), the 2021 IRC continues in force statewide (unchanged in the July 1, 2026 update).2021 International Building Code (IBC) — per Utah Code § 15A-2-103(1)(a), effective through June 30, 2026; 2024 IBC takes effect statewide July 1, 2026.2021 International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel Gas Code (IFGC), International Energy Conservation Code (IECC), International Existing Building Code (IEBC), International Swimming Pool and Spa Code (ISPSC) — all adopted statewide per Utah Code § 15A-2-103, as amended by the State of Utah, per Nibley's own 'ICC Codes as amended by the state of Utah' statement.2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g), statewide in force.

Permit types & fees

Residential Building Permit

Verified

Required for new single-family residential construction and any work regulated by the adopted 2021 IRC/IBC in Nibley. Nibley issues its own building permits independently of Cache County (confirmed via the county's own Building Division page, which lists Nibley among cities that 'issue their own permits'). Fees are valuation-based per Nibley's Consolidated Fee Schedule, using the same IRC-derived formula structure as the statewide model fee schedule.

Verified 2026-07-08 · Source

Requirements

  • New single-family residential construction or work regulated by the adopted 2021 IRC/IBC
  • Two copies of engineered, stamped (if applicable), to-scale plans; electronic plans may be submitted with the application
  • To-scale plot plan showing setbacks and location of project/building as well as intended location of utility services
  • Engineering calculations, Manual J/S/D, and Res-Check paperwork
  • SWPPP compliance documentation (if necessary), using Nibley's Common Plan SWPPP Template and the State of Utah Notice of Intent (NOI)
  • Compliance with NCC 17.10.010 Finished Floor Elevation groundwater/basement standards where applicable

Required documents

  • RequiredBuilding Permit ApplicationSubmitted online via Nibley's CivicReview application portal, linked from the official Building Department page.
  • RequiredEngineered/Stamped Plans (two copies, to-scale)Per Nibley's official Building Department page general submittal requirements; electronic plans and application can be submitted electronically.
  • RequiredTo-Scale Plot PlanShowing setbacks and location of project/building as well as intended location of utility services, per Nibley's official Building Department page.
  • RequiredEngineering Calculations / Manual J, S, D / Res-Check PaperworkRequired documentation per Nibley's official Building Department page general submittal requirements.
  • OptionalSWPPP Compliance DocumentationRequired if necessary, using Nibley's Common Plan SWPPP Template and the State of Utah Notice of Intent (NOI), both linked from the official Building Department page.

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation-based (Nibley City Consolidated Fee Schedule)$1–$500: $24.00 flat. $501–$2,000: $24 for the first $500 plus $3 for each additional $1,000 (or fraction thereof). $2,001–$40,000: $69 for the first $2,000 plus $11 for each additional $1,000 (or fraction thereof). $40,001–$100,000: $487 for the first $40,000 plus $9 for each additional $1,000 (or fraction thereof). $100,001–$500,000: $1,027 for the first $100,000 plus $7 for each additional $1,000 (or fraction thereof). $500,001–$1,000,000: $3,827 for the first $500,000 plus $5 for each additional $1,000 (or fraction thereof). $1,000,001–$5,000,000: $6,327 for the first $1,000,000 plus $3 for each additional $1,000 (or fraction thereof). $5,000,001 and over: $18,327 for the first $5,000,000 plus $1 for each additional $1,000 (or fraction thereof).Nibley City Consolidated Fee Schedule (2024, current as of page retrieval 2026-07-08), 'Building Permit Fees' table: valuation 'according to building inspector's review,' based on 'formula below or latest State adopted IRC manual building permit fees.'
Plan Review Fee0.1% of valuation of the improvementNibley City Consolidated Fee Schedule, Building Permit Fees section: 'Plan Review Fee — 0.1% of valuation of the improvement. Additional fees for inspections outside of normal business hours may be charged according to IRC fee schedule.'
State Collected 1% Fee1% of Building Permit FeesNibley City Consolidated Fee Schedule, Impact Fees section: 'State Collected 1% Fee — 1% of Building Permit Fees.'
Sewer Impact Fee (1" Service)$1,425.00Nibley City Consolidated Fee Schedule, Impact Fees section. Additional per-size tiers published: 2" Service $4,629.00; 3" Service $8,685.00; 4" Service $14,478.00; Multifamily Unit/Per-Door Charge and ADU $1,189.00.
Water Impact Fee (1" Service)$3,363.00Nibley City Consolidated Fee Schedule, Impact Fees section. Additional per-size tiers published: 2" Service $10,733.00; 3" Service $20,137.00; 4" Service $33,568.00; Multifamily Unit/Per-Door Charge and ADU $2,757.00.
Park Impact Fee (per Single Family Home/ADU)$9,003.00Nibley City Consolidated Fee Schedule, Impact Fees section.
Transportation Impact Fee (Single Family Home)$887.00 per unitNibley City Consolidated Fee Schedule, Impact Fees section.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nibley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-16) →View current record →All versions →

Permalink: /utah/cache-county/nibley/as-of/2026-07-08/

Snapshot date: 2026-07-08

Commit: 9184d5d

Reproducible from PermitBase’s version-controlled dataset, commit 9184d5d.