Bountiful building permits

Verified

Bountiful, Utah — as published 2026-07-17.

Verified 2026-06-30 · Source

Codes adopted

2021 International Residential Code (IRC) with Appendices AE and AQ — residential construction; as adopted by the State of Utah (Utah Code § 15A-2-103(1)(b)/(k)/(c)); unaffected by the 7/1/2026 statute revision, continues in force; Bountiful Design Criteria, rev. Oct 13, 20252015 International Residential Code Chapter 11 (residential energy provisions) — per Bountiful Design Criteria, rev. Oct 13, 2025 (statewide residential energy baseline per Utah Code § 15A-2-103)2024 International Building Code (IBC) with Appendices C and J — commercial construction; Utah Code § 15A-2-103(1)(a); effective 2026-07-01, superseded the 2021 edition2024 International Mechanical Code (IMC) — commercial; Utah Code § 15A-2-103(1)(e); effective 2026-07-01, superseded the 2021 edition2024 International Plumbing Code (IPC) — commercial; Utah Code § 15A-2-103(1)(d); effective 2026-07-01, superseded the 2021 edition2024 International Fuel Gas Code (IFGC) — commercial; Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition2024 International Energy Conservation Code (IECC) — commercial; Utah Code § 15A-2-103(1)(h); effective 2026-07-01, superseded the 2021 edition2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective 2026-07-01, superseded the 2021 edition2021 International Fire Code (IFC) — commercial; Bountiful Design Criteria, rev. Oct 13, 20252024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition; CONFIRMED 2026-07-17: the live Bountiful Design Criteria PDF (still dated Rev. October 13, 2025, unchanged/not reissued) explicitly lists '2021 International Swimming Pool and Spa Code' — the city has NOT yet published an updated Design Criteria reflecting the 2024 ISPSC (or the other 2024 commercial code editions) despite the statute taking effect 2026-07-01; the statutory 2024 editions govern by operation of Utah Code regardless, but Bountiful's own summary sheet is stale on this point — call (801) 298-6125 to confirm practical enforcement if this matters for a specific project2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force; Bountiful Design Criteria, rev. Oct 13, 2025NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC (residential provisions) replaced the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). The 2021 IRC and 2023 NEC were unaffected and remain in force.

Permit types & fees

Residential Building Permit

Verified

Required for new residential construction, additions, structural alterations, and work requiring plan review in Bountiful, governed by the 2021 IRC. All permits are applied for through the Cityinspect online portal.

Verified 2026-07-01 · Source

Requirements

  • New single-family, duplex, or townhome construction
  • Additions requiring structural work
  • Structural modifications — load-bearing wall removal, foundation alterations
  • Conversion of non-habitable space to habitable space

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk. All permits are submitted through Cityinspect.
  • RequiredConstruction PlansComplete drawings to scale — site plan, floor plans, elevations, sections, structural details. Uploaded electronically through Cityinspect.
  • RequiredEnergy Compliance DocumentationPer 2015 IRC Chapter 11 (residential energy); REScheck or equivalent calculation demonstrating compliance.
  • OptionalEngineered Truss PlansSealed truss layouts for new construction with trusses.
  • RequiredBond Form — New ResidentialStreet damage cash deposit bond form available on Building Dept page; $3,000 deposit required for new SFR.

Fee schedule

Fee typeAmountNotes
Application Fee — New Home$500 (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023), Engineering/Building Permits section
Application Fee — Addition$100 (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Application Fee — Remodel$100 (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Building Permit FeeValuation-based per 1997 Uniform Administrative Code using current ICC valuation dataGrounded/verified: assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6), re-confirmed live 2026-07-01. Application fee credited against total.
Plan Review Fee — Residential Single Family29% of permit feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Plan Review Fee — Commercial65% of permit feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
South Davis Metro Fire Impact Fee$644 per SFR / condominium unit / apartment unitBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023); also per 5,000 sq ft (or fraction) for commercial
Street Damage Cash Deposit — New Single Family Residential$3,000 per driveway/accessBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Street Damage Cash Deposit — Single Family Addition$1,500 per driveway/accessBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
State Surcharge~1% of permit fee (state-mandated, collected by city)Utah state surcharge; confirmed in Bountiful Electrical Policy (eff. Sep 25, 2023): $0.75 per $75 permit, $1.50 per $150 permit

Electrical Permit

Verified

Required for electrical work in Bountiful including service changes, panel upgrades, new circuits, and rewiring. Governed by the 2023 NEC (Utah Code § 15A-2-103). The Change of Service / Electrical Policy (eff. Sep 25, 2023) governs service upgrades. Apply through Cityinspect. EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; neither the Change of Service / Electrical Policy nor the FY2023-2024 Schedule of Rates and Fees publishes an EV-specific line item — a charger circuit would be billed as new wiring/rewire (valuation-based) or, if it requires a panel/service change, under the Change of Service fee tiers.

Verified 2026-07-17 · Source

Requirements

  • Change of electrical service (overhead or underground)
  • Electrical panel upgrade or interior panel replacement
  • New electrical circuits, rewiring, or adding outlets/switches/fixtures
  • Solar panel electrical connections
  • Generator connections

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalElectrical Plan / Single-Line DiagramRequired for service changes — panel schedule and circuit layout. See Change of Service / Electrical Policy (eff. Sep 25, 2023) for service conductor clearance requirements.
  • OptionalUtah Electrical Contractor License (DOPL)Required for work not performed by the homeowner on their own primary residence.

Fee schedule

Fee typeAmountNotes
Overhead Change of Service Permit$75.50 ($75.00 permit + $0.75 state fee)Bountiful City Change of Service / Electrical Policy (eff. Sep 25, 2023)
Underground Change of Service Permit$151.50 ($150.00 permit + $1.50 state fee)Bountiful City Change of Service / Electrical Policy (eff. Sep 25, 2023)
Single Inspection Permit (minor electrical work)$75.00 (plus state surcharge ~1%)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Rewire / Interior Panel ReplacementValuation-based per 1997 Uniform Administrative Code (current ICC data)Bountiful City Change of Service / Electrical Policy (eff. Sep 25, 2023): 'Rewire and interior panel changes are based on project valuation per State standards.'

Plumbing Permit

Verified

Required for plumbing installations, alterations, and repairs in Bountiful including water heaters, fixture additions, and gas line work. Governed by the 2024 IPC (Utah Code § 15A-2-103(1)(d)), effective July 1, 2026 (superseded the 2021 edition). Apply through Cityinspect.

Verified 2026-07-01 · Source

Requirements

  • New plumbing fixture installations (sinks, toilets, showers)
  • Water heater installation or replacement
  • Water line or sewer line replacement or extension
  • Gas line installation or modification
  • Backflow prevention device installation

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalUtah Plumbing Contractor License (DOPL)Required for work not performed by the homeowner on their primary residence.

Fee schedule

Fee typeAmountNotes
Single Inspection Permit (minor plumbing)$75.00 (plus state surcharge ~1%)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023). Bountiful does not publish a separate fixture-count or per-fixture fee table.
Plumbing Permit (larger projects)Valuation-based per 1997 Uniform Administrative Code (current ICC data)Grounded/verified: assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6), re-confirmed live 2026-07-01.

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in Bountiful. Governed by the 2024 IMC (Utah Code § 15A-2-103(1)(e)), effective July 1, 2026 (superseded the 2021 edition). Apply through Cityinspect.

Verified 2026-07-01 · Source

Requirements

  • Furnace or boiler installation or replacement
  • Air conditioning system installation or replacement
  • Ductwork installation or major modification
  • Evaporative cooler installation
  • Fireplace or wood-burning stove installation

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, heat pump, or evaporative cooler
  • OptionalUtah HVAC Contractor License (DOPL)Required for work not performed by the homeowner on their primary residence.

Fee schedule

Fee typeAmountNotes
Single Inspection Permit (minor mechanical work)$75.00 (plus state surcharge ~1%)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023). Bountiful does not publish a separate BTU-tier or appliance-type fee table.
Mechanical Permit (larger projects)Valuation-based per 1997 Uniform Administrative Code (current ICC data)Grounded/verified: assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6), re-confirmed live 2026-07-01.

Roofing Permit

Verified

Required for roof replacement, re-roofing, and structural roof repairs in Bountiful. The Reroof & Roof Repair Policy (revised March 31, 2025) governs all roofing work under the 2021 IRC. Apply through Cityinspect.

Verified 2026-07-17 · Source

Requirements

  • Complete roof replacement (tear-off and re-roof) — all layers must be removed per IRC R908.3
  • Roof recover (overlay) — permitted only where IRC R908.3.1 conditions are met; maximum two total layers
  • Structural roof repairs or modifications
  • Roof repairs over 20% of one roof surface or over 10% of total roof area require a permit; minor repairs below these thresholds do not (Reroof Policy)

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalUtah Roofing Contractor License (DOPL)Required if work is not performed by the homeowner on their primary residence.

Fee schedule

Fee typeAmountNotes
Residential Reroof or Roof Recover Permit (over-the-counter)$151.50 ($150.00 permit + $1.50 state fee)CORRECTED 2026-07-17: verbatim from Bountiful City Reroof & Roof Repair Policy (revised March 31, 2025), p.2, Residential Reroof or Roof Recover Procedures item B: 'The cost is $151.50. ($150.00 permit & $1.50 state fee)'. Supersedes a prior generic '$75 Single Inspection Permit' figure sourced from Ord. 2023-01, which does not govern reroof/recover work — the reroof-specific policy is the correct, more specific source for this permit type.
Commercial Re-Roof PermitValuation-based per City and State standardsBountiful City Reroof & Roof Repair Policy (revised March 31, 2025), p.3, Commercial Re-Roof Procedures item B: 'The cost is valuation based per City and State standards.'

Solar Panel Permit

Verified

Required for installation of rooftop or ground-mounted solar PV systems in Bountiful. Bountiful has its own municipal electric utility — Bountiful City Light & Power (BCLP). A NET Metered Agreement is required for all grid-tied systems. Apply through Cityinspect.

Verified 2026-06-30 · Source

Requirements

  • Rooftop or ground-mounted solar PV installation
  • Battery storage system installation (separate Solar Packet — Battery System available on Building Dept page)
  • Electrical service upgrade for solar interconnection (separate change-of-service permit required)

Required documents

  • RequiredSolar Permit Application (Cityinspect) + $50 Application FeeApply online; pay $50 fee by calling Engineering at (801) 298-6125 BEFORE submitting. Incomplete applications are not accepted.
  • RequiredSite PlanBird's-eye view showing panel placement, north arrow, scale, date, and street address. For ground-mounted: property lines, dimensions, easements, adjacent structures within 50 feet.
  • RequiredOne-Line Diagram (Two sets)Electrical diagram following Bountiful City Light & Power sample diagram (Attachment 4 in Solar Packet).
  • RequiredEngineer Analysis LetterLicensed engineer's analysis of existing roof structure with added solar equipment and uplift resistance, based on site visit or photos. Must confirm compliance with 145 mph Exposure B per ASCE 7.
  • RequiredSolar Panel Questions Form (Attachment 2)Array dimensions, panel count, total kW rating, roof pitch, roofing material, age and condition, and roof construction type.
  • RequiredPhotovoltaic System NET Metered Agreement (Attachment 3)Signed by property owner; required for all grid-tied systems connecting to BCLP. BCLP retains all Renewable Energy Certificates.
  • RequiredEquipment Spec SheetsSolar panels, inverter, and racking product data sheets.
  • RequiredElectrical Service PhotosThree clear photos: location (10 ft either side), panel dead front ON, panel dead front OFF.

Fee schedule

Fee typeAmountNotes
Solar Permit Application Fee$50Bountiful City Solar Packet — Net Meter, Attachment 1 and NET Meter Solar Panel Permitting step guide (a page within the same packet PDF is dated 9/30/25, so this is not literally undated as previously recorded — re-confirmed live 2026-07-17). Paid by calling Engineering at (801) 298-6125 prior to submittal. NOTE: the same 9/30/25 step-guide page shows an example total-cost table (Application Fee $50 + NET Metering $578 + Building Permit for City $300 + Building Permit for State $3.50 + Building Permit for Plan Check $101.50 = $1,033.00 TOTAL) for a sample project; the $578 NET Metering connect fee is NOT currently itemized elsewhere in this permitType's fees array (Ord. 2023-01's FY2023-2024 schedule lists a flat '$525.00 Photovoltaic Service Connect fee, collected by Planning Dept' instead) — could not fully reconcile whether $578 is a current update to that $525 connect fee or a different line item; flagged for follow-up rather than asserted as fact.
Change of Service — Overhead (if upgrading service as part of solar)$75 additionalBountiful City Solar Packet — Net Meter, Attachment 2: 'add $75.00' for overhead change of service.
Change of Service — Underground (if upgrading service as part of solar)$150 additionalBountiful City Solar Packet — Net Meter, Attachment 2: 'add $150.00' for underground change of service.

Deck Permit

Verified

Required for new deck construction, structural modifications to existing decks, and decks attached to the house in Bountiful. Fees are valuation-based. Apply through Cityinspect.

Verified 2026-07-01 · Source

Requirements

  • New deck construction attached to or detached from the house
  • Decks higher than 30 inches above grade
  • Structural modifications to existing decks
  • Adding or replacing a deck ledger connection

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • RequiredConstruction DrawingsFraming plan with beam/joist sizes, post locations, footing details, and ledger attachment method
  • RequiredSite PlanDeck location showing setbacks from property lines and relationship to existing structure

Fee schedule

Fee typeAmountNotes
Application Fee — Remodel/Addition$100 (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Building PermitValuation-based per 1997 Uniform Administrative Code (current ICC data)Grounded/verified: assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6), re-confirmed live 2026-07-01.
Plan Review Fee — Residential Single Family29% of permit feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Street Damage Cash Deposit (Deck > 500 sq ft)$1,500Grounded/verified: Bountiful City Ord. 2023-01 fee schedule (p.6) lists this under 'Retaining, Pool, Accessory Structure, Deck >500 sqft' at $1,500 — confirmed against the live PDF 2026-07-01.

Basement Finish Permit

Verified

Required for finishing or remodeling an unfinished basement in Bountiful, including framing, electrical, plumbing, and mechanical work. Governed by the 2021 IRC. Apply through Cityinspect.

Verified 2026-07-01 · Source

Requirements

  • Framing walls in an unfinished basement
  • Adding a bedroom (requires egress window per IRC R310)
  • Adding a bathroom (requires separate plumbing permit)
  • Electrical wiring for new rooms
  • Any structural modifications

Required documents

  • RequiredBuilding Permit Application (Cityinspect) with $100 Remodel FeeApply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk; $100 application fee credited to total permit cost.
  • RequiredFloor PlanLayout showing room sizes, egress windows, door locations, and smoke/CO detector placement
  • OptionalElectrical PlanCircuit layout, panel capacity verification, smoke/CO detector locations
  • OptionalMechanical PlanHVAC supply/return for new rooms, combustion air provisions for furnace room

Fee schedule

Fee typeAmountNotes
Application Fee — Remodel$100 (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Building PermitValuation-based per 1997 Uniform Administrative Code (current ICC data)Grounded/verified: assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6), re-confirmed live 2026-07-01.
Plan Review Fee — Residential Single Family29% of permit feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)

Accessory Dwelling Unit (ADU)

Verified

Bountiful City allows both internal and detached ADUs. Internal ADUs are reviewed and approved by City Staff. Detached ADUs are a conditional use requiring Bountiful City Administrative Committee approval prior to the building permit. Apply through Cityinspect.

Verified 2026-07-01 · Source

Requirements

  • Internal ADUs: staff-reviewed and approved; apply for building permit directly
  • Detached ADUs: conditional use — obtain Administrative Committee approval first
  • Must comply with Bountiful City Land Use Code (see bountifulutah.gov/planning-and-zoning)
  • Separate entrance from primary dwelling required

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk. For detached ADUs, obtain Administrative Committee conditional use approval first.
  • RequiredConstruction PlansFull construction drawings — floor plan, elevations, sections, and structural details
  • RequiredSite PlanProperty layout showing both units, setbacks, parking, and access

Fee schedule

Fee typeAmountNotes
Application Fee — Remodel (internal ADU) or New Home (detached ADU)$100 remodel or $500 new (credited to total permit cost)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
Building PermitValuation-based per 1997 Uniform Administrative Code (current ICC data)Grounded/verified: ADU new construction/internal conversion is treated as standard building-permit work, assessed on project valuation per Bountiful's published fee schedule (Ord. 2023-01, Schedule of Rates and Fees FY2023-2024, eff. May 9, 2023, Engineering Fees — Building Permits section, p.6); ADU program itself re-confirmed live on bountifulutah.gov/Bountiful-City-Planning---ADU-Information 2026-07-01 (internal ADU staff-approved; detached ADU is a conditional use requiring Administrative Committee approval).
Plan Review Fee — Residential Single Family29% of permit feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023)
South Davis Metro Fire Impact Fee$644 per dwelling unitBountiful City Ord. 2023-01 (eff. May 9, 2023). Utah HB 82 (2021) may reduce or waive impact fees for internal ADUs — confirm with Bountiful Building Dept at (801) 298-6125.

Fence Permit

Verified

Required for new fence installation in Bountiful. Bountiful charges a flat $25 fee. Height and setback restrictions apply based on zoning district. Apply through Cityinspect.

Verified 2026-06-30 · Source

Requirements

  • Any new fence construction
  • Replacement of existing fence (confirm with Building Dept whether like-for-like in same location requires a permit)

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalSite PlanShowing fence location relative to property lines and setbacks

Fee schedule

Fee typeAmountNotes
Fence Permit$25 flat feeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023). COULD NOT INDEPENDENTLY RE-CONFIRM 2026-07-17: read the full 26-page Ord. 2023-01 Exhibit A (Engineering Fees, Planning Fees, and all other fee sections) verbatim and found no explicit 'Fence Permit $25' line item; also not found on the Building Dept or Applications-Forms pages. Not asserting this figure is wrong — no contradicting evidence was found either — but it could not be positively re-grounded against the cited source this session. Call (801) 298-6125 to confirm before relying on this figure.

Water Heater Permit

Verified

Required for water heater installation, replacement, or conversion (tank to tankless) in Bountiful. A subset of the plumbing permit for this common project. Apply through Cityinspect.

Verified 2026-06-30 · Source

Requirements

  • Water heater replacement (including like-for-like swaps)
  • New water heater installation
  • Conversion from tank to tankless water heater
  • Gas line modification for water heater

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk
  • OptionalUtah Plumbing Contractor License (DOPL)Required if work is not performed by the homeowner on their primary residence.

Fee schedule

Fee typeAmountNotes
Single Inspection Permit$75.00 (plus state surcharge ~1%)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023). Water heater replacement is a single-inspection permit in Bountiful.

Demolition Permit

Verified

Required to demolish all or part of a structure in Bountiful (apply through Cityinspect). A demolition permit is a building permit; for a historic site the City may delay issuance up to one week for documentation. State/federal rules add a Davis County dust-control plan and a minimum 10-working-day asbestos (NESHAP) notification to the Utah Division of Air Quality before demolition may begin.

Verified 2026-07-17 · Source

Requirements

  • Complete demolition of any structure
  • Partial demolition involving structural elements or load-bearing walls
  • Federal NESHAP asbestos inspection required for structures built before approximately 1980

Required documents

  • RequiredDemolition Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk; include scope of demolition and disposal plan
  • OptionalAsbestos Survey (NESHAP)Federal NESHAP asbestos inspection required for structures built before approximately 1980 — coordinate with Utah DEQ
  • RequiredUtility Disconnect ConfirmationProof that gas, electric, water, and sewer are disconnected by the respective utility companies prior to demolition

Fee schedule

Fee typeAmountNotes
Demolition permit (issued as a building permit)Assessed on project valuation using Bountiful's building-permit fee schedule (ICC valuation by floor area); no separate flat demolition feeBountiful City Code Sec. 4-5-101 (Building Permit Fees), verbatim re-confirmed 2026-07-17: 'Whenever a building permit is required by the codes which are adopted in this Chapter, permit fees shall be as outlined in the fee schedules provided in the Uniform Administrative Code, with the exception that the plan review fees will be charged in accordance with State law. The valuation of the building construction shall be determined by the current cost per square foot of floor area of such construction as established by the International Conference of Building Officials...' CORRECTED 2026-07-17: Sec. 4-5-103 is titled 'Demolition of Historic Sites – Notification' and its text (mirrored by Sec. 3-2-107) covers ONLY a possible one-week documentation delay for demolition of HISTORIC sites — it does not itself state that demolition generally requires a permit. Bountiful City Code Title 4 Ch.5 (Sec. 4-5-101 through 4-5-109, fully reviewed) has no separate section generally requiring a demolition permit; that requirement instead flows from the adopted IBC/IEBC (Section 105-series permit provisions) plus Sec. 4-5-106 (Construction Without Required Permits Unlawful). Since the code sets building-permit fees by valuation with no separate flat demolition line item, application fee is credited toward the total permit fee per the fee schedule (Ord. 2023-01).

Commercial Building Permit

Verified

Required for new commercial building construction in Bountiful, governed by the 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 2026-07-01). Bountiful's fee schedule prices commercial building permits differently from residential: both the application fee and the plan review fee are set at 65% of the underlying (valuation-based) building permit fee, rather than a flat dollar amount. Apply through Cityinspect.

Verified 2026-07-19 · Source

Requirements

  • New commercial building construction (shell, ground-up, or new structure)
  • Electronic copy of plans and engineering
  • Site plan to scale
  • Structural engineering plan review
  • SWPPP (Storm Water Pollution Prevention Plan)
  • Energy code compliance documentation for the adopted 2024 IECC
  • Contractor license number (Utah DOPL)

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk. All permits are submitted through Cityinspect.
  • RequiredConstruction Plans and EngineeringComplete drawings to scale — site plan, floor plans, elevations, sections, structural details, sealed by a licensed design professional.
  • RequiredSWPPP (Storm Water Pollution Prevention Plan)Required for new commercial construction; reviewed under Storm Water Fees (Ord. 2023-01, Engineering Fees, p.6) — Review SWPPP base fee $150 (up to 2 hrs, additional staff time $75/hr).
  • RequiredEnergy Code Compliance DocumentationCOMcheck or equivalent demonstrating compliance with the adopted 2024 IECC (Utah Code § 15A-2-103(1)(h)).

Fee schedule

Fee typeAmountNotes
Commercial Building Permit Application Fee65% of Permit FeeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023), Engineering Fees — Building Permits (p.6): 'Commercial Building Permit Application Fee Each* 65% of Permit Fee' with footnote 'Application Fees will be credited to the total cost of the Building Permit.' Verified live from the PDF 2026-07-19.
Building Permit Plan Review Fee — Commercial65% of Permit FeeBountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023), Engineering Fees — Building Permits (p.6): 'Building Permit Plan Review Fee - Commercial Each 65% of Permit Fee.'
Building Permit Fee (base, valuation-based)Valuation-based per 1997 Uniform Administrative Code using current ICC valuation dataBountiful City Ord. 2023-01, Engineering Fees — Building Permits (p.6): 'Building Valuation is based on current ICC valuation data' / 'Per 1997 Uniform Administrative Code.' Same formula applies to residential and commercial; the 65% application and plan-review multipliers above are calculated against this base fee for commercial projects.
South Davis Metro Fire Impact Fee — Commercial$644.00 per 5,000 sq ft (or fraction) of commercial buildingBountiful City Ord. 2023-01, Engineering Fees (p.6): '$644.00 ... per SFR / Condominium Unit / Apartment or per 5,000 sqft (or fract) commercial.'
Street Damage Cash Deposit — New Commercial$4,000.00 per Access (Drive Approach)Bountiful City Ord. 2023-01, Engineering Fees — Street Damage Cash Deposit (p.6): 'New Commercial Each $4,000.00 per Access (Drive Approach).'
Architectural & Site Plan Review — Non-Residential (Planning Dept)$1,500.00Bountiful City Ord. 2023-01, Planning Fees — Land Use Development Fees (p.8): 'Architectural & Site Plan Review - Non-Residential $1,500.00.' Charged separately as preliminary and final review (see fee-schedule note: 'Architectural & Site Plan Review requires a separate payment for preliminary and final').
State Building Fee Surcharge~1% of permit fee (state-mandated, collected by city)Utah state surcharge, applied to the base building permit fee, consistent with the state-surcharge treatment documented on Bountiful's residential-building-permit entry and Electrical Policy (eff. Sep 25, 2023).

Commercial Tenant Improvement / Tenant Finish Permit

Verified

Required for interior remodel, tenant finish, and tenant-improvement work inside an existing commercial building in Bountiful. Bountiful's Ord. 2023-01 fee schedule does not maintain a separate commercial-remodel fee table from new commercial construction — the same 65%-of-permit-fee application and plan-review multipliers apply, but the Street Damage Cash Deposit steps down to the 'Commercial Remodel / Addition' tier. Apply through Cityinspect.

Verified 2026-07-19 · Source

Requirements

  • Interior remodel, tenant finish, or tenant improvement within an existing commercial building
  • Electronic copy of plans and engineering, where structural or MEP scope is involved
  • Wall section and rebar details where structural work is included
  • Site plan (if exterior/site changes are part of scope)
  • Contractor license number (Utah DOPL)

Required documents

  • RequiredBuilding Permit Application (Cityinspect)Apply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk.
  • RequiredConstruction PlansInterior floor plan, MEP layout, and structural details as applicable to the tenant improvement scope.
  • OptionalEnergy Code Compliance DocumentationCOMcheck or equivalent where the adopted 2024 IECC applies to the scope of work (e.g., new HVAC, envelope changes).

Fee schedule

Fee typeAmountNotes
Commercial Building Permit Application Fee65% of Permit FeeBountiful City Ord. 2023-01, Engineering Fees — Building Permits (p.6): 'Commercial Building Permit Application Fee Each* 65% of Permit Fee.' The fee schedule's line item is labeled generically ('Commercial Building Permit') and is not split into separate new-construction vs. tenant-improvement rows — the same multiplier applies to remodel/tenant-finish work as to new commercial construction.
Building Permit Plan Review Fee — Commercial65% of Permit FeeBountiful City Ord. 2023-01, Engineering Fees — Building Permits (p.6): 'Building Permit Plan Review Fee - Commercial Each 65% of Permit Fee.'
Building Permit Fee (base, valuation-based)Valuation-based per 1997 Uniform Administrative Code using current ICC valuation dataBountiful City Ord. 2023-01, Engineering Fees — Building Permits (p.6): 'Building Valuation is based on current ICC valuation data' / 'Per 1997 Uniform Administrative Code.'
Street Damage Cash Deposit — Commercial Remodel / Addition$1,500.00 / $3,000.00Bountiful City Ord. 2023-01, Engineering Fees — Street Damage Cash Deposit (p.6): 'Commercial Remodel / Addition Each $1,500.00 / $3,000.00.' The published table lists two dollar figures on this line without further breakdown of which projects fall into each tier; quoted verbatim as published rather than guessed at. Call (801) 298-6125 to confirm which figure applies to a specific tenant-improvement scope.
Single Inspection Permit (minor tenant-finish work, over-the-counter)$75.00 (plus ~1% state surcharge)Bountiful City Ord. 2023-01, Engineering Fees — Building Permits (p.6): 'Single Inspection Permit Each $75.00.' Applies to minor scopes not requiring full plan review; not specific to commercial, but available for small tenant-finish jobs at the Building Department's discretion.

EV Charger / EVSE Permit

Bountiful City does not publish a distinct "EV Charger" or "EVSE" fee line item. Its Building Department page and Applications & Forms page list no EV-specific application, and its published Change of Service / Electrical Policy (eff. Sep 25, 2023) prices electrical work by service type — Overhead Change of Service, Underground Change of Service, Single Inspection Permit, and valuation-based rewire/panel work — rather than by equipment type. Installing an EV charger that adds a new dedicated circuit without a service change would most plausibly fall under the city's Single Inspection Permit (minor electrical work) category or the valuation-based rewire/panel category, but no city document explicitly names EV chargers.

Reviewed 2026-07-20 · Source

Requirements

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Bountiful City
  • Dedicated 240V circuit and/or panel capacity installed by a licensed electrician
  • If the installation requires a change to the electrical service (overhead or underground), the corresponding Change of Service Permit process applies

Required documents

  • RequiredElectrical Permit Application (via CityInspect online portal)Bountiful City processes building and electrical permits through the CityInspect online portal; no distinct EV-charger form exists as of this review.

Fee schedule

Fee typeAmountNotes
Single Inspection Permit (minor electrical work — closest applicable category for a simple new circuit, not explicitly confirmed for EV chargers)$75.00 (plus state surcharge ~1%)Bountiful City Ord. 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023). No Bountiful document explicitly names EV chargers under this category; included as the most plausible applicable fee for a minor add-a-circuit EVSE install.
Rewire / Interior Panel Replacement (if a panel upgrade is needed to support the charger)Valuation-based per 1997 Uniform Administrative Code (current ICC data)Bountiful City Change of Service / Electrical Policy (eff. Sep 25, 2023): 'Rewire and interior panel changes are based on project valuation per State standards.'

Sign Permit

Verified

Required by Bountiful City Code Chapter 19 (Sign Regulations, Ord 2020.01) for erecting, installing, or painting any sign, or changing the face of any sign (temporary or permanent), except signs specifically exempted under § 14-19-109 (e.g., small on-premises directional signs, small residential signs, flags within size limits, A-Frame signs removed daily). Sign permits are reviewed and issued by the Bountiful City Planning Department (not the Building Department), per § 14-19-118 (Sign Permit Process). Bountiful's own fee schedule does not publish a distinct dollar figure for this permit — the Planning Fees table in Ordinance 2023-01 cross-references the Building/Engineering Dept.'s fee structure instead of pricing signs separately.

Verified 2026-07-21 · Source

Requirements

  • No person shall erect, install, or paint any sign, or change the face of any sign, whether temporary or permanent, without a sign permit from the Planning Department, except as specifically exempted by Chapter 19 (§ 14-19-118.A)
  • Signs allowed in all zones without a permit (§ 14-19-109): one on-premises directional sign ≤5 sq ft/4 ft height; national/political-subdivision flags ≤32 sq ft; any regulatory sign; residential single-family-zone signs ≤12 sq ft; residential multi-family-zone signs ≤24 sq ft; changeable copy area changes on an already-approved sign; political signs
  • Commercial-zone monument, freestanding/pole, wall, canopy/awning, projecting, and changeable-copy signs require a permit under the applicable zone section (§§ 14-19-111 through 14-19-115)
  • Temporary signs (banners, A-Frame, pedestal signs) generally require a permit under § 14-19-117, except a temporary A-Frame sign removed at the end of each business day
  • Any permanent sign involving electrical wiring/connections must be installed by a licensed and bonded contractor (§ 14-19-119.C)
  • Sign structures falling under the International Building Code (e.g., monument/freestanding sign foundations) require plans stamped by a Utah-licensed structural engineer (§ 14-19-118.I.1.c)

Required documents

  • RequiredSign Permit Application (Planning Department)Filed with the Planning Department on a form provided; must include all required fees and clear/complete graphics and written information showing compliance with Chapter 19 (§ 14-19-118.F). Contact Planning at (801) 298-6190.
  • RequiredSite Plan (Monument, Freestanding/Pole Signs)At least two copies showing location of existing/proposed signs, building locations within 50 ft on adjacent properties, property lines/dimensions, required setbacks, and landscaping, per § 14-19-118.I.1.
  • RequiredScaled Drawing / Sign Construction DetailsAccurately dimensioned drawing showing height, color, square footage, sign composition, illumination type, and how the sign will appear from the street; details of construction including electrical plan and foundation scheme (§ 14-19-118.I.1.b-c, I.2).
  • OptionalStructural Engineer Stamp (where IBC applies)If the sign constitutes a structure or otherwise falls under IBC jurisdiction, the foundation plan must be stamped and signed by a licensed Utah Professional Engineer (§ 14-19-118.I.1.c).
  • RequiredBusiness License / Additional InformationCurrent Bountiful City business license (or completed application), business address/phone, property owner address/phone, general and/or electrical contractor's license number, and value of the sign (§ 14-19-118.J).

Fee schedule

Fee typeAmountNotes
Sign PermitSee Engineering Dept. Fees (building permits) — no separate dollar figure is publishedBountiful City Ordinance 2023-01, Schedule of Rates and Fees FY2023-2024 (eff. May 9, 2023), Planning Fees — Land Use Development Fees table (p.8), verbatim line item: 'Sign Permit ... See Engineering Dept. Fees (building permits).' Fetched and confirmed live 2026-07-21. This is a cross-reference, not a waiver — signs are priced through the same Building/Engineering Dept. fee structure used for building permits generally (e.g., the $75 Single Inspection Permit for minor signage, or a valuation-based Building Permit fee for larger monument/freestanding signs requiring structural/IBC review), consistent with the pre-existing tip on this jurisdiction's residential- and commercial-building-permit entries.

Fire Sprinkler System Permit

Verified

Required for installation or modification of an automatic fire sprinkler (suppression) system in Bountiful. Fire protection system plan review and permitting for Bountiful is handled entirely by South Davis Metro Fire (SDMF), a special fire district headquartered in Bountiful (255 S 100 W) that also serves Centerville, North Salt Lake, West Bountiful, and Woods Cross — this is a separate submittal and fee from the City's own Cityinspect building permit process. Bountiful's own building-permit fee schedule (Ord. 2023-01) has no line item for fire sprinkler systems; SDMF sets and collects this fee directly under its own Fee Ordinance.

Verified 2026-07-21 · Source

Requirements

  • Installation, modification, or removal from service of an automatic fire protection (suppression) system, fire pumps and related fuel tanks, jockey pumps, controllers, or a standpipe system
  • Per International Fire Code Section 104.7.2, SDMF requires a 'technical opinion and report' (peer review) of plans for these systems
  • Projects with more than 10 sprinkler devices are treated as a deferred submittal and reviewed by a qualified third-party peer reviewer rather than by SDMF directly
  • Submit plan review application and plans to fireplans@sdmetrofire.gov, not through the City Building Department

Required documents

  • RequiredPlan Review ApplicationSDMF plan review application form, submitted with fire sprinkler plans to fireplans@sdmetrofire.gov
  • RequiredFire Sprinkler System PlansPlans, specifications, and hydraulic calculations for the automatic sprinkler system
  • OptionalThird-Party Peer Review ReportRequired for systems with more than 10 devices — a 'technical opinion and report' from an SDMF-approved third-party reviewer, per IFC 104.7.2

Fee schedule

Fee typeAmountNotes
Sprinkler Plan Review$100 per hour, minimum 1 hourSouth Davis Metro Fire Fee Ordinance (04/2024), 'PERMITS/PLAN REVIEWS/INSPECTIONS' section, line item 'Sprinkler - Plan Review ... $100 per hour, Minimum 1 hour' — fetched directly as a PDF and read verbatim 2026-07-21. SDMF's Plan Reviews webpage describes this imprecisely as 'will require a plan review fee of $100 if there are less than 10 devices' (confirmed live 2026-07-21 at sdmetrofire.gov/copy-of-plan-reviews-1).
Fire Sprinkler System Permit$300SDMF Fee Ordinance (04/2024), same section, verbatim: 'Fire sprinkler system permit (3 Inspections) ... $300.' This flat $300 permit fee includes 3 inspections and is separate from (in addition to) the hourly Sprinkler Plan Review fee above. SDMF's website independently confirms the $300 figure under 'SUPPRESSION REVIEWS - $300 (review /2 inspections)' — the formal Fee Ordinance's '3 Inspections' is treated as authoritative over the website's '2 inspections' wording since the ordinance is the dated, official fee-setting document.
Deferred Submittal (10+ devices)No additional SDMF plan review feeSouth Davis Metro Fire, Plan Reviews page (sdmetrofire.gov/copy-of-plan-reviews-1, fetched live 2026-07-21): if there are more than 10 devices, plans are reviewed by a qualified 3rd party reviewer and will not require an SDMF plan review fee. The third-party reviewer is paid separately by the applicant; the $300 permit fee itself is not stated as waived.

Fire Alarm System Permit

Verified

Required for installation or modification of a fire alarm and detection system in Bountiful. As with fire sprinkler permits, fire alarm plan review and permitting is handled by South Davis Metro Fire (SDMF) — the fire district headquartered in Bountiful that also serves Centerville, North Salt Lake, West Bountiful, and Woods Cross — separately from the City's own Cityinspect building permit process.

Verified 2026-07-21 · Source

Requirements

  • Installation or modification of a fire alarm and detection system and related equipment
  • Per International Fire Code Section 104.7.2, SDMF requires a 'technical opinion and report' (peer review) of plans for fire alarm systems
  • Deferred submittals reviewed by a third-party peer reviewer are still billed the same permit fee
  • Submit plan review application and plans to fireplans@sdmetrofire.gov, not through the City Building Department

Required documents

  • RequiredPlan Review ApplicationSDMF plan review application form, submitted with fire alarm plans to fireplans@sdmetrofire.gov
  • RequiredFire Alarm System PlansDevice locations, wiring diagrams, and system design for the fire alarm and detection system; if more than 10 devices, plans are deferred to a qualified third-party reviewer

Fee schedule

Fee typeAmountNotes
Fire Alarm Systems Plan Review$100 per hour, minimum 1 hourSouth Davis Metro Fire Fee Ordinance (04/2024), 'PERMITS/PLAN REVIEWS/INSPECTIONS' section, line item 'Fire Alarm Systems - Plan Review ... $100 per hour, Minimum 1 hour' — fetched directly as a PDF and read verbatim 2026-07-21.
Fire Alarm System Permit$200SDMF Fee Ordinance (04/2024), same section, verbatim: 'Fire alarm system permit (2 Inspections) ... $200.' SDMF's Plan Reviews webpage independently confirms this figure (fetched live 2026-07-21): 'ALARM REVIEWS - $200 - (review/2 inspections)' and states deferred (third-party-reviewed) submittals are billed the same $200.

Change of Use / Certificate of Occupancy Compliance

Verified

Bountiful City has no separately named or separately priced 'Change of Use Permit' product. Instead, Bountiful City Land Use Code § 14-1-106 ('Certificate of Occupancy and Use Compliance') makes it unlawful to occupy any building with a greater intensity of use or different occupancy than specifically provided for in its Certificate of Occupancy, and requires a new Certificate any time occupancy changes to a more intensive use. Separately, § 14-1-106.F ('Illegal Change of Use') makes it a class C misdemeanor to change the use of a structure or property to a use not permitted by current City ordinances without first obtaining required re-zoning, variance, or other use approvals. Where a use change does require such approval, it is priced through Bountiful's existing Planning Fees (Conditional Use Permit, Variance, Zoning Map Amendment, or Determination of Non-Compliance/Non-Conformance) rather than a distinct change-of-use fee.

Verified 2026-07-21 · Source

Requirements

  • It is unlawful to use or occupy, or to permit the use or occupancy of, any building or premises prior to issuance of a Certificate of Occupancy by the City (§ 14-1-106.A)
  • It is unlawful to occupy, or allow to be occupied, any building with a greater intensity of use or different occupancy than specifically provided for in the Certificate of Occupancy (§ 14-1-106.A)
  • A new Certificate of Occupancy is required any time the occupancy of a building changes to a more intensive use (§ 14-1-106.B)
  • No building permit shall be granted for a change of use in any land, building, or structure if such change would violate any provision of the Land Use Code (§ 14-1-105.B)
  • Any person who changes the use of a structure or property to a use not permitted by current City ordinances, without first obtaining required re-zoning, variance, or other use approvals, is guilty of a class C misdemeanor ('Illegal Change of Use,' § 14-1-106.F)
  • Where the new use requires a Conditional Use Permit, Variance, or Zoning Map Amendment, that Planning Department approval process (and its fee) applies before the Certificate of Occupancy can be reissued

Required documents

  • RequiredBuilding Permit Application (Cityinspect) — where construction/remodel accompanies the use changeApply online at https://utah.cityinspect.com/register?registration_id=mtpX64oVmk. A building permit and Planning Department approval are required before the use of land or a structure may be changed, per § 14-1-105.A.
  • OptionalConditional Use Permit / Variance / Zoning Map Amendment Application (Planning Department)Required only where the new use is not already permitted outright in the applicable zone — filed with the Planning Department at (801) 298-6190.
  • OptionalDetermination of Non-Compliance/Non-Conformance RequestAvailable from the Planning Department for a formal determination of whether an existing or proposed use is a legal nonconforming use or otherwise complies with current zoning.

Fee schedule

Fee typeAmountNotes
Certificate of Occupancy (issuance/reissuance)No separate fee — issued by the Engineering and Building Department as part of the final building-permit inspectionBountiful City Land Use Code § 14-1-106.B: a Certificate of Occupancy 'shall be issued by the Engineering and Building Department of the City at the time a building is completed and final inspection conducted. A new Certificate shall be required any time the occupancy of the building changes to a more intensive use.' No distinct Certificate of Occupancy fee line item appears in Ordinance 2023-01's Engineering Fees (Building Permits) section, confirmed live 2026-07-21 — CO issuance is bundled into the standard building-permit/final-inspection process.
Conditional Use Permit (if the new use requires one)$950.00Bountiful City Ordinance 2023-01, Planning Fees — Land Use Development Fees table (p.8), verbatim: 'Conditional Use Permit ... $950.00.' Fetched and confirmed live 2026-07-21.
Variance (if the new use requires one)$1,150.00Bountiful City Ordinance 2023-01, Planning Fees table (p.8), verbatim: 'Variance ... $1,150.00.'
Zoning Map Amendment / Rezone (if the new use requires one)$2,000.00Bountiful City Ordinance 2023-01, Planning Fees table (p.8), verbatim: 'Zoning Map Amendment ... $2,000.00.'
Determination of Non-Compliance/Non-Conformance$450.00Bountiful City Ordinance 2023-01, Planning Fees table (p.8), verbatim: 'Determination of Non-Compliance/Non-Conformance ... $450.00.' This is the closest fee-schedule analog Bountiful publishes to a formal use/zoning-compliance determination for an existing building.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-16)View current record →All versions →

Permalink: /utah/davis-county/bountiful/as-of/2026-07-17/

Snapshot date: 2026-07-17

Commit: 0fd24e8

Reproducible from PermitBase’s version-controlled dataset, commit 0fd24e8.