This is PermitBase’s published record for Holladay as of 2026-07-16. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Holladay building permits

Verified

Holladay, Utah — as published 2026-07-16.

Verified 2026-07-03 · Source

Codes adopted

2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a), superseding the 2021 IBC. Holladay's own Inspection Guidelines & Codes page, live-checked 2026-07-16, still lists '2021 International Building Code' verbatim — the city's page has NOT been updated to reflect the 7/1/2026 statewide flip. The statute controls regardless of the city page's lag.2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did NOT change this edition in the 7/1/2026 amendment. Matches the city's Inspection Guidelines & Codes page (live-checked 2026-07-16: '2021 International Residential Code').Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not itemized on the city's own Inspection Guidelines & Codes page (live-checked 2026-07-16), added here per statute.2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e), superseding the 2021 IMC. The city's page still lists '2021 International Mechanical Code' — live-checked 2026-07-16, confirming lag. The statute controls.2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f), superseding the 2021 IFGC. The city's page still lists '2021 International Fuel Gas Code' — live-checked 2026-07-16, confirming lag. The statute controls.2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d), superseding the 2021 IPC. The city's page still lists '2021 International Plumbing Code' — live-checked 2026-07-16, confirming lag. The statute controls.2023 National Electrical Code (NEC) — statewide-mandatory edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (the 2023 NEC baseline predates this code cycle). The city's Inspection Guidelines & Codes page lists '2020 National Electric Code' — one edition behind the statewide-mandatory floor, confirmed still unchanged via live-check 2026-07-16. Per Utah Code § 15A-1-204 (statewide-mandatory construction code), the 2023 NEC governs regardless of the city's own page.2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(h) (no residential/commercial split under current law), superseding the 2018 IECC. The city's page still lists '2018 International Energy Conservation Code' — live-checked 2026-07-16, confirming lag (this was already one edition behind the pre-7/1/2026 2021 IECC baseline other Salt Lake County cities used, and is now two editions behind current). The statute controls.2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not listed on the city's own Inspection Guidelines & Codes page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not listed on the city's own Inspection Guidelines & Codes page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.Modular Building Institute (MBI) Standards 1200 and 1205 — statewide per Utah Code § 15A-2-103(1)(o); not listed on the city's own Inspection Guidelines & Codes page, added here per statute.2021 International Fire Code (IFC) — per the city's official Inspection Guidelines & Codes page, live-checked 2026-07-16, unchanged. NOTE: the IFC is NOT among the codes adopted by Utah Code § 15A-2-103 (Title 15A Chapter 2, State Construction Code) — Utah's Fire Code is separately adopted under Title 15A Chapter 5, State Fire Code Act; left as published by the city, no statutory edition change applies via § 15A-2-103.2009 ANSI A117.1 Standard for Accessible and Usable Buildings and Facilities — per the city's official Inspection Guidelines & Codes page, live-checked 2026-07-16, unchanged.2015 Uniform Code for the Abatement of Dangerous Buildings — per the city's official Inspection Guidelines & Codes page, live-checked 2026-07-16, unchanged.Holladay City Code Title 3 (Consolidated Fee Schedule) and Title 13 (Building Permit / Zoning Compliance Review) — local amendments to the above; see localAmendments below.NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Holladay's Inspection Guidelines & Codes page (holladayut.gov/departments/community_development/building_division/inspection_guidelines___codes.php) was live-checked 2026-07-16 via real-browser navigation and confirmed still lagging — it verbatim lists 2021 IBC/IMC/IFGC/IPC/IRC/IFC, 2020 National Electric Code, and 2018 IECC, and omits IEBC and ISPSC entirely. The statewide statute controls over the city's un-updated page.

Permit types & fees

Residential Building Permit (New Dwelling / Remodel)

Verified

Required for new single-family residential construction and residential remodels regulated by the 2021 IRC and the 2024 IBC (current statewide per Utah Code § 15A-2-103, effective 7/1/2026; Holladay's own Inspection Guidelines & Codes page still lists the 2021 IBC as of live-check 2026-07-16, but the statute controls). Holladay uses a valuation-based (Based on Valuation / BOV) fee model tied to the 1997 Uniform Administrative Code Table 3-A, administered case-by-case by an in-house city Building Official (Rob Sears) rather than a published flat-dollar fee table.

Verified 2026-07-03 · Source

Requirements

  • New residential dwelling construction or residential remodel regulated by the 2021 IRC and the current-statewide 2024 IBC (Utah Code § 15A-2-103(1)(a)/(b))
  • Online application only, submitted via the city's iWorq-based Building Permit Application portal (holladay.portal.iworq.net)
  • Building plans uploaded with the application — the city will not accept an application without accompanying plans (oversized plans emailed directly to the permits team)
  • Zoning compliance review per Holladay City Code section 13.08.100 (Building Permit Zoning Compliance Review)
  • Site-specific design factors (snow load, seismic, frost depth) confirmed per address using the city's referenced Utah State University snow-load tool

Required documents

  • RequiredBuilding Permit Application (City of Holladay form / iWorq portal)Official application form listing property/owner/applicant/contractor information, licensed-contractor vs. owner-builder declaration, and an office-use fee breakdown (Building B.O.V. Fee, Electrical, Mechanical, Plumbing, Grading, Demolition, 1% Building Surcharge, Plan Check Fees, Geologic Study, Park/Storm/Fire/Police Impact fees, Pre-Inspection/Pre-Plan-Check credit).
  • OptionalOwner-Builder Certification and Agreement to Comply (DOPL)Required, signed and notarized, for applicants pursuing an owner-builder permit. The city automatically registers the permit with DOPL upon issuance. State restrictions: one house per calendar year, no more than three houses in five years.

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on Valuation (BOV)Determined per project valuation using the 1997 Uniform Administrative Code, Table 3-A
City of Holladay official Building FAQs page: 'Fees are based on the valuation of the project as per 1997 Uniform Administrative Code, Table 3-A.' No further public dollar-figure table was located; Show full citation

City of Holladay official Building FAQs page: 'Fees are based on the valuation of the project as per 1997 Uniform Administrative Code, Table 3-A.' No further public dollar-figure table was located; the city directs applicants to call the Building Division (801-527-3890) for a specific cost estimate. Left as the cited formula rather than an invented dollar amount.

1% Building Surcharge1% of the building fee, split 85%/15% between two accounting line items (per the official Building Permit application form's office-use fee section)Per the city's official Building Permit application form fee breakdown; no further public explanation of the 85/15 split purpose was located.

Electrical, Mechanical & Plumbing Permit

Verified

Covers standalone or combined electrical, mechanical, and plumbing work in Holladay. The city's official Building Permit application form lists these as separate itemized fee lines assessed alongside the Building B.O.V. Fee, but no public flat-dollar or percentage figure is published for these trade fees.

Verified 2026-07-03 · Source

Requirements

  • Electrical, mechanical, or plumbing work regulated statewide by the 2024 IPC / 2024 IMC / 2024 IFGC (Utah Code § 15A-2-103(1)(d)/(e)/(f), effective 7/1/2026) and the 2023 NEC (§ 15A-2-103(1)(g), unchanged); Holladay's own Inspection Guidelines & Codes page still lists the 2021 IPC/IMC/IFGC and 2020 NEC as of live-check 2026-07-16, but the statute controls
  • Online application via the city's iWorq Building Permit Application portal

Required documents

  • RequiredBuilding Permit Application (City of Holladay form / iWorq portal)Submitted online only; the city does not accept paper or in-person-only applications without accompanying plans.

Fee schedule

Fee typeAmountNotes
Electrical FeeNot publicly itemized — assessed per project at permit issuance
The city's official Building Permit application form lists 'Electrical' as a distinct fee line in the office-use fee breakdown, but no public dollar figure or percentage formula for this line was… Show full citation

The city's official Building Permit application form lists 'Electrical' as a distinct fee line in the office-use fee breakdown, but no public dollar figure or percentage formula for this line was located on the Building Division, FAQs, or Fee Schedule pages. Contact 801-527-3890 for the specific fee.

Mechanical FeeNot publicly itemized — assessed per project at permit issuanceSame fee-form line-item basis as Electrical Fee above; no public dollar figure located.
Plumbing FeeNot publicly itemized — assessed per project at permit issuanceSame fee-form line-item basis as Electrical Fee above; no public dollar figure located.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holladay building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-07)Later version (2026-07-19) →View current record →All versions →