Skip to main content
PermitBase

You are viewing the permanent link for the record currently in effect, published 2026-07-16.

Sandy building permits

Verified

Sandy, Utah — as published 2026-07-16.

Verified 2026-06-29 · Source

Codes adopted

2024 International Building Code (IBC) — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a))2021 International Residential Code (IRC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b))2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d))2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e))2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f))2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g))2024 International Energy Conservation Code (IECC) — currently in effect as of July 1, 2026, superseding the 2021 IECC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(h))2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i))Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — currently in effect as of July 1, 2026, superseding the 2021 ISPSC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(n))NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. This file cites no Sandy-specific code-adoption webpage; all codesAdopted entries above are sourced directly from the statute.

Permit types & fees

Single-Family New Construction

Verified

Required for new single-family residential construction in Sandy. Permit fees are based on total project valuation and include plan review at 65% of the permit fee. The state adds a 1% surcharge on all building fees.

Verified 2026-07-20 · Source

Requirements

  • New single-family dwelling construction on a permitted lot
  • Complete architectural and structural drawings
  • Site plan showing setbacks, lot coverage, and drainage
  • Energy code compliance documentation (REScheck or equivalent)
  • Soils report if lot has special conditions

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredConstruction PlansComplete drawings to scale — site plan, floor plans, elevations, sections, and structural details
  • RequiredEnergy Code Compliance DocumentationREScheck or equivalent documentation demonstrating compliance with adopted IECC
  • OptionalStructural CalculationsSealed by a licensed Utah PE for projects requiring engineered design

Fee schedule

Fee typeAmountNotes
New Single-Family Build — total valuation < $100,000$2,967Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Single Family New Build
New Single-Family Build — total valuation $100,000–$500,000$4,866Sandy City 2026 Consolidated Fee Schedule, § 3122
New Single-Family Build — total valuation $500,000–$1,000,000$6,837Sandy City 2026 Consolidated Fee Schedule, § 3122
New Single-Family Build — total valuation $1,000,000–$2,500,000$8,569Sandy City 2026 Consolidated Fee Schedule, § 3122
New Single-Family Build — total valuation $2,500,000–$5,000,000$10,185Sandy City 2026 Consolidated Fee Schedule, § 3122
New Single-Family Build — total valuation > $5,000,000$12,572Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122
After-Hours Inspection (after 5 p.m. or holidays/weekends)$35/hour, minimum $70 (2-hour minimum)Sandy City 2026 Consolidated Fee Schedule

Residential Addition

Verified

Required for adding livable square footage to an existing single-family home, including room additions, garage conversions, and attached accessory apartment additions. Fee is based on total project valuation.

Verified 2026-06-29 · Source

Requirements

  • Addition to an existing single-family or duplex residential structure
  • Complete drawings showing existing structure and proposed addition
  • Site plan with updated setbacks and lot coverage
  • Energy code compliance for new conditioned space

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredConstruction PlansExisting and proposed floor plans, elevations, sections, and structural details
  • RequiredEnergy Compliance DocumentationREScheck or equivalent for new conditioned square footage

Fee schedule

Fee typeAmountNotes
Addition — total valuation < $10,000$345Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Addition
Addition — total valuation $10,000–$50,000$527Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation $50,000–$100,000$1,987Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation $100,000–$250,000$2,867Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation $250,000–$500,000$4,584Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation $500,000–$1,000,000$6,196Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation $1,000,000–$2,500,000$8,614Sandy City 2026 Consolidated Fee Schedule, § 3122
Addition — total valuation > $2,500,000$11,001Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Residential Remodel

Verified

Required for interior and exterior remodels to existing single-family residences, including kitchen remodels, bathroom updates, and structural alterations. Fee is based on project valuation.

Verified 2026-06-29 · Source

Requirements

  • Structural modification or significant interior alteration to an existing residential structure
  • Load-bearing wall modifications require engineered plans
  • Work involving the building envelope (exterior walls, windows, roof) requires permit

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredConstruction PlansFloor plan showing scope of work; structural details if load-bearing elements affected
  • OptionalStructural CalculationsRequired if removing or modifying load-bearing walls or other structural elements

Fee schedule

Fee typeAmountNotes
Remodel — total valuation < $5,000$169Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Remodel
Remodel — total valuation $5,000–$10,000$254Sandy City 2026 Consolidated Fee Schedule, § 3122
Remodel — total valuation $10,000–$20,000$296Sandy City 2026 Consolidated Fee Schedule, § 3122
Remodel — total valuation $20,000–$100,000$430Sandy City 2026 Consolidated Fee Schedule, § 3122
Remodel — total valuation $100,000–$250,000$514Sandy City 2026 Consolidated Fee Schedule, § 3122
Remodel — total valuation $250,000–$1,000,000$823Sandy City 2026 Consolidated Fee Schedule, § 3122
Remodel — total valuation > $2,500,000$908Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Basement Finish

Verified

Required when converting an unfinished basement into habitable living space. Includes framing, electrical, plumbing, HVAC, insulation, and drywall work in the basement area.

Verified 2026-06-29 · Source

Requirements

  • Unfinished or partially finished basement being converted to conditioned/habitable space
  • Must meet egress requirements per adopted IRC (egress window in each sleeping room)
  • Smoke and CO detectors required per adopted IRC

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredBasement Floor PlanLayout showing room use, egress window locations, mechanical/electrical/plumbing rough-in

Fee schedule

Fee typeAmountNotes
Basement Finish — total valuation < $5,000$169Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Basement Finish
Basement Finish — total valuation $5,000–$10,000$254Sandy City 2026 Consolidated Fee Schedule, § 3122
Basement Finish — total valuation $10,000–$20,000$296Sandy City 2026 Consolidated Fee Schedule, § 3122
Basement Finish — total valuation $20,000–$250,000$387Sandy City 2026 Consolidated Fee Schedule, § 3122
Basement Finish — total valuation $250,000–$1,000,000$611Sandy City 2026 Consolidated Fee Schedule, § 3122
Basement Finish — total valuation > $1,000,000$781Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Deck / Patio Cover

Verified

Required for new decks, attached patio covers, and covered porch structures attached to or detached from the home. Flat fee regardless of valuation.

Verified 2026-06-29 · Source

Requirements

  • New attached or detached deck, porch, or patio cover structure
  • Structural drawings if deck is elevated or has complex framing
  • Site plan showing location relative to property lines

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredSite Plan and Deck PlansDrawing showing deck dimensions, framing, ledger attachment, and post/footing sizes

Fee schedule

Fee typeAmountNotes
Deck / Patio Permit (flat fee)$375Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Deck/Patio
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Residential Solar / PV System

Verified

Required for rooftop and ground-mount residential solar photovoltaic systems. Two fee tiers based on system size: under 10,000 kW and 10,000 kW or larger (or energy storage systems). Fees are based on total project valuation.

Verified 2026-06-29 · Source

Requirements

  • Rooftop or ground-mount PV system installation
  • Equipment specifications and installation drawings
  • Structural letter or engineering for roof-mounted systems on older homes
  • Electrical single-line diagram
  • Utility interconnection application (Rocky Mountain Power)

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredElectrical Single-Line DiagramShowing PV array, inverter, disconnect, and utility interconnection
  • RequiredPV System Layout PlanRoof plan with module locations, dimensions, and attachment details
  • OptionalStructural / Load CalculationsManufacturer specs and, if required, a structural engineer letter confirming roof capacity

Fee schedule

Fee typeAmountNotes
Solar < 10,000 kW — total valuation < $50,000$372Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Solar <10,000 kW
Solar < 10,000 kW — total valuation $50,000–$100,000$589Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar < 10,000 kW — total valuation $100,000–$250,000$1,239Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar < 10,000 kW — total valuation $250,000–$500,000$1,517Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar < 10,000 kW — total valuation $500,000–$1,000,000$2,156Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar < 10,000 kW — total valuation $1,000,000–$2,500,000$2,722Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar < 10,000 kW — total valuation > $2,500,000$3,446Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or Energy Storage System — total valuation < $50,000$553Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Solar >10,000 kW or ESS
Solar >= 10,000 kW or ESS — total valuation $50,000–$100,000$638Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or ESS — total valuation $100,000–$250,000$1,037Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or ESS — total valuation $250,000–$500,000$1,303Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or ESS — total valuation $500,000–$1,000,000$2,150Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or ESS — total valuation $1,000,000–$2,500,000$3,107Sandy City 2026 Consolidated Fee Schedule, § 3122
Solar >= 10,000 kW or ESS — total valuation > $2,500,000$3,796Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

HVAC / AC / Furnace Replacement

Verified

Required for replacing or installing a new air conditioner, furnace, heat pump, or other HVAC equipment in a residential property. Flat fee.

Verified 2026-06-29 · Source

Requirements

  • Replacement of an existing heating or cooling unit
  • New HVAC installation in an existing or new structure
  • Equipment specifications (model, BTU/ton rating)

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredEquipment SpecificationsManufacturer data sheet for the replacement unit

Fee schedule

Fee typeAmountNotes
AC / Furnace Replacement (flat fee)$105Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — AC/Furnace
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Water Heater Replacement

Verified

Required for replacing a residential water heater (tank or tankless). Flat fee.

Verified 2026-06-29 · Source

Requirements

  • Replacement of an existing water heater in a residential structure
  • Equipment specifications (model, BTU/gallon rating)

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway

Fee schedule

Fee typeAmountNotes
Water Heater Replacement (flat fee)$105Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Water Heater Replacement
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Reroof

Verified

Required for reroofing an existing residential structure. Flat fee for residential reroof.

Verified 2026-06-29 · Source

Requirements

  • Full or partial replacement of roof covering on any structure
  • Roofing material specifications

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway

Fee schedule

Fee typeAmountNotes
Residential Reroof (flat fee)$115Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Reroof
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

In-Ground Swimming Pool

Verified

Required for new in-ground residential swimming pool construction. Fee is based on total project valuation. A $2,500 inspection bond is also required.

Verified 2026-06-29 · Source

Requirements

  • In-ground swimming pool construction
  • Site plan showing pool location, setbacks, and fencing plan
  • Pool barrier/fencing plan meeting IRC and ISPSC requirements
  • Electrical plan for pump, lighting, and bonding

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredSite PlanShowing pool location relative to property lines, house, and utility easements
  • RequiredPool Construction PlansStructural and electrical plans for the pool system
  • RequiredBarrier / Fence PlanFencing plan meeting ISPSC pool barrier requirements

Fee schedule

Fee typeAmountNotes
In-Ground Swimming Pool — total valuation < $100,000$570Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Swimming Pool (In-Ground)
In-Ground Swimming Pool — total valuation > $100,000$965Sandy City 2026 Consolidated Fee Schedule, § 3122
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Swimming Pool Inspection Bond$2,500Sandy City 2026 Consolidated Fee Schedule, § 3122 — inspection bond required at permit issuance
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Commercial Building Permit

Verified

Required for new commercial building construction in Sandy ("New Build" category under the Commercial Permits table of the city's fee schedule), covering new shell buildings, offices, retail, and other commercial structures. Fees are based on total project valuation using a separate Commercial Permits fee table from the residential schedule. Plan review adds 65% of the permit fee and the state adds a 1% surcharge on all building fees, same as residential.

Verified 2026-07-19 · Source

Requirements

  • New commercial building construction on a permitted, properly zoned lot
  • Complete architectural and structural drawings sealed by a licensed design professional
  • Site plan showing setbacks, parking, and drainage per Sandy's Planning Division requirements
  • Energy code compliance documentation (COMcheck or equivalent) for the adopted IECC
  • Fire sprinkler and/or fire alarm plans where required by the adopted IBC/IFC, reviewed separately by the Fire Department

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredConstruction PlansComplete drawings to scale — site plan, floor plans, elevations, sections, and structural details, sealed by a licensed Utah design professional
  • RequiredEnergy Code Compliance DocumentationCOMcheck or equivalent documentation demonstrating compliance with the adopted commercial IECC
  • OptionalFire Sprinkler / Fire Alarm PlansRequired where the adopted IBC/IFC mandates fire suppression or alarm systems; reviewed and fee'd separately by the Sandy Fire Department per the Consolidated Fee Schedule

Fee schedule

Fee typeAmountNotes
Commercial New Build — total valuation < $100,000$2,495Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Commercial Permits — New Build
Commercial New Build — total valuation $100,000–$250,000$3,714Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation $250,000–$500,000$6,452Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation $500,000–$1,000,000$10,927Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation $1,000,000–$2,500,000$15,472Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation $2,500,000–$5,000,000$19,098Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation $5,000,000–$10,000,000$24,352Sandy City 2026 Consolidated Fee Schedule, § 3122
Commercial New Build — total valuation > $10,000,000$29,676–$77,548 (six further tiers up to >$50,000,000)Sandy City 2026 Consolidated Fee Schedule, § 3122 — full table runs $10M–$15M: $29,676; $15M–$20M: $35,000; $20M–$30M: $45,094; $30M–$40M: $55,188; $40M–$50M: $66,333; >$50M: $77,548
New Construction Fire Sprinkler Plan Review — 1-100 heads$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — New Construction Fire Sprinklers 1-100 heads (additional tiers up to $325 + $0.55/head for >300 heads)
New Construction Fire Alarm Plan Review — 1-3,000 sq ft$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — New Construction Fire Alarm 1-3,000 sq ft (additional tiers up to $270 + $0.005/sq ft for >8,000 sq ft)
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122
Sign Permit Bond (Commercial)$500Sandy City 2026 Consolidated Fee Schedule, § 3122 Inspection Bonds — Sign Permit Bond (Commercial)

Commercial Tenant Improvement / Tenant Finish Permit

Verified

Required for tenant improvement (tenant finish) work in existing commercial buildings in Sandy — interior build-outs, remodels, and finish work for a new or changing tenant space. Listed as its own "Tenant Improvement" line item in the Commercial Permits section of the city's fee schedule, distinct from new commercial construction. Fees are based on total project valuation; plan review adds 65% and the state adds a 1% surcharge, same as new commercial construction.

Verified 2026-07-19 · Source

Requirements

  • Interior build-out, remodel, or finish work in an existing commercial tenant space
  • Floor plan showing existing and proposed layout, occupancy classification, and egress
  • Mechanical, electrical, and plumbing plans for the scope of work
  • Fire sprinkler and/or fire alarm modification plans where the scope affects existing systems

Required documents

  • RequiredBuilding Permit ApplicationSubmit via Sandy City online permit portal or in person at 10000 Centennial Parkway
  • RequiredConstruction PlansFloor plan showing scope of work, occupancy classification, and egress; structural details if load-bearing elements are affected
  • OptionalFire Sprinkler / Fire Alarm Modification PlansRequired where the tenant improvement scope affects existing fire suppression or alarm systems; reviewed and fee'd separately by the Sandy Fire Department

Fee schedule

Fee typeAmountNotes
Tenant Improvement — total valuation < $5,000$574Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Commercial Permits — Tenant Improvement
Tenant Improvement — total valuation $5,000–$50,000$881Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation $50,000–$100,000$2,287Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation $100,000–$250,000$2,860Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation $250,000–$500,000$4,600Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation $500,000–$1,000,000$6,011Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation $1,000,000–$2,500,000$8,792Sandy City 2026 Consolidated Fee Schedule, § 3122
Tenant Improvement — total valuation > $2,500,000$11,679Sandy City 2026 Consolidated Fee Schedule, § 3122
Fire Sprinkler Plan Review — Tenant Improvement, 1-50 heads$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — Commercial Sprinkler Plan Review, Tenant Improvement 1-50 heads (>50 heads is $215)
Fire Alarm Plan Review — Tenant Improvement, 1-5,000 sq ft$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — Fire Alarm Plan Review, Tenant Improvement 1-5,000 sq ft (>5,000 sq ft is $215)
Plan Review Fee65% of the building permit feeSandy City 2026 Consolidated Fee Schedule, § 3122
State Building Fee Surcharge1% of total permit feeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
Re-Inspection Fee$70Sandy City 2026 Consolidated Fee Schedule, § 3122

Sign Permit

Verified

Required for permanent and temporary signs in Sandy City, administered by the Planning Division under a distinct Sign Permit fee schedule (fee code 312290), separate from general building permit fees. Businesses must have a current or applied-for Sandy City Business License before a sign permit will be released, and all permanent sign installations require wet-stamped engineering details regardless of sign size, design, weight, or placement.

Verified 2026-07-20 · Source

Requirements

  • Completed Sign Permit Application
  • Business must have a current or applied-for Sandy City Business License — permits are not approved and released until license verification is complete
  • Temporary Sign Permit: plot plan showing relationship of sign(s) to buildings, property lines, setback from public rights-of-way, intersections, easements and driveways; length of period for display; type of temporary sign request; dimensions of proposed sign(s)
  • Permanent Sign Permit: value of the sign including all labor and material costs; contractor license number and expiration date for the sign installer; two sets of scaled, wet-stamped engineering details (construction, connections, footings, calculations) from an engineer licensed in Utah — required for ALL permanent sign installations regardless of size, design, weight, or placement
  • Monument and freestanding signs additionally require: plot plan with setbacks/site contours (1-ft intervals) and nearest monument/freestanding signs on the same frontage; dimensioned scaled drawings of color, height, street appearance, landscaping, materials, composition, square footage, illumination type, and site acreage/frontage
  • Signs on a building exterior additionally require: scaled drawings of building and sign square footage, sign composition, illumination type, and a street/parking-area profile drawing
  • All permanent sign applications must demonstrate adequate landscaping, appropriate color/style, appropriate illumination, appropriate scale/proportioning, architectural compatibility, and location — the Planning Director may deny or refer an application to the Planning Commission if these elements are not adequately shown

Required documents

  • RequiredSign Permit ApplicationCompleted application; business license verification required before release.
  • RequiredPlot PlanRelationship of sign(s) to buildings, property lines, rights-of-way setback, intersections, easements, driveways (temporary signs); adds site contours and nearest monument/freestanding sign locations for monument/freestanding permanent signs.
  • RequiredEngineering Details (Permanent Signs)Two sets of scaled, wet-stamped engineering details showing construction, all connections, footings, and calculations; engineer must be licensed to practice in Utah. Required for all permanent signs regardless of size, design, weight, or placement.
  • RequiredScaled DrawingsColor, height, street appearance, landscaping, materials, sign composition, square footage, illumination type (monument/freestanding); or building and sign square footage, composition, illumination type, and street/parking-area profile (building-exterior signs).

Fee schedule

Fee typeAmountNotes
Permit Fee Per Sign$190 (2026 Approved)Sandy City 2026 Consolidated Fee Schedule, fee code 312290 'Sign Permit Fees': 'Permit Fee Per Sign' — 2025/2026 Approved figure $190 (up from $177 in 2023/2024), confirmed by visual read of the fee-schedule table (page 20 of the PDF) after pdftotext column-alignment produced a garbled row order.
Temporary Sign / 7-Day Period$93 (2026 Approved)Sandy City 2026 Consolidated Fee Schedule, fee code 312290: 'Temporary Sign / 7-Day Period' — 2025/2026 Approved figure $93 (up from $91 in 2023/2024).
Signs Installed Without Permits$240 (2026 Approved), or double the applicable permit feeSandy City 2026 Consolidated Fee Schedule, fee code 312290: 'Signs Installed Without Permits (or double the applicable permit fee)' — 2025/2026 Approved figure $240 (up from $220 in 2023/2024).
Sign Review/Appeal Document Prep. for Planning Commission$496 (2026 Approved)Sandy City 2026 Consolidated Fee Schedule, fee code 312290: 'Sign Review/Appeal Document Prep. for Planning Commission' — 2025/2026 Approved figure $496 (up from $460 in 2023/2024).
Sign Permit Bond (Commercial)$500Sandy City 2026 Consolidated Fee Schedule, § 3122 Inspection Bonds — Sign Permit Bond (Commercial), flat $500 across the 2023/2024 through 2025/2026 schedules (a prior version of this entry mistakenly cited a $65-to-$70 progression that actually belongs to the unrelated Building Permit Renewal/Transfer fee line).

EV Charger / EVSE Permit

Sandy City's Building & Safety fee schedule (section 3122, Building Permit Fees) includes a standalone "Electrical" permit fee category alongside other trade categories (Egress, Equipment, Fence, etc.), assessed per its own valuation-tiered table. A full-text search of the published fee schedule found no distinct "EV Charger," "EVSE," or "electric vehicle charging" permit line item — the only other EV-related entry, "Charging Station Fees" (category 316972), is a Facilities-department utility rate for electricity sold at Sandy's own public charging stations (per-kWh usage price), not a building/electrical permit fee. Because the multi-tier PDF table did not extract cleanly enough to confirm a single precise base dollar figure for the Electrical permit category, this entry is marked partial rather than citing a specific number.

Reviewed 2026-07-20 · Source

Requirements

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Sandy City
  • Work performed per Sandy City's adopted electrical code

Required documents

  • RequiredElectrical Permit ApplicationSubmitted through Sandy City's Building Permits process (Paperless Permits & Plans portal).

Fee schedule

Fee typeAmountNotes
Electrical PermitValuation/category-tiered fee — exact base figure not confirmedSandy City Consolidated Fee Schedule, Building & Safety section (3122 Building Permit Fees), lists a standalone 'Electrical' category with per-year approved amounts, but the published PDF's multi-column table did not extract with reliable row alignment for this research pass. No distinct 'EV Charger' or 'EVSE' fee line exists anywhere in the schedule (confirmed by full-text search); confirm the current Electrical permit amount directly with Sandy City Building & Safety before applying.

Fire Sprinkler Permit

Verified

Required for installation, modification, or addition to a fire sprinkler system in Sandy City, reviewed by the Sandy Fire Department against the current edition of NFPA 13. Plans and specifications are submitted through the city's online CityWorks permitting portal; the permit is issued through CityWorks once plans are approved and fees are paid.

Verified 2026-07-22 · Source

Requirements

  • Installation, modification, or addition to a fire sprinkler system subject to the current edition of NFPA 13
  • For new systems, a letter from a third-party independent plan review must be submitted with the plan set
  • Complete plan submittal per Sandy Fire Department's Fire Sprinkler Plan Requirements (floor plan, cross section, hydraulic calculations, equipment cut sheets, and related items)

Required documents

  • RequiredFire Sprinkler Permit ApplicationSubmitted through Sandy City's online CityWorks permitting portal
  • RequiredFire Sprinkler Plans and SpecificationsPer NFPA 13 plan requirements: scaled floor plan showing partitions, fire walls, occupancy classes, and fire riser location; full-height cross section/schematic; concealed-space locations; head count and dry-system capacity; antifreeze solution data; hanger/sleeve/brace details; control/check valve and drain/test connection locations; standpipe and riser schematic; hydraulic calculations and nameplate data; fire department connection sizing/location with hydrant location within 100 feet; and manufacturer cut sheets
  • OptionalThird-Party Independent Review LetterRequired specifically for new fire sprinkler systems per Sandy Fire Department's plan requirements

Fee schedule

Fee typeAmountNotes
New Construction Fire Sprinkler Plan Review — 1-100 heads$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — New Construction Fire Sprinklers 1-100 heads (additional tiers up to $325 + $0.55/head for >300 heads)
Fire Sprinkler Plan Review — Tenant Improvement, 1-50 heads$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — Commercial Sprinkler Plan Review, Tenant Improvement 1-50 heads (>50 heads is $215)

Fire Alarm Permit

Verified

Required for installation or modification of a fire alarm system in Sandy City, reviewed by the Sandy Fire Department. Plans and specifications are submitted through the city's online CityWorks permitting portal; the permit is issued through CityWorks once plans are approved and fees are paid. Final acceptance testing must meet NFPA 72 standards.

Verified 2026-07-22 · Source

Requirements

  • Installation or modification of a fire alarm system requiring plan/specification submittal to the Fire Department
  • Final acceptance testing and inspection must meet current NFPA 72 testing standards

Required documents

  • RequiredFire Alarm Permit ApplicationSubmitted through Sandy City's online CityWorks permitting portal
  • RequiredFire Alarm Plans and SpecificationsPlan set for the fire alarm installation or modification, submitted with the permit application for Fire Department review

Fee schedule

Fee typeAmountNotes
New Construction Fire Alarm Plan Review — 1-3,000 sq ft$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — New Construction Fire Alarm 1-3,000 sq ft (additional tiers up to $270 + $0.005/sq ft for >8,000 sq ft)
Fire Alarm Plan Review — Tenant Improvement, 1-5,000 sq ft$160Sandy City 2026 Consolidated Fee Schedule, Fire § 314224 Fire Inspection Fees — Fire Alarm Plan Review, Tenant Improvement 1-5,000 sq ft (>5,000 sq ft is $215)

Business License Update — Change of Use / Change of Location

Verified

Sandy City has no standalone change-of-use or certificate-of-occupancy permit product. A change in the nature of a business, or a licensed business relocating within the city, is instead handled through the city's Update Application for an Existing Commercial License, administered by the Business License Office. New positive final inspections/recommendations from Building & Safety and the Fire Department (and other agencies where applicable) are required before an updated license is issued — this is the genuine Sandy-specific process, documented as found rather than inventing a separate standalone product.

Verified 2026-07-22 · Source

Requirements

  • An existing Sandy City commercial business license undergoing a change in business location within the city, a change in the nature/type of business, or another update to license details
  • Update Application for an Existing Commercial License filed with the Business License Office (a separate application is required for each business location)
  • Positive final inspection or recommendation from the Building & Safety Department
  • Positive final inspection or recommendation from the Sandy Fire Department
  • Recent documentation of valid or active entity status with the Utah Department of Commerce
  • Not usable for a complete change in ownership or for transferring a license to a new owner — those require a new business license application

Required documents

  • RequiredUpdate Application for an Existing Commercial LicenseFiled with the Business License Office at 10000 S Centennial Parkway, Suite 210, Sandy, UT 84070
  • RequiredUtah Department of Commerce Entity Status DocumentationRecent documentation showing a valid or active entity status, required to accompany all update applications
  • RequiredBuilding & Safety Inspection Sign-OffScheduled with Building & Safety (801-568-7251) after the update application is filed
  • RequiredFire Department Inspection Sign-OffScheduled with the Sandy Fire Department (801-568-2938) after the update application is filed

Fee schedule

Fee typeAmountNotes
Fire Inspection Fee$44.00Sandy City Update Application for an Existing Commercial License form (Business License Office, buslic@sandy.utah.gov), form updated 6/2024
Code Inspection Fee$22.00Sandy City Update Application for an Existing Commercial License form, form updated 6/2024
Building Inspection Fee$22.00Sandy City Update Application for an Existing Commercial License form, form updated 6/2024
Employee Fee$20.00 per employeeSandy City Update Application for an Existing Commercial License form, form updated 6/2024
Per-Apartment Fee (residential rental units, if applicable)$17.00 per apartment unitSandy City Update Application for an Existing Commercial License form, form updated 6/2024
Duplicate License Fee (issued when the business name changes)$26.00Sandy City Update Application for an Existing Commercial License form, form updated 6/2024
Special Regulations / Beer License Fee (if applicable)$52.00Sandy City Update Application for an Existing Commercial License form, form updated 6/2024

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-02)View current record →All versions →

Permalink: /utah/salt-lake-county/sandy/as-of/2026-07-16/

Snapshot date: 2026-07-16

Commit: 0214041

Reproducible from PermitBase’s version-controlled dataset, commit 0214041.