Skip to main content
PermitBase

This is PermitBase’s published record for Taylorsville as of 2026-06-30. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Taylorsville building permits

Verified

Taylorsville, Utah — as published 2026-06-30.

Verified 2026-06-30 · Source

Codes adopted

2021 International Building Code (IBC) — Taylorsville Building Department page (taylorsvilleut.gov/government/building-department, accessed 2026-06-30)2021 International Residential Code (IRC) — Taylorsville Building Department page (accessed 2026-06-30)2021 International Plumbing Code (IPC) — Taylorsville Building Department page (accessed 2026-06-30)2021 International Mechanical Code (IMC) — Taylorsville Building Department page (accessed 2026-06-30)2021 International Fuel Gas Code (IFGC) — Taylorsville Building Department page (accessed 2026-06-30)2021 International Energy Conservation Code (IECC) — Taylorsville Building Department page (accessed 2026-06-30)2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g) (statewide mandate supersedes Taylorsville's building page which references 2020 NEC)NOTE: Effective July 1, 2026 — 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC replace the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026)

Permit types & fees

Residential Building Permit

Verified

Required for new residential construction, additions, structural alterations, and work requiring plan review in Taylorsville. Permit fees are valuation-based per the Taylorsville City Consolidated Fee Schedule. Valuation for new construction and additions is calculated using Taylorsville's published per-square-foot rates.

Verified 2026-06-30 · Source

Requirements

  • New single-family or multi-family residential construction
  • Additions or structural modifications to existing structures
  • Conversion of non-habitable space to habitable space
  • Any work requiring plan review under the adopted building codes

Required documents

  • RequiredBuilding Permit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • RequiredConstruction PlansComplete drawings to scale — site plan, floor plans, elevations, sections, and structural details. See the Residential Plan Submittal Requirements form on the Information Forms page.
  • RequiredEnergy Code Compliance DocumentationREScheck or equivalent documentation demonstrating compliance with the adopted IECC
  • OptionalEngineered Truss PlansSealed truss layouts for new construction

Fee schedule

Fee typeAmountNotes
Building Permit — valuation under $2,000$24.00 for the first $500, plus $3.50 for each additional $100 or fraction thereof, to and including $2,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939)
Building Permit — valuation $2,000 to $25,000$76.50 for the first $2,000, plus $16.50 for each additional $1,000 or fraction thereof, to and including $25,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Building Permit — valuation $25,000 to $50,000$456.00 for the first $25,000, plus $12.00 for each additional $1,000 or fraction thereof, to and including $50,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Building Permit — valuation $50,000 to $100,000$765.00 for the first $50,000, plus $8.50 for each additional $1,000 or fraction thereof, to and including $100,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Building Permit — valuation $100,000 to $500,000$1,181.00 for the first $100,000, plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Building Permit — valuation $500,000 to $1,000,000$3,781.00 for the first $500,000, plus $5.50 for each additional $1,000 or fraction thereof, to and including $1,000,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Building Permit — valuation over $1,000,000$6,531.00 for the first $1,000,000, plus $4.50 for each additional $1,000 or fraction thereofTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Main Floor / Second Floor$88.03 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 — used to calculate project valuation before applying the permit fee tiers above
Residential Valuation Rate — Rough Basement$36.50 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Finished Basement$15.00 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Garage / Shed$34.18 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Carport / Covered Deck$25.00 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Deck$20.00 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
Residential Valuation Rate — Converted Garage/Carport to Living Space$45.00 per sq. ft.Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026

Water Heater Permit

Verified

Required for water heater installation or replacement (standard tank and tankless) in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • Water heater replacement (including like-for-like swaps)
  • New water heater installation
  • Conversion from tank to tankless water heater

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • OptionalEquipment SpecificationsManufacturer data sheet for the water heater (recommended for tankless or non-standard units)

Fee schedule

Fee typeAmountNotes
Hot Water Heater (Standard and Tankless) — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations and replacements in Taylorsville, including furnaces and air conditioners. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • Furnace or air conditioner installation or replacement
  • Heat pump installation
  • Evaporative cooler installation
  • Ductwork installation or major modification

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, or heat pump

Fee schedule

Fee typeAmountNotes
HVAC (Furnace/Air Conditioner) — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'

Electrical Service Permit

Verified

Required for electrical service changes, panel upgrades, and new electrical service installations in Taylorsville. The Consolidated Fee Schedule lists 'Electrical Service Charge' as a standalone flat-fee category and 'Temporary Power' separately.

Verified 2026-06-30 · Source

Requirements

  • Electrical service entrance change or upgrade
  • Main panel replacement or upgrade
  • New electrical service installation
  • Temporary power installation during construction

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • OptionalSingle-Line DiagramPanel schedule and service entrance diagram for upgrades

Fee schedule

Fee typeAmountNotes
Electrical Service Charge — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'
Temporary Power — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026

Roofing Permit

Verified

Required for roof replacement and re-roofing in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule. The fee schedule also lists 'Exterior Coverings' as a separate $60 flat-fee category (siding, stucco, and similar re-cladding projects).

Verified 2026-06-30 · Source

Requirements

  • Complete roof replacement (tear-off and re-roof)
  • Overlay of new roofing over existing
  • Structural roof repairs or modifications

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice; include scope of work, square footage, and material specifications
  • OptionalContractor LicenseValid Utah roofing contractor license (Utah DOPL) if not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Roofing — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'

Fence Permit

Verified

Required for new fence installation and fence replacement in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • New fence construction
  • Fence replacement that changes height, location, or material
  • Fences over 6 feet in height in any zone

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • OptionalSite PlanPlot plan showing fence location relative to property lines and structures

Fee schedule

Fee typeAmountNotes
Fences — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'

Demolition Permit

Verified

Required for partial or complete demolition of structures in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • Complete demolition of any structure
  • Partial demolition involving structural elements
  • Removal of load-bearing walls

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice; include scope of demolition, structure details, and disposal plan
  • OptionalAsbestos / DAQ ClearanceUtah DAQ involvement required for structures that may contain asbestos-containing materials — contact Utah DEQ/DAQ before demolition
  • RequiredUtility Disconnect ConfirmationProof that gas, electric, water, and sewer are disconnected prior to demolition

Fee schedule

Fee typeAmountNotes
Demolition (Residential and Commercial) — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed as 'Demolition (Residential and Commercial)' under the Flat Fee Permits table. Note: the section heading reads 'Flat Fee Permits per Residential Location (Except Demolition)' — the demolition line applies to both residential and commercial regardless.

Solar Panel Permit

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Taylorsville. The Taylorsville Consolidated Fee Schedule (Revised & Approved March 19, 2026) does not list a separate flat fee for solar PV; the structural mounting falls under the valuation-based building permit and the electrical interconnection requires an Electrical Service permit ($60 flat fee). Taylorsville publishes a 'Solar P.V.' information form on its Information Forms page.

Reviewed 2026-06-30 · Source

Requirements

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Electrical service change or upgrade for solar interconnection (Electrical Service permit required)

Required documents

  • RequiredSolar Site Plan / Roof PlanShowing panel placement, setbacks, and access pathways — download the Solar P.V. information form from taylorsvilleut.gov/government/community-development/information-forms
  • RequiredElectrical Single-Line DiagramSystem wiring from panels to inverter to main panel and utility meter
  • RequiredStructural AnalysisRoof load calculation confirming structure can support panels
  • RequiredEquipment SpecificationsData sheets for panels, inverter, and racking system
  • OptionalInterconnection AgreementRocky Mountain Power utility approval for grid-tied systems

Fee schedule

Fee typeAmountNotes
Building Permit (structural/valuation-based)Valuation-based — see residential building permit fee schedule; valuation calculated from project cost or square-footage ratesTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 — no standalone solar flat-fee line item; solar structural work falls under the valuation-based building permit
Electrical Service Charge — Flat Fee (for electrical interconnection)$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 — separate permit required for electrical service change or interconnection

Window & Door Replacement Permit

Verified

Required for replacement of windows and exterior doors in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • Replacement of one or more windows or exterior doors
  • Structural modification associated with window or door opening (may also require a valuation-based building permit)

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice

Fee schedule

Fee typeAmountNotes
Replacing Windows & Doors — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed under 'Flat Fee Permits per Residential Location'

Gas Line Permit

Verified

Required for installation, modification, or extension of natural gas or propane piping in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

Requirements

  • New gas line installation to an appliance
  • Extending or relocating existing gas piping
  • Adding a gas stub for future appliance (BBQ, fire pit, etc.)

Required documents

  • RequiredPermit ApplicationSubmit via the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice
  • OptionalGas Piping PlanPipe routing, sizing based on BTU load, and material specifications

Fee schedule

Fee typeAmountNotes
Gas Line — Flat Fee$60.00Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed as 'Gas Line' under 'Flat Fee Permits per Residential Location'

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylorsville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-06-27)Later version (2026-07-01) →View current record →All versions →

Permalink: /utah/salt-lake-county/taylorsville/as-of/2026-06-30/

Snapshot date: 2026-06-30

Commit: 475f6a6

Reproducible from PermitBase’s version-controlled dataset, commit 475f6a6.