You are viewing the permanent link for the record currently in effect, published 2026-07-16.
Cedar Hills building permits
VerifiedCedar Hills, Utah — as published 2026-07-16.
Verified 2026-07-08 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for all new residential construction in Cedar Hills, regulated by the adopted 2021 IRC / 2024 IBC (per Utah Code § 15A-2-103, effective 7/1/2026 — Cedar Hills' own Building Permit Requirements form has not yet been updated to reflect the 2024 IBC as of 2026-07-16). The city's fee schedule charges a valuation-based Building Permit fee (no separate printed dollar table; assessed 'Based on valuation' per the International Building Code, i.e. IBC Section 109 / ICC Building Valuation Data methodology) plus a mandatory Residential Plan Check fee (65% of the building permit fee) and a tiered, square-footage-based Plan Check Deposit due at application. Cedar Hills' Master Fee Schedule lists a 'Temporary Power & Permanent Power Inspection (Residential)' fee of $65.00 and a separate 'Electrical Permit (Commercial)' fee category, both collected as part of the Building Permit, but no distinct EV charger/EVSE line item was found as of 2026-07-19 — a standalone home EV charger circuit would fall under the standard Temporary/Permanent Power Inspection fee rather than a dedicated EV charge.
Verified 2026-07-08 · Source
Requirements
- New single-family residential construction regulated by the adopted 2021 IRC / 2024 IBC (per Utah Code § 15A-2-103, effective 7/1/2026)
- Completed Building Permit Application (submitted via the online iworq permit portal or by print application)
- 2 sets of building plans drawn to scale, including a site plan (north arrow, lot dimensions, setbacks, easements, property lines, water meter/sewer lateral location, driveway/hard-surface locations, retaining walls, and topographical details if slope exceeds 10%)
- Construction plans: floor plans, footing/foundation details, structural framing, electrical/mechanical/plumbing design details, energy code compliance documentation (RES Check, COMM Check, Manual D/J/S as applicable)
- Structural calculations stamped by a Utah-licensed structural engineer (roof trusses may be a deferred submittal)
- Geotechnical report, including slope stability evaluation and retaining wall design, if lot slope exceeds 15%
- HOA approval if applicable
- Plan Check Deposit, based on gross square footage and/or valuation, due at application
Required documents
- RequiredBuilding Permit Requirements ChecklistCity of Cedar Hills' official checklist (revised 06/12/2025) listing all required plan-set contents, structural/energy documentation, and the plan check deposit requirement.
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal (cedarhills.portal.iworq.net/portalhome/cedarhills), or as a Non-Digital (print) application for new construction, remodels, accessory buildings, HVAC, roofing, and solar installations.
- OptionalOwner/Builder Certification and Agreement to Comply with the Construction Trades Licensing ActUtah Division of Occupational and Professional Licensing (DOPL) form, required only if the property owner is acting as their own contractor; filed with the city Building Department, which forwards it to DOPL.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Based on valuation (no flat table published; assessed per International Building Code valuation methodology) | City of Cedar Hills Fee Schedule, effective 07/01/2026, Planning/Building/Zoning section: 'Building Permit — Based on valuation — Building Permit — International Building Code.' No standalone dollar/square-footage table is published by Cedar Hills; valuation is assessed under the adopted 2021 IBC's valuation-based permit fee framework. |
| Residential Plan Check Fee | 65% of building permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Residential Plan Check — 65% of building permit fee — Building Permit — Resolution 04-21-2015A.' |
| 1% State Fee | 1% of Building Permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: '1% State Fee — 1% of Building Permit — Building Permit — International Building Code' (statewide surcharge collected via the local building permit). |
| Residential Plan Check Deposit | $300.00 (1-275 sq ft) up to $3,900.00 (9,501-10,000 sq ft), tiered by gross square footage; Estimated Actual Cost for 10,000+ sq ft | City of Cedar Hills Fee Schedule, effective 07/01/2026, full tiered table (e.g. 1,801-2,100 sq ft: $1,100.00; 2,701-3,000 sq ft: $1,500.00; 4,701-5,000 sq ft: $2,300.00), due 'At Application' per Resolution 02-07-2017A. |
| Refundable Improvement Bond | $4,000.00 (general); $3,000.00 for pools and accessory structures | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Refundable Improvement Bond — $4,000.00 — Building Permit — Resolution 05-21-2024B' and 'Refundable Improvement Bond – Pools and Accessory Structures — $3,000.00.' |
| New Construction Utility Fees (Per ERU) | Construction Water Fee $150.00; Water Meter (3/4") & Installation $575.00; Water Lateral Inspection $75.00; Sewer Lateral Inspection $75.00; Gas Line Inspection (Residential) $53.00; Temporary/Permanent Power Inspection, each (Residential) $53.00; Pressurized Irrigation Infrastructure $656.90 | City of Cedar Hills Fee Schedule, effective 07/01/2026, 'New Construction Fees (Per ERU)' table, all collected at Building Permit issuance. |
| Impact Fees (Per ERU) | Parks (Single Family) $2,256.00; Public Safety (Residential, per unit) $495.13; Sewer (Cedar Hills, 3/4") $928.80; Culinary Water (3/4" meter) $887.53; plus Transportation impact fee (Single Family Detached Housing) $852.54 | City of Cedar Hills Fee Schedule, effective 07/01/2026, 'Impact Fees (Per ERU)' and 'Transportation' tables, collected at Building Permit. |
| Re-inspection Fee | $100.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Re-inspection Fee — $100.00 — Prior to Re-inspect — Resolution 09-20-2005A.' |
Residential Addition / Remodel / Basement Finish Permit
VerifiedRequired for additions, remodels, and basement finishes in Cedar Hills. The city publishes a separate Basement Permit Requirements checklist distinct from new-construction requirements, and charges a reduced 26% Residential Plan Check rate (vs. 65% for new construction) for basement finishes, small structures, and solar.
Verified 2026-07-08 · Source
Requirements
- Additions and remodels to existing one- and two-family residential structures, regulated by the adopted 2021 IRC
- Basement finish work: 2 sets of scale drawings (1/4" = 1'), gross floor area and room sizes, labeled rooms including proposed future use of unfinished areas, identification of new vs. existing construction
- Window sizes/types, ceiling heights, smoke/CO detector locations, electrical device types and locations, plumbing fixture locations, water heater/floor drain/water softener locations, furnace and return air location, heat source in all habitable rooms
- Gas line drawing required for any additional gas-fired appliances or gas line extension
- Blue Stakes (811) utility locate required before any digging
- HOA-approved and signed plans required for any exterior changes (e.g. walkouts), if applicable
- Plan Check Deposit not required for basement finishes only (per the city's Building Permit Requirements form), but the reduced 26% Plan Check fee still applies
Required documents
- RequiredBasement Permit Requirements ChecklistCity of Cedar Hills' official checklist specific to basement plan submittals, covering room labeling, life-safety devices, MEP locations, and utility-locate requirements.
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal, or as a Non-Digital (print) application.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Based on valuation (per International Building Code) | City of Cedar Hills Fee Schedule, effective 07/01/2026: same valuation-based 'Building Permit' line item used for all construction types; no separate flat fee for additions/remodels/basements. |
| Residential Plan Check (Basement Finish/Small Structures/Solar) | 26% of building permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Residential Plan Check (Basement Finish)(Small Structures)(Solar) — 26% of building permit fee — Building Permit — Resolution 01-05-2021A.' Confirmed distinct from the 65% rate used for new residential construction generally. |
| 1% State Fee | 1% of Building Permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026. |
| Refundable Improvement Bond | $4,000.00 (general); $3,000.00 for pools/accessory structures | City of Cedar Hills Fee Schedule, effective 07/01/2026, Resolution 05-21-2024B. |
Solar Panel (PV) Permit
VerifiedRequired for residential rooftop solar photovoltaic installations in Cedar Hills. Requires a Building Permit Application, two sets of plans meeting the city's Solar PV System Plan Review Requirements checklist, and a $300 plan-check deposit (check only, per the city's Installation Permit page).
Verified 2026-07-08 · Source
Requirements
- Building Permit Application, with 'solar panel installations' work type
- Two copies of a detailed site plan showing the home and all PV system components
- Structural Engineer of Record report/evaluation confirming the roof can support the added array load; Utah-licensed structural engineer, wet-stamped
- Mounting system details: module mounting system, added component weight, roof covering type and number of layers
- One-line diagram: PV system type, module count/wiring/layout, wire types/sizes, conduit, component locations, fuse/breaker ratings, and which home electrical panel the system backfeeds to
- Module manufacturer spec sheets (rated watts, volts, amps, Voc, Isc)
- Inverter manufacturer spec sheets (rated watts/volts, max AC output amps/voltage); utility-tied inverters must be listed 'utility interactive' meeting UL 1741 with ground fault protection
- Total array power calculations (watts, amps, volts, Voc at coldest expected temperature per NEC 690.7, Isc)
- System component listings and equipment ratings
- Illustrations of required signage and sign locations
- HOA-approved and signed plans, if applicable
- $300 plan-check deposit, check only
Required documents
- RequiredSolar PV System Plan Review Requirements ChecklistCity of Cedar Hills' official Solar Photovoltaic (PV) System Plan Submittal Checklist (form dated CHBD 08162016), covering site plan, structural engineer evaluation, mounting system, one-line diagram, module/inverter specs, array power calculations, component listings, and signage.
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal, or as a Non-Digital (print) application, for solar panel installations.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Based on valuation (per International Building Code) | City of Cedar Hills Fee Schedule, effective 07/01/2026: solar installations use the same valuation-based 'Building Permit' line item; no separate flat solar permit fee is published. |
| Residential Plan Check (Solar) | 26% of building permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Residential Plan Check (Basement Finish)(Small Structures)(Solar) — 26% of building permit fee — Resolution 01-05-2021A.' |
| Solar Plan-Check Deposit | $300.00 (check only) | City of Cedar Hills official Installation Permit page and Building Department FAQ: 'A building permit, two sets of plans, and a plan-check deposit of $300 are required for installation of solar panels.' The Installation Permit page specifies the deposit must be paid by check only. |
| 1% State Fee | 1% of Building Permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026. |
Commercial Building Permit
VerifiedRequired for new commercial construction (including commercial shell buildings) in Cedar Hills, regulated by the adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 7/1/2026; Cedar Hills' own Building Permit Requirements form still lists the 2021 IBC as of its 06/12/2025 revision, live re-checked 2026-07-16). Cedar Hills is a small, almost entirely residential planned community with limited commercial zoning concentrated along Cedar Hills Drive, but its Fee Schedule maintains a distinct 'Commercial/Industrial Plan Check' line (65% of the building permit fee), standalone commercial trade-permit and trade-inspection fees, non-residential impact fees, and a Cedar Hills Drive-specific street improvement fee, all separate from the residential fee structure. There is no separate commercial-specific submittal checklist published — the same Building Permit Requirements form used for residential construction governs commercial submittals too, and explicitly references 'COMM Check' energy-code documentation alongside 'RES Check' for residential.
Verified 2026-07-19 · Source
Requirements
- New commercial construction, regulated by the adopted 2024 IBC (per Utah Code § 15A-2-103(1)(a), effective 7/1/2026)
- Completed Building Permit Application (submitted via the online iworq permit portal or by print application)
- 2 sets of building plans drawn to scale, including a site plan (north arrow, lot dimensions, setbacks, easements, property lines, water meter/sewer lateral location, driveway/hard-surface locations, retaining walls), per the city's Building Permit Requirements form — the same checklist used for residential submittals
- Construction plans: floor plans, footing/foundation details, structural framing, electrical/mechanical/plumbing design details, and Energy Code compliance documentation via COMM Check (the Building Permit Requirements form explicitly lists 'RES Check, COMM Check, Manual D, J & S, etc. as applicable')
- Structural calculations stamped by a Utah-licensed structural engineer
- Concept/Preliminary/Final Site Plan Review approval for new commercial development — a separate Planning-level review process from the building permit itself, per the city's Fee Schedule
- Commercial/Industrial Plan Check Deposit, estimated actual cost, due at application
- Fire Department in-house plan review submittal if the project includes an automatic fire sprinkler system or fire alarm system
Required documents
- RequiredBuilding Permit Requirements ChecklistCity of Cedar Hills' official checklist (revised 06/12/2025), used for both residential and commercial submittals; explicitly lists 'COMM Check' as acceptable Energy Code compliance documentation for commercial projects. No separate commercial-only checklist is published by the city.
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal (cedarhills.portal.iworq.net/portalhome/cedarhills), or as a Non-Digital (print) application.
- RequiredConcept/Preliminary/Final Site Plan Review ApplicationRequired Planning-level review for new commercial development prior to or alongside the building permit; fee is billed separately from the building permit fee per the city's Fee Schedule.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Based on valuation (no flat table published; assessed per International Building Code valuation methodology) | City of Cedar Hills Fee Schedule, effective 07/01/2026, Planning/Building/Zoning section: 'Building Permit — Based on valuation — Building Permit — International Building Code.' Same line item used for both residential and commercial construction; no separate commercial dollar table is published. |
| Commercial/Industrial Plan Check | 65% of building permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Commercial/Industrial Plan Check — 65% of building permit fee — Building Permit — Resolution 09-20-2011B.' |
| Commercial/Industrial Plan Check Deposit | Estimated Actual Cost | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Commercial/Industrial Plan Check Deposit — Estimated Actual Cost — At Application — Resolution 02-07-2017A.' |
| 1% State Fee | 1% of Building Permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: '1% State Fee — 1% of Building Permit — Building Permit — International Building Code.' |
| Commercial Site Plan Review Fee (Concept/Preliminary/Final) | $2,000.00 + $150.00 per lot | City of Cedar Hills Fee Schedule, effective 07/01/2026, Development Fees section: 'Concept/Preliminary/Final Site Plan Review – Commercial — $2,000.00 + $150.00/Lot — At Application — Resolution 08-05-2025B.' A Planning-level development fee, billed separately from the building permit fee. |
| Commercial Trade Inspection Fees | Gas Line Inspection (Commercial) $65.00; Temporary Power & Permanent Power Inspection, each (Commercial) $65.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, New Construction Fees (Per ERU) table: 'Gas Line Inspection (Commercial) — $65.00 — Building Permit — Resolution 01-05-2021A' and 'Temporary Power & Permanent Power Inspection (each)(Commercial) — $65.00 — Building Permit — Resolution 01-05-2021A.' Both are higher than the $53.00 residential equivalents on the same table. |
| Commercial Trade Permits (Plumbing/Mechanical/Electrical) | $35.00 each | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Plumbing Permit (Commercial) — $35.00', 'Mechanical Permit (Commercial) — $35.00', and 'Electrical Permit (Commercial) — $35.00 — Building Permit — Resolution 01-05-2021A' (three separate line items). Residential trade work has no equivalent standalone fee — it is folded into the residential Building Permit fee. |
| Non-Residential Impact Fees (Per ERU/unit) | Public Safety (Non-Residential, per 1,000 unit) $711.18; Sewer (Cedar Hills, Non-Residential, by meter size) $1,207.44 (1") up to $33,808.28 (10"); Culinary Water (AWWA ratio, by meter size) $887.53 (3/4") up to $14,795.12 (4") | City of Cedar Hills Fee Schedule, effective 07/01/2026, Impact Fees (Per ERU) table: 'Public Safety – Non Residential, Per 1,000 Unit — $711.18', 'Sewer (Cedar Hills), Non-Residential' meter-size tiers (1" $1,207.44 through 10" $33,808.28), and 'Culinary Water / AWWA RATIOS 2023' meter-size tiers (3/4" $887.53 through 4" $14,795.12), all collected at Building Permit. |
| Transportation Impact Fee (Commercial Land Use Categories) | Varies by use, e.g. General Office Building $1,306.02 per 1,000 sq ft; Business Park $1,106.49 per 1,000 sq ft; Shopping Plaza $4,913.91 per 1,000 sq ft gross leasable area (40% pass-by); Business Hotel $281.16 per room | City of Cedar Hills Fee Schedule, effective 07/01/2026, Transportation table: 'General Office Building, 1,000 SQ FT gross floor area — $1,306.02', 'Business Park, 1,000 SQ FT gross floor area — $1,106.49', 'Shopping Plaza, 1,000 SQ FT gross leasable area (40% Pass-By) — $4,913.91', 'Business Hotel, Rooms — $281.16' — Resolution 02-07-2023B. |
| Commercial Street Improvement Fee (Cedar Hills Drive) | $10,750.00 per acre | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Commercial Street Improvement Fee (Cedar Hills Drive) – Cost Per Acre — $10,750 — Building Permit — Series 2000 Road Bond.' Applies specifically to commercial development fronting Cedar Hills Drive, the city's primary commercial corridor. |
| Automatic Fire Protection System / Fire Alarm Plan Review (In-House) | Sprinkler system: <100 heads $75.00; 101-199 heads $100.00; 200-299 heads $150.00; >300 heads base fee plus $0.50/head ($200.00 shown). Fire alarm new system: $100.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: 'Automatic Fire Protection System / In House Plan Review — <100 heads $75.00, 101-199 heads $100.00, 200-299 heads $150.00, >300 heads – base fee plus $0.50 per head $200.00 — Resolution 07-16-2019A' and 'Fire Alarm System (Fees are for In-House Plan Reviews Only) / Plan Review — New System $100.00 — Resolution 07-16-2019A.' |
Commercial Tenant Improvement / Tenant Finish Permit
VerifiedRequired for commercial remodel and tenant improvement (tenant finish) work in existing commercial buildings in Cedar Hills. Cedar Hills' Fee Schedule does not carry a reduced tenant-improvement plan-check rate distinct from new commercial construction — unlike the residential schedule, which discounts basement finishes/small structures/solar to 26% of the building permit fee, commercial tenant improvements are billed at the same 'Commercial/Industrial Plan Check' rate of 65% of the building permit fee as new commercial construction. No separate tenant-improvement-specific submittal checklist is published; the same general Building Permit Requirements form is used.
Verified 2026-07-19 · Source
Requirements
- Commercial remodel or tenant improvement scope within an existing commercial structure, regulated by the adopted 2024 IBC (per Utah Code § 15A-2-103(1)(a), effective 7/1/2026)
- Completed Building Permit Application (online iworq portal or print application)
- 2 sets of scale plans per the city's Building Permit Requirements form — the same general checklist used for new construction; no distinct tenant-improvement-specific checklist is published
- Structural calculations stamped by a Utah-licensed structural engineer, if the scope includes structural work
- Energy Code compliance documentation (COMM Check) if the scope affects the building envelope or mechanical/electrical systems
- Fire Alarm plan review submittal if the remodel adds to or modifies an existing fire alarm system
- Commercial Hood System plan review submittal if the scope adds or modifies a commercial kitchen exhaust hood
- Commercial/Industrial Plan Check Deposit, estimated actual cost, due at application
Required documents
- RequiredBuilding Permit Requirements ChecklistCity of Cedar Hills' official checklist (revised 06/12/2025), used generally for construction submittals including tenant improvements; no dedicated TI-specific checklist is published by the city.
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal, or as a Non-Digital (print) application.
- OptionalFire Alarm / Commercial Hood System Plan Review SubmittalRequired only if the tenant improvement scope adds or modifies a fire alarm system or a commercial kitchen exhaust hood; reviewed in-house by the Fire Department per the city's Public Safety fee table.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Based on valuation (no flat table published; assessed per International Building Code valuation methodology) | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Building Permit — Based on valuation — Building Permit — International Building Code.' Same line item used for all construction types, including tenant improvements. |
| Commercial/Industrial Plan Check | 65% of building permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Commercial/Industrial Plan Check — 65% of building permit fee — Building Permit — Resolution 09-20-2011B.' No reduced rate is published for tenant improvements/remodels distinct from new commercial construction — both fall under this single line item. |
| Commercial/Industrial Plan Check Deposit | Estimated Actual Cost | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Commercial/Industrial Plan Check Deposit — Estimated Actual Cost — At Application — Resolution 02-07-2017A.' |
| 1% State Fee | 1% of Building Permit fee | City of Cedar Hills Fee Schedule, effective 07/01/2026: '1% State Fee — 1% of Building Permit — Building Permit — International Building Code.' |
| Commercial Trade Permits (Plumbing/Mechanical/Electrical) | $35.00 each | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Plumbing Permit (Commercial) — $35.00', 'Mechanical Permit (Commercial) — $35.00', and 'Electrical Permit (Commercial) — $35.00 — Building Permit — Resolution 01-05-2021A.' Directly relevant to TI work that reconfigures plumbing, mechanical, or electrical systems. |
| Addendum Plan Review | $65.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Addendum Plan Review — $65.00 — Per Occurrence — Resolution 02-07-2023B.' Applies if submitted plans are revised after initial plan check. |
| Fire Alarm System Plan Review (Remodel) | $50.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: 'Fire Alarm System (Fees are for In-House Plan Reviews Only) / Plan Review — Remodel — $50.00 — Resolution 07-16-2019A.' |
| Commercial Hood Systems Plan Review | $100.00 per hood | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: 'Commercial Hood Systems / Plan Review each hood — $100.00 — Resolution 07-16-2019A.' Relevant to restaurant/food-service tenant finish work adding a kitchen exhaust hood. |
| Re-inspection Fee | $100.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026: 'Re-inspection Fee — $100.00 — Prior to Re-inspect — Resolution 09-20-2005A.' |
Sign Permit
VerifiedRequired in Cedar Hills for erecting, altering, or relocating a sign, under City Code § 10-5-26 (Signs), added by Ordinance No. 3-7-2006B. The ordinance text itself does not publish a specific dollar fee — it requires 'a new fee paid' upon permit renewal without stating the amount. Re-chased 2026-07-20: the dollar figure was located and confirmed by fetching the city's live Fee Schedule page (cedarhillsutah.gov/page/fee-schedule) through a reader-proxy (r.jina.ai), which surfaced a direct link to the city's official 'Current Fee Schedule' PDF (effective 07/01/2026). That PDF's Administration table lists 'Sign Permit — $1.00 — Per Sign, Per occurrence — Resolution 04-18-2006C.' The table cell text was column-jumbled on plain pdftotext extraction, so the row was confirmed by rendering page 2 of the PDF to a PNG image and reading it visually.
Verified 2026-07-20 · Source
Requirements
- All signs require a permit or approval from the City; it is unlawful to erect, alter, or relocate a sign without first obtaining a sign permit, per § 10-5-26(C)(3)(d)
- Application shall be made on a City-provided form and may include a site plan, sign layout, and elevation of existing and future buildings, per § 10-5-26(C)(3)(a)
- A permit expires and becomes void if work is not commenced, or is suspended/abandoned, within 60 days of the permit date; a new permit and a new fee are then required, per § 10-5-26(C)(3)(b)
- All signs must bear a City of Cedar Hills sign insignia furnished by the Zoning Administrator at permit issuance, installed in a visible, legible, and accessible location, per § 10-5-26(C)(4)
- Written consent of the property owner is required before erecting a sign on their property, per § 10-5-26(C)(5)
- Billboards, animated/flashing signs, marquee signs, movable/portable signs, roof signs, rotating signs, snipe signs, and most window signs are expressly prohibited, per § 10-5-26(C)(2)
- Short-Term Signs and Campaign Signs do not require a permit, per § 10-5-26(C)(3)(f)
- Residential Zone signs: most allowed sign types capped at 8 sq ft area and 6 ft height; temporary signs allowed up to 3 months in any 6-month period; signs on undeveloped parcels capped at 24 sq ft and 10 ft height
- Commercial Zone signs: most allowed sign types capped at 8 sq ft area and 6 ft height for temporary signs (2-month period); monument signs allowed only at locations approved during final development approval; project approval signs capped at 32 sq ft and 10 ft height
Required documents
- RequiredSign Permit ApplicationCity-provided form; may require a site plan, sign layout, and building elevations, per § 10-5-26(C)(3)(a).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign Permit Fee | $1.00 per sign, per occurrence | Cedar Hills official Fee Schedule (effective 07/01/2026), Administration table: 'Sign Permit — $1.00 — Per Sign, Per occurrence — Resolution 04-18-2006C.' Confirmed 2026-07-20 by rendering page 2 of the current fee-schedule PDF to a PNG image and reading it visually, since plain text extraction column-jumbled the table. The same fee also applies to a required renewal ('a new fee paid') when a permit expires per City Code § 10-5-26(C)(3)(b), since the ordinance does not carve out a separate renewal-fee amount. |
EV Charger / EVSE Permit
Cedar Hills does not publish a distinct "EV Charger" or "EVSE" fee line item. Its Fee Schedule (effective 07/01/2026) lists an "Electrical Permit (Commercial)" category priced off the Building Permit fee under Resolution 05-21-2024B, with no equivalent residential electrical-permit line shown separately from the general Building Permit. A full-text search of the current Fee Schedule found no mention of "EV," "EVSE," "electric vehicle," or "charging station." An EV charger installation in Cedar Hills would be permitted through the city's standard electrical/building permit process, priced under the Building Permit fee rather than a dedicated EV category.
Reviewed 2026-07-20 · Source
Requirements
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Cedar Hills
- Dedicated 240V circuit and/or panel capacity installed by a licensed electrician
- Electrical/building permit filed with the Cedar Hills Building Department
Required documents
- RequiredBuilding/Electrical Permit ApplicationFiled with the Cedar Hills Building Department for the electrical work associated with the charger installation.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit (Commercial) — priced off the Building Permit fee (no distinct EV charger line item; residential rate not separately itemized) | Per Building Permit fee (valuation-based) | Cedar Hills Fee Schedule, effective 07/01/2026, Planning/Building/Zoning section: 'Electrical Permit (Commercial) ... Building Permit ... Resolution 05-21-2024B.' No EV/EVSE line item exists anywhere in the schedule; no distinct residential electrical permit fee line was found either. |
Automatic Fire Protection (Fire Sprinkler) System Permit
VerifiedRequired in Cedar Hills for installation of an automatic fire sprinkler system, plan-reviewed in-house by the City (not delegated to a third-party reviewer) under the Public Safety section of the City's own Fee Schedule (effective 07/01/2026), Resolution 07-16-2019A. These are the same 'Automatic Fire Protection System / In House Plan Review' fees already itemized within this record's commercial-building-permit entry; this entry consolidates them as their own permit type, matching the convention used for this permit category in peer Utah County jurisdictions (e.g. American Fork's fire-sprinkler-permit). Fees are priced by sprinkler head count, plus separate acceptance-testing fees; there is no distinct fee schedule from a separate joint fire authority — Cedar Hills' own Public Safety fee table is the governing source.
Verified 2026-07-21 · Source
Requirements
- Automatic fire sprinkler system installation (or remodel/extension) in a commercial building or tenant space within Cedar Hills
- Sprinkler system plans, including sprinkler head count, submitted to the City for in-house plan review under Resolution 07-16-2019A
- Filed alongside the underlying Building Permit (new commercial construction or tenant improvement) — Cedar Hills does not publish a standalone sprinkler-permit application separate from the Building Permit Application
- Acceptance testing (underground flush, hydrostatic, and acceptance tests) required prior to final approval
Required documents
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal, or as a Non-Digital (print) application, for the underlying commercial construction or tenant improvement project the sprinkler system is part of.
- RequiredAutomatic Fire Protection System PlansSprinkler system plans sufficient for in-house plan review, including sprinkler head count for fee calculation, per the City's Public Safety fee table.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Automatic Fire Protection System — In House Plan Review, <100 heads | $75.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section, page 9: '<100 heads — $75.00 — Resolution 07-16-2019A.' Confirmed 2026-07-21 by rendering page 9 of the current fee-schedule PDF to a PNG image and reading it visually, since plain-text extraction jumbled the table (same column-jumbling issue previously documented for this fee schedule's Sign Permit row). |
| Automatic Fire Protection System — In House Plan Review, 101-199 heads | $100.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: '101-199 heads — $100.00 — Resolution 07-16-2019A.' |
| Automatic Fire Protection System — In House Plan Review, 200-299 heads | $150.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: '200-299 heads — $150.00 — Resolution 07-16-2019A.' |
| Automatic Fire Protection System — In House Plan Review, >300 heads | $200.00 base fee plus $0.50 per head | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: '>300 heads – base fee plus $0.50 per head — $200.00 — Resolution 07-16-2019A.' |
| Acceptance Testing (Underground Flush, Hydrostatic, Acceptance) | $50.00 each (Underground Flush; Hydrostatic (2); Acceptance (2); Any Acceptance (2)) | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section, Acceptance Testing sub-table: 'Underground Flush — $50.00', 'Hydrostatic (2) — $50.00', 'Acceptance (2) — $50.00', 'Any Acceptance (2) — $50.00' — all Resolution 07-16-2019A. |
Fire Alarm System Permit
VerifiedRequired in Cedar Hills for installation of a new fire alarm system, remodel of an existing system, or extension of alarm coverage to additional floors, plan-reviewed in-house by the City under the Public Safety section of the City's own Fee Schedule (effective 07/01/2026), Resolution 07-16-2019A, explicitly labeled 'Fees are for In-House Plan Reviews Only.' These are the same fees already itemized within this record's commercial-building-permit and commercial-tenant-improvement-permit entries (new system and remodel, respectively); this entry consolidates them as their own permit type, matching the convention used for this permit category in peer Utah County jurisdictions (e.g. American Fork's fire-alarm-permit).
Verified 2026-07-21 · Source
Requirements
- Fire alarm system installation, remodel, or extension to additional floors in a commercial building or tenant space within Cedar Hills
- Fire alarm system plans submitted to the City for in-house plan review before installation, remodel, or extension, per Resolution 07-16-2019A
- Filed alongside the underlying Building Permit (new commercial construction or tenant improvement) — Cedar Hills does not publish a standalone fire-alarm-permit application separate from the Building Permit Application
Required documents
- RequiredBuilding Permit ApplicationSubmitted online via the Cedar Hills iworq Building Permit Portal, or as a Non-Digital (print) application, for the underlying commercial construction or tenant improvement project the fire alarm system is part of.
- RequiredFire Alarm System PlansPlans for the new fire alarm system, remodel, or floor-addition scope, submitted for in-house plan review.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fire Alarm System Plan Review — New System (in-house) | $100.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section, page 9: 'Fire Alarm System (Fees are for In-House Plan Reviews Only) / Plan Review — New System — $100.00 — Resolution 07-16-2019A.' Confirmed 2026-07-21 by rendering page 9 of the current fee-schedule PDF to a PNG image and reading it visually, since plain-text extraction jumbled the table. |
| Fire Alarm System Plan Review — Remodel (in-house) | $50.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: 'Remodel — $50.00 — Resolution 07-16-2019A.' Also cited in this record's commercial-tenant-improvement-permit entry. |
| Fire Alarm System Plan Review — Additional Floors (in-house) | $50.00 | City of Cedar Hills Fee Schedule, effective 07/01/2026, Public Safety section: 'Additional Floors — $50.00 — Resolution 07-16-2019A.' |
Change of Use / Change of Occupancy
VerifiedCedar Hills does not publish a standalone Change of Use, Change of Occupancy, or existing-building Certificate of Occupancy re-issuance permit or fee. A full-text review of the current Fee Schedule (effective 07/01/2026) found zero mentions of 'change of use,' 'change of occupancy,' or 'certificate of occupancy' anywhere in the document, confirming the finding already noted in this record's commercial-tenant-improvement-permit entry. City Code Title 8, Chapter 1 (Codes Adopted and Regulations) requires a building permit generally for 'any work within the city regulated or controlled by this chapter,' with no separate change-of-use category. In practice, a use or occupancy change in an existing commercial space in Cedar Hills is processed through (1) the Commercial Tenant Improvement / Tenant Finish Permit if the change involves construction scope, and (2) the City's own annual Commercial Business License, which itself bundles a required Building and Fire inspection.
Verified 2026-07-21 · Source
Requirements
- A use or occupancy change in an existing commercial building or tenant space within Cedar Hills, where the change involves construction or tenant-improvement scope, is processed as a Commercial Tenant Improvement / Tenant Finish Permit (see that permit type in this record for full requirements and fees)
- An annual Commercial Business License is required for the business occupying the space, per the City's Business Licensing fee table
- A Building and Fire inspection is required as part of the Commercial Business License process, per Resolution 12-09-2008A
- No separate Change of Use, Change of Occupancy, or Certificate of Occupancy application, fee, or process is published by the City independent of the above two mechanisms
Required documents
- OptionalBuilding Permit Application (Tenant Improvement)Required only if the use/occupancy change involves construction or tenant-improvement scope; see the Commercial Tenant Improvement / Tenant Finish Permit entry in this record.
- RequiredCommercial Business License ApplicationAnnual license required for the business occupying the space, filed with the City; includes a Building and Fire inspection component.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Commercial Business License — Base | $75.00 per year | City of Cedar Hills Fee Schedule, effective 07/01/2026, Business Licensing section, page 3: 'Commercial / Base — $75.00 — Per year — Resolution 12-09-2008A.' Confirmed 2026-07-21 by rendering page 3 of the current fee-schedule PDF to a PNG image and reading it visually, since plain-text extraction jumbled the table. |
| Commercial Business License — Building and Fire Inspection | $60.00 per year | City of Cedar Hills Fee Schedule, effective 07/01/2026, Business Licensing section: 'Building and Fire inspection — $60.00 — Per year — Resolution 12-09-2008A.' This inspection is the closest thing to an occupancy-change check Cedar Hills publishes — there is no separate standalone Change of Use or Certificate of Occupancy inspection fee. |
| Commercial Business License — Additional Per Employee | $10.00 per year | City of Cedar Hills Fee Schedule, effective 07/01/2026, Business Licensing section: 'Additional Per Employee — $10.00 — Per year — Resolution 06-18-2002A.' |
| Commercial Business License — Temporary Use | $40.00 per specified time period | City of Cedar Hills Fee Schedule, effective 07/01/2026, Business Licensing section: 'Temporary Use — $40.00 — Per specified time period — Resolution 04-03-2012A.' |
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cedar Hills building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.