You are viewing the permanent link for the record currently in effect, published 2026-07-16.

Washington City building permits

Verified

Washington City, Utah — as published 2026-07-16.

Verified 2026-07-03 · Source

Codes adopted

2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a). Washington City Building Department's own 'Climatic and Geographic Design Criteria' notice was live-checked 2026-07-16 (raw HTML, not an AI summary) and STILL displays '2021 IBC' — the city page has NOT been updated to reflect the statewide 7/1/2026 transition2021 Utah State Residential Code (based on IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment. Washington City's own page (live-checked 2026-07-16) correctly still shows '2021 UTAH STATE RESIDENTIAL CODE'Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized on Washington City's own page, added here per statute2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IPC' — the city page has NOT been updated2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IMC' — the city page has NOT been updated2024 International Fuel Gas Code (IFGC, listed on city page as 'IFCI') — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IFCI' — the city page has NOT been updated2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 amendment. Washington City Building Department page explicitly updated 'MAY 7 2025 UPDATE OF ADOPTED CODES BY THE STATE OF UTAH: 2023 NEC code update' (superseding the previously listed 2020 NEC, still shown struck-through/superseded on the live page as of 2026-07-16); this is one of the few Washington County-area jurisdiction pages independently confirmed current on the electrical code edition, not just inferred from state law2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IECC' — the city page has NOT been updatedResidential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(n). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 ISPSC', and the city's Swimming Pool permit instructions (ISPSC sections 305.3.3/305.3.4, 807, 809, 323) likewise still cite the 2021 edition — the city has NOT updated either page2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); NOT listed at all on Washington City's own Building Department page (live-checked 2026-07-16), added here per statute since the City's own materials omit it entirelyICC A117.1-2009 or 2017 (Accessibility Standard) — listed on Washington City Building Department page; not part of Utah Code § 15A-2-103's construction-code list, left unchanged2018 IBC construction-type valuation table (ICC Building Valuation Data) — used directly in the city's own published 'Square Foot Construction Costs Table B' on its fee schedule; a fee-calculation reference table, not a code edition, left unchangedNOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Washington City's own Building Department page ('Climatic and Geographic Design Criteria' notice) was independently re-fetched 2026-07-16 (raw HTML, not an AI summary, to guard against summarizer fabrication) and STILL displays 2021 editions for IBC/IMC/IPC/IFCI(IFGC)/IECC/ISPSC — confirmed NOT updated to reflect the statutory transition, unlike its NEC line which was separately updated in May 2025. This file now states the governing statutory codes (2024/2021/2023 editions per subsection) as current per Utah's statewide-mandatory code regime (Utah Code § 15A-1-204), while preserving the City's own (lagging) page text above as historical/local-document context. The Utah Code § 15A-2-103 citation in the sources array below has been updated to the current in-force version link

Permit types & fees

Residential Building Permit (Single Family)

Verified

Required for new single-family residential construction in Washington City. Governed by the 2021 Utah State Residential Code. Fees are valuation-based per Washington City's own published Building Permit Fee Table (a distinct, current ICC-style fee schedule — not St. George's 1997 UBC scale or Washington County's identical-to-St.-George scale).

Verified 2026-07-03 · Source

Requirements

  • New single-family residential construction
  • Submitted through the Washington City CityInspect Builder Account portal
  • New Single Family permits use the city's 'Packet Review' process — all reviewing departments (building, planning, power, public works, fire) review concurrently and either approve or return the packet for corrections

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Submitted via the Washington City CityInspect portal; new users register for a Builder Account before applying
  • RequiredConstruction PlansFull architectural and structural drawings reflecting the adopted 2021 Utah State Residential Code
  • RequiredBuilder ValuationProject valuation entered on the Builder Info page of the application — drives the fee calculation from the city's Building Permit Fee Table

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1.00 to $1,000.00$30.00Washington City Building Department Master Fee Schedule (published Google Sheets PDF linked from washingtoncity.org/development/building/buildingfeeschedule), fetched and verified 2026-07-03. This fee table is Washington City's own — it is a current ICC-style valuation table distinct from the 1997 UBC scale used by St. George and unincorporated Washington County.
Building Permit — valuation $2,001 to $3,000$62.43Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation $10,001 to $11,000$152.43Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation $25,001 to $26,000$317.33Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation $50,001 to $51,000$499.81Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation $99,001 to $100,000$738.93Washington City Building Department Master Fee Schedule, verified 2026-07-03; the full $1–$100,000 table is tabulated in $1,000 increments in the source document
Building Permit — valuation $100,001 to $500,000$738.93 for the first $100,000.00 plus $4.03 for each additional $1,000.00, or fraction thereof, to and including $500,000.00Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation $500,001 to $1,000,000$2,350.93 for the first $500,000.00 plus $3.44 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00Washington City Building Department Master Fee Schedule, verified 2026-07-03
Building Permit — valuation over $1,000,000$4,070.93 for the first $1,000,000.00 plus $2.42 for each additional $1,000.00, or fraction thereofWashington City Building Department Master Fee Schedule, verified 2026-07-03
Plan Review Fee45% of the total calculated building permit feeWashington City Building Department Master Fee Schedule, verified 2026-07-03 — notably higher than St. George's 65%-of-a-much-smaller-base-fee structure and Washington County's fee approach; direct like-for-like comparison requires computing both on the same valuation.

Swimming Pool Permit

Verified

Required for swimming pool construction in Washington City. Governed by the residential provisions of the 2024 ISPSC (Utah Code § 15A-2-103(1)(n), effective 7/1/2026, superseding the 2021 edition; Washington City's own pool-permit page still cites the 2021 ISPSC as of 2026-07-16) and the 2021 IRC as adopted, plus Washington City Code Title 4, Chapter 6 (pool fencing/gates). Fees are valuation-based per the same Building Permit Fee Table used for building permits.

Verified 2026-07-03 · Source

Requirements

  • Engineered, lot-specific pool plans with a current engineer stamp, signed and dated
  • Pool fencing and gates complying with Washington City Code Title 4, Chapter 6, paragraphs 3 and 4, including ISPSC 305.3.3 and 305.3.4
  • Site plan showing pool location, dimensions from pool to property lines/structures, easements, and pool equipment location
  • A copy of the recorded final plat

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Select 'Pool' as the permit type
  • RequiredSite PlanScaled overview of the lot showing north arrow, street name/address, lot dimensions, pool location, easements, pool fencing/gates per Washington City Code Title 4 Ch. 6 and ISPSC 305.3.3/305.3.4, existing structures, retaining walls, and pool equipment location
  • RequiredFinal PlatRecorded final plat, obtainable via the Washington County GIS Html5Viewer subdivision search
  • RequiredEngineered Pool PlansCurrent engineer stamp; must show cross-sectional depth/slope design per ISPSC section 807 (statewide-current edition is 2024 per Utah Code § 15A-2-103(1)(n) effective 7/1/2026, though Washington City's own page still cites 2021 as of 2026-07-16); non-conducting pool shells require a water bond detail per 2021 IRC E4204.3 (IRC unchanged); stairs/rise-run per ISPSC section 809 and handholds per section 323

Fee schedule

Fee typeAmountNotes
Pool PermitValuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)Washington City's Swimming Pool permit page (washingtoncity.org/development/building/poolinspections, fetched 2026-07-03) requires a 'Builder Valuation' field on the application but does not publish a separate flat pool-permit fee distinct from the general Building Permit Fee Table — confirmed by direct fetch of both the pool page and the Master Fee Schedule PDF; no flat pool fee tier is listed. This is a grounded valuation-based fee, not an estimate.

Solar Panel Permit

Verified

Required for solar photovoltaic installation in Washington City. Washington City imposes two local prerequisites not found in the sibling St. George or Washington County files: installer pre-approval by the Washington City Power Department, and mandatory third-party plan pre-approval.

Verified 2026-07-19 · Source

Requirements

  • Installer must be an approved installer with the Washington City Power Department PRIOR to submitting for permit (required as of May 15, 2023)
  • All plans must be pre-approved by an approved third-party reviewer PRIOR to submitting for permit (required as of July 1, 2023)
  • Renewable Resource Agreement (RRA) with original notarized property-owner signature required for properties in the Washington City Power service area
  • Properties in the Dixie Power service area instead require a Dixie Power Net Meter Agreement

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Select 'Solar' as the permit type
  • RequiredRenewable Resource AgreementCompleted document with original notarized property-owner signature (docu-sign not accepted); original must be delivered in person to the Washington City Power Department at 111 N 100 E; a copy uploaded with the permit application
  • OptionalDixie Power Net Meter AgreementRequired instead of the Washington City RRA for properties in the Dixie Power service area
  • RequiredSite Plan / Single-Line DrawingSingle-page site plan indicating location of solar modules, inverter, batteries (if any), lockable disconnect switch, and point of utility connection

Fee schedule

Fee typeAmountNotes
Solar PermitValuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)Washington City's Solar Permit Submittal Requirements page (washingtonutah.gov/development/building/solarpermitrequirements, re-verified 2026-07-19; formerly hosted at washingtoncity.org, which now 301-redirects to the same page on the washingtonutah.gov domain) requires a 'Valuation' field correlated to the RRA project cost, but does not publish a separate flat solar-specific fee — assessed on the same Building Permit Fee Table as other permit types. This is a grounded valuation-based fee, not an estimate.

Accessory Dwelling Unit (ADU)

Verified

Required for construction of a secondary dwelling unit in Washington City. Qualification is governed by Washington City Ordinance #2019-25, which the city's own permit page instructs applicants to review before designing plans.

Verified 2026-07-03 · Source

Requirements

  • Property must qualify under Washington City Ordinance #2019-25 — contact Planning and Zoning at (435) 656-6325 before creating plans
  • Accessory Dwelling Unit Deed Restriction — must be completed, notarized, and recorded at the Washington County Assessor's office; the recorded document is uploaded with the permit application
  • Site plan showing lot layout, setbacks, easements, topographical details (if slope >10%), utilities, and nearest hydrant location
  • Defensible space provisions per the Utah Wildland Urban Interface Code (adopted under Utah Code § 15A-2-103), if required

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Select 'Accessory Building' as the permit type
  • RequiredADU Deed RestrictionCompleted, notarized, and recorded at the Washington County Assessor's office
  • OptionalOwner Builder CertificationRequired if the homeowner is acting as the builder (no contractor/business license required in that case)
  • RequiredSite PlanSingle-page, drawn to scale, with north arrow/legend, lot size/dimensions, setbacks, easements, retaining walls, utilities, driveway locations, and nearest hydrant

Fee schedule

Fee typeAmountNotes
Building PermitValuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)ADUs are assessed on the same Building Permit Fee Table as other new construction — Washington City's ADU permit page (washingtoncity.org/development/building/ResidentialDetachedAccessory, fetched 2026-07-03) does not publish a separate ADU-specific fee tier.

Demolition Permit

Verified

Required for demolition of structures in Washington City, including asbestos report and Fire Department coordination for explosive use.

Verified 2026-07-03 · Source

Requirements

  • Asbestos report upload required with permit application
  • If explosives are used at any time during demolition, prior written approval from the Washington City Fire Department is required
  • WCSW (Washington County Solid Waste) form completion required as part of submittal

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Complete builder valuation and required fields
  • RequiredAsbestos ReportUploaded with the permit application
  • OptionalFire Department Explosives ApprovalWritten approval required if explosives are used during demolition; uploaded to the 'Additional Document' field
  • RequiredWCSW FormWashington County Solid Waste form included with submittal

Fee schedule

Fee typeAmountNotes
Demolition PermitValuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)Washington City's Demolition Permit Requirements page (washingtoncity.org/development/building/DemoPermitRequirements, fetched 2026-07-03) requires a 'Builder Valuation' field but does not publish a separate flat demolition fee tier — assessed on the same Building Permit Fee Table.

Simple Permit (Electrical / Gas Line / Plumbing / HVAC Equipment Swap)

Verified

Washington City's own consolidated permit category for straightforward trade work — generators, water heater replacement, HVAC equipment upgrades, electrical meter upgrades, and gas line additions — submitted as a single 'Simple Permit' rather than separate trade-specific permits. This category and its explicit examples are unique to Washington City among the three Washington County jurisdictions in this corpus.

Verified 2026-07-03 · Source

Requirements

  • Generator installation
  • Water heater replacement
  • HVAC equipment upgrades
  • Electrical meter upgrades
  • Gas line additions
  • Washington City or current Business License number required for Builder and all Subcontractors

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Select 'Electrical', 'Gas Line', or 'Plumbing' as the permit type most compatible with the inspection need
  • RequiredSite PlanSingle-page site plan with lot identification and the scope-of-work area clearly depicted/highlighted, labeling the street and identifying fence/gate access
  • RequiredEquipment SpecificationsManufacturer specs and installation instructions for the equipment being installed
  • RequiredPhotos of Current EquipmentPhotos of the existing equipment relevant to the installation/inspection

Fee schedule

Fee typeAmountNotes
Simple Permit (Electrical/Gas Line/Plumbing)Valuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)Washington City's Simple Permit page (washingtoncity.org/development/building/simplepermit, fetched 2026-07-03) requires a 'Builder Valuation' field but does not publish a separate flat fee tier for this permit category — assessed on the same Building Permit Fee Table.

EV Charger / EVSE Permit

Verified

Washington City has not published a distinct EV-charger fee category. EV charger/EVSE installation is treated as standard electrical work filed under the city's 'Simple Permit' category: the official Simple Permit Requirements page instructs applicants to select 'ELECTRICAL' as the permit type, lists example projects (generators, water heater replacement, HVAC equipment upgrades, electrical meter upgrades, gas line additions) with no distinct EV-charger or electric-vehicle-charging line item, and assesses the same valuation-based Building Permit Fee Table used for other Simple Permit work.

Verified 2026-07-20 · Source

Requirements

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property, filed as an 'Electrical' Simple Permit
  • Washington City or current Business License number required for Builder and all Subcontractors

Required documents

  • RequiredOnline Permit Application (CityInspect Builder Account)Select 'ELECTRICAL' as the permit type, per the Simple Permit Requirements page — Washington City has no dedicated EV-charger permit category.
  • RequiredSite PlanSingle-page site plan with lot identification and the scope-of-work area clearly depicted/highlighted, labeling the street and identifying fence/gate access
  • RequiredEquipment SpecificationsManufacturer specs and installation instructions for the EV charger (EVSE) being installed
  • RequiredPhotos of Current EquipmentPhotos of the existing electrical panel/equipment relevant to the installation/inspection

Fee schedule

Fee typeAmountNotes
Simple Permit (Electrical)Valuation-based per the Washington City Building Permit Fee Table (see residential building permit fees)Washington City's Simple Permit page (washingtoncity.org/development/building/simplepermit, live-checked 2026-07-19) requires a 'Builder Valuation' field but publishes no separate flat fee tier or EV-specific line item — assessed on the same Building Permit Fee Table as other Simple Permit / Electrical work.

Commercial Building Permit

Verified

Required for new commercial construction, additions, and common area buildings in Washington City. Building permit applications and plans will not be accepted until Civil Plans are approved. Washington City publishes its own detailed 'Commercial Plans Submittal Checklist' and a step-by-step CityInspect submittal guide distinct from the residential process, and calculates the fee from the city's own current valuation-based Building Permit Fee Table plus a Square Foot Construction Costs table (2018 IBC) covering commercial occupancy classifications such as B Business and M Mercantile — with a Plan Review Fee equal to 45% of the total calculated building permit fee.

Verified 2026-07-19 · Source

Requirements

  • All Commercial/Industrial building permits require completion of the Pre-Submittal Process before submitting complete building plans — contact the Building Department at (435) 656-6326 to begin, per the city's official Commercial Plans Submittal Checklist
  • Completed and approved Washington City Commercial Building Permit Pre-submittal Information form (Commercial Pre-Submittal Packet, washingtoncity.org/downloads/building/CommercialPreSubmittalPacketWashingtonCity.pdf) — 'Commercial/Industrial building permit submittals will not be accepted without this item'
  • For Commercial New Construction, Additions, and Common Area Buildings, building permit applications and plans will not be accepted until Civil Plans are approved — this is not a deferral item
  • Approved Civil Drawings (Site Construction Plans) — city-stamped and signed civil plans uploaded with the application
  • SWPPP (Stormwater Pollution Prevention Plan) and SWPPP Notice of Intent (NOI) — the NOI inspection is required for initiation of the Stormwater Permit and must be scheduled at footings
  • Commercial Checklist, completed and signed — 'permit applications will not be accepted without a Commercial Checklist'
  • Fire Review Information Form, Fire & Life Safety (F&LS) plan, fire sprinkler and fire alarm plans as applicable
  • Washington County Water Conservancy District (WCWCD) receipt confirming the impact fee has been paid
  • Applications submitted via the CityInspect Builder Account, selecting 'Commercial (New Build)' or 'Commercial Addition' for permit type

Required documents

  • RequiredCommercial Pre-Submittal PacketWashington City's official pre-submittal information form; required before complete building plans can be submitted, per the Commercial Plans Submittal Checklist. Current codes listed on the checklist: 2018 IBC, 2018 IMC, 2018 IPC, 2017 NEC, 2018 IFCI, 2018 IECC with Utah State Amendments — stale relative to the current statewide-mandatory 2024 IBC/IPC/IMC/IECC and 2023 NEC under Utah Code § 15A-2-103, effective 7/1/2026; the statute controls regardless of the checklist's un-updated edition list.
  • RequiredWashington City Commercial Plans Submittal ChecklistDetailed city-published checklist covering site plan (topographical plot plans, lot dimensions, building footprint, accessible parking/routes), title page (occupancy classification, construction type, square footage, height, occupant load, sprinklered status, allowable area, special inspections statement), foundation plan, floor plan, exterior elevations, structural/architectural details, structural plans, prefabricated trusses, HVAC plan (with COMcheck), plumbing layout, electrical plan (with energy code compliance check), calculations (two wet-stamped copies), fire sprinkler plans, and handicap accessibility requirements including for remodels/tenant improvements.
  • RequiredCommercial Checklist (CityInspect submittal)Completed and signed checklist uploaded with the CityInspect application; per Washington City's Commercial New Build and Additions submittal guide, 'permit applications will not be accepted without a Commercial Checklist.'
  • RequiredApproved Civil Drawings (Site Construction Plans)City-stamped and signed civil plans uploaded to the CityInspect application. 'Note: permit application will not be accepted without approved civil plans. This item is not a deferral.'
  • RequiredFire Review Information FormCompleted form indicating any requested deferral, plus a single-page Fire & Life Safety plan, fire sprinkler plans, and fire alarm system plans as applicable.
  • RequiredCOMcheck Energy Compliance DocumentationSigned and dated energy code compliance documentation, per the CityInspect Commercial New Build and Additions submittal requirements.
  • RequiredWashington County Water Conservancy District (WCWCD) ReceiptCompleted WCWCD form/receipt confirming the water impact fee has been paid, uploaded with the application; contact Public Works if the fee has not yet been paid.

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1.00 to $1,000.00$30.00Washington City Building Department Master Fee Schedule (Google Sheets PDF linked from washingtonutah.gov/development/building/buildingfeeschedule), fetched 2026-07-19 — the same current, city-specific ICC-style valuation table used for the Residential Building Permit entry in this file; no separate residential/commercial split is published.
Building Permit — valuation $100,001 to $500,000$738.93 for the first $100,000.00 plus $4.03 for each additional $1,000.00, or fraction thereof, to and including $500,000.00Washington City Building Department Master Fee Schedule, 'BUILDING PERMIT FEE TABLE A', fetched 2026-07-19.
Building Permit — valuation over $1,000,000$4,070.93 for the first $1,000,000.00 plus $2.42 for each additional $1,000.00, or fraction thereofWashington City Building Department Master Fee Schedule, fetched 2026-07-19.
Plan Review Fee45% of the total calculated building permit feeWashington City Building Department Master Fee Schedule: 'PLAN REVIEW FEE: The plan review fee shall be equal to 45% of the total calculated building permit fee.'
Commercial valuation rate — Group B Business (Square Foot Construction Costs Table B, 2018 IBC)$127.83/sq ft (Type IA) down to $87.43/sq ft (Type VB)Washington City Building Department Master Fee Schedule, 'SQUARE FOOT CONSTRUCTION COSTS TABLE B — Group 2018 IBC', row 'B Business': IA 127.83, IB 123.20, IIA 119.28, IIB 113.70, IIIA 101.74, IIIB 101.18, IV 109.36, VA 90.86, VB 87.43. This table is labeled '2018 IBC' — stale relative to the current statewide-mandatory 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 7/1/2026); use with the same caution noted for the checklist's code-edition list.
Commercial valuation rate — Group M Mercantile (Square Foot Construction Costs Table B, 2018 IBC)$93.28/sq ft (Type IA) down to $62.65/sq ft (Type VB)Washington City Building Department Master Fee Schedule, Table B, row 'M Mercantile': IA 93.28, IB 89.77, IIA 85.71, IIB 82.26, IIIA 74.39, IIIB 74.08, IV 78.09, VA 64.86, VB 62.65. Footnote (b): 'Unfinished basements (all use groups) = $15. per square foot.'

Sign Permit

Verified

Required in Washington City to paint, mark, post, or otherwise affix a sign to any public or private land or structure, or to physically change/modify an existing sign to add new or additional features, per Washington City Code § 9-18-6 (Chapter 18, Signs). Governed by a dedicated sign chapter of the zoning title rather than folded silently into the building permit. Per § 9-18-6(D), the application is assessed a 'planning review fee' plus a fee under the Building Permit Fee Table; the city's published Planning-Zoning-Economic Development fee schedule (the Master Fee Schedule's 'Maps/Land Use' tab, 'CUP, BOA & MISC.' section) lists that planning review fee by name — 'Sign Permit ... $35.00' — with a separate 'Conditional Use Permit - Signs ... $100.00' line for signs not specifically allowed under Chapter 18 and therefore requiring a conditional use permit per Title 9, Chapter 17.

Verified 2026-07-20 · Source

Requirements

  • Application submitted to the city on the city standard building permit form, per § 9-18-6(C)
  • Associated site plan and building elevation plans showing the locations, dimensions, materials, colors, and copy of all existing and proposed signs, per § 9-18-6(C)
  • Signs not specifically allowed under Chapter 18 require a conditional use permit, processed per the procedures in Title 9, Chapter 17
  • No sign may be located on or project over publicly owned land or inside existing/planned street rights of way identified in the city transportation master plan, per § 9-18-6(A)
  • Certain small, non-advertising signs on private property are exempt from the permit requirement, per § 9-18-15 — e.g., on-premises directional/instructional signs (max 4 sq ft, 4 ft height), no trespassing/no dumping signs (max 16 sq ft for a single sign, or up to 4 signs at 4 sq ft each per lot), and neighborhood identification signs/walls bearing only the neighborhood name and/or address

Required documents

  • RequiredCity Standard Building Permit FormWashington City Code § 9-18-6(C) directs that 'application for a permit to place or construct a sign in any location shall be submitted to the city on the city standard building permit form' — there is no separate, distinct sign-permit application form.
  • RequiredSite Plan and Building Elevation PlansMust show the locations, dimensions, materials, colors, and copy of all existing and proposed signs, per § 9-18-6(C).
  • OptionalConditional Use Permit ApplicationRequired if the proposed sign is not specifically allowed under Chapter 18; processed per the Title 9, Chapter 17 conditional-use procedures.

Fee schedule

Fee typeAmountNotes
Sign Permit (Planning Review Fee)$35.00Washington City's Master Fee Schedule (Google Sheets publication, 'Maps/Land Use' tab — Planning-Zoning-Economic Development section, 'CUP, BOA & MISC.' table), fetched and rendered directly: 'Sign Permit ... $35.00.' This is the 'planning review fee' referenced by City Code § 9-18-6(D) ('All applications for permits filed with the city shall be assessed a planning review fee and a fee in accordance with the duly adopted building permit fee schedule of the city'). Confirmed by rendering the published sheet to an image — a first pass using pdftotext -layout on this same tab mis-jumbled the columns and had misread this line as $300.00; the correct value, verified visually against the source table, is $35.00.
Conditional Use Permit - Signs$100.00Same Master Fee Schedule 'Maps/Land Use' tab, 'CUP, BOA & MISC.' table: 'Conditional Use Permit - Signs ... $100.00 ... $1.50 for each mailing notice.' Applies when the proposed sign is not specifically allowed under Chapter 18 and must instead go through the Title 9, Chapter 17 conditional-use process — in addition to, not instead of, the $35.00 Sign Permit planning review fee.
Building Permit Fee Table (if the sign also requires a building permit)Per the city's duly adopted Building Permit Fee Table (see the residential/commercial building permit entries in this file), plus a 45% plan review feeWashington City Code § 9-18-6(D) additionally assesses 'a fee in accordance with the duly adopted building permit fee schedule of the city' — the same valuation-based Building Permit Fee Table (Table A/B) and 45% Plan Review Fee used elsewhere in this file, on top of the $35.00 Sign Permit planning review fee.

Commercial Tenant Improvement / Tenant Finish Permit

Verified

Required for tenant improvement and tenant finish work in existing commercial buildings in Washington City. The city's own Commercial Plans Submittal Checklist directly addresses tenant improvement scope in its handicap-accessibility section: 'For remodeling and tenant improvements - the area of improvement shall comply with the access requirements for new construction. An accessible route of travel will be required to the remodeled/improved area.' No separate CityInspect permit-type option specific to 'tenant improvement' was found distinct from 'Commercial Addition' — the same Pre-Submittal Process, Commercial Checklist, and fee mechanism used for new commercial construction apply.

Verified 2026-07-19 · Source

Requirements

  • Tenant improvement or remodel work in an existing commercial structure, requiring completion of the Pre-Submittal Process before full plans are submitted (contact the Building Department, (435) 656-6326)
  • The area of improvement must comply with new-construction accessibility requirements, and an accessible route of travel to the remodeled/improved area is required, per the Commercial Plans Submittal Checklist's handicap accessibility section
  • Completed and signed Commercial Checklist — 'permit applications will not be accepted without a Commercial Checklist'
  • Applicable plan set for the scope of work (floor plan, electrical, mechanical, plumbing) reflecting the tenant-finish scope
  • Applications submitted via the CityInspect Builder Account under the closest available permit type (e.g., 'Commercial Addition'), since no distinct 'Tenant Improvement' category was confirmed in the portal

Required documents

  • RequiredWashington City Commercial Plans Submittal ChecklistThe same checklist used for new commercial construction; item 14 (Handicap Accessibility) directly covers remodeling and tenant improvements, requiring compliance with new-construction access requirements for the area of improvement and an accessible route of travel to it.
  • RequiredCommercial Checklist (CityInspect submittal)Completed and signed checklist uploaded with the CityInspect application; required per the Commercial New Build and Additions submittal guide.
  • OptionalFire Review Information FormCompleted form, plus fire sprinkler and fire alarm plans if the tenant-finish scope affects life-safety systems.

Fee schedule

Fee typeAmountNotes
Building Permit — valuation-based (Washington City Fee Table A), inferred mechanismSame tiered schedule as the Commercial Building Permit (Washington City Building Department Master Fee Schedule)Washington City's fee schedule publishes no tenant-improvement-specific valuation rate distinct from new commercial construction; this entry assumes the same Table A fee mechanism applies to TI work, based on declared project valuation, but that has not been independently confirmed against a TI-specific line item.
Plan Review Fee45% of the total calculated building permit feeWashington City Building Department Master Fee Schedule: 'PLAN REVIEW FEE: The plan review fee shall be equal to 45% of the total calculated building permit fee' — not split by permit type.

Fire Sprinkler & Fire Alarm System Plans (Commercial)

Verified

Washington City has no standalone fire sprinkler or fire alarm permit application, fee, or CityInspect permit-type category distinct from the Commercial Building Permit. Fire sprinkler plans, fire alarm system plans, a Fire Review Information Form, and a single-page Fire & Life Safety (F&LS) plan are required attachment items within the Commercial Building Permit's CityInspect submittal (and the Commercial Tenant Improvement Permit's submittal, where life-safety systems are affected), reviewed by the Washington City Fire Department (WCFD) as part of the city's multi-department 'Packet Review' process alongside Building, Planning, Power, and Public Works.

Verified 2026-07-22 · Source

Requirements

  • Two (2) complete sets of fire sprinkler plans submitted for Washington City Fire Department review and approval, per the Commercial Plans Submittal Checklist item 13 — plans must show location and detail for bracing and seismic requirements, riser detail, and electrical information and requirements
  • Fire Review Information Form, completed and submitted with the Commercial Building Permit application; if requesting a deferral of any fire-related item, indicate it on the form
  • Single Page Fire & Life Safety (F&LS) plan uploaded with the CityInspect application, per the Commercial New Build and Additions submittal checklist
  • Fire Alarm System plans uploaded as applicable, per the same CityInspect submittal checklist — listed as its own attachment item distinct from the Fire Sprinklers item
  • Reviewed by Washington City Fire Department (WCFD) concurrently with Building, Planning, Power, and Public Works as part of the Commercial Building Permit's 'Packet Review' process — not a separately issued permit

Required documents

  • RequiredFire Review Information FormCompleted and submitted with the Commercial Building Permit application via CityInspect; indicate any requested deferral directly on the form.
  • OptionalFire Sprinkler PlansTwo (2) complete sets, per Commercial Plans Submittal Checklist item 13 — must show bracing/seismic location and detail, riser detail, and electrical information, for Fire Department review and approval.
  • OptionalFire Alarm System PlansUploaded as its own attachment item in the CityInspect Commercial New Build and Additions submittal, distinct from the Fire Sprinklers upload item.
  • RequiredFire & Life Safety (F&LS) PlanSingle-page plan uploaded with the CityInspect application per the Commercial New Build and Additions submittal checklist.

Fee schedule

Fee typeAmountNotes
Fire Sprinkler / Fire Alarm Plan Review (bundled in Commercial Building Permit)No separate fee published — reviewed by WCFD as part of the Commercial Building Permit's Fee Table A valuation-based fee plus the 45% Plan Review Fee (see Commercial Building Permit entry in this file)Washington City's Commercial Plans Submittal Checklist (washingtonutah.gov/development/building/commercialpermitprocess) and Commercial New Build and Additions submittal page (washingtonutah.gov/development/building/CommercialNewBuildAdditions), both fetched 2026-07-22, list fire sprinkler and fire alarm items as required attachments with no distinct fee line item; the Building Department Master Fee Schedule PDF (both the Building Permit Fee Table A/B tab and the Maps/Land Use planning-fee tab) was checked directly and contains no fire-sprinkler- or fire-alarm-specific fee entry.

Certificate of Occupancy / Change of Use Permit

Verified

Governed by Washington City Code § 9-2-11 (Occupancy Permit). A certificate of occupancy (CO) must be issued by the city official charged with administering and enforcing the zoning title before occupancy of any building 'hereafter erected, enlarged or structurally altered,' before any vacant land (other than for permitted agricultural uses) is occupied or used, and — the change-of-use trigger — 'whenever the character or use of any building or land is proposed to be changed from one use to another use.' Washington City's own site publishes no distinct online application, form, or fee specifically for a pure change-of-use CO (one not accompanying new construction); for new construction and additions, CO issuance is folded into the Commercial/Residential Building Permit's final-inspection process already documented elsewhere in this file.

Verified 2026-07-22 · Source

Requirements

  • A certificate of occupancy is required prior to occupancy of any building hereafter erected, enlarged, or structurally altered, per Washington City Code § 9-2-11(A)
  • A certificate of occupancy is required when vacant land is proposed to be occupied or used, except for permitted agricultural uses, per § 9-2-11(A)
  • A certificate of occupancy is required whenever the character or use of any building or land is proposed to be changed from one use to another use, per § 9-2-11(A) — this is the change-of-use trigger
  • For an existing lawful use (including nonconforming buildings and uses) already in place as of the code's effective date, a certificate of occupancy is issued upon written request from the owner, per § 9-2-11(B)
  • For new construction, additions, or common area buildings, CO release additionally requires final inspection and sign-off from Building, Planning, Fire, Public Works, Power, and Parks Departments and St. George Treatment, plus four uploaded certifications (Soils Compliance, Insulation, Stucco, Termite) — see the Commercial Building Permit entry in this file

Required documents

  • RequiredWritten Request for Certificate of Occupancy (existing use)Per Washington City Code § 9-2-11(B), a property owner may request in writing a certificate of occupancy covering any lawful existing use of a building or premises, including nonconforming buildings and uses. No dedicated online form for this written request was found on washingtonutah.gov — contact the Building Department directly.
  • OptionalBuilding Permit Application (new construction / change accompanied by construction)Where a change of use is accompanied by construction, alteration, or enlargement, a Certificate of Occupancy is issued through the standard Building Permit final-inspection process (see the Residential and Commercial Building Permit entries in this file) rather than a standalone change-of-use application.

Fee schedule

Fee typeAmountNotes
Certificate of Occupancy / Change of UseNo standalone fee foundThe Washington City Building Department Master Fee Schedule was checked directly on both its Building Permit Fee Table A/B tab and its Planning-Zoning-Economic Development 'Maps/Land Use' tab (CUP, BOA & MISC. section) — neither publishes a 'Certificate of Occupancy' or 'Change of Use' line item. Where a change of use accompanies new construction, the CO is released as part of the same valuation-based Building Permit Fee Table process documented in this file's Building Permit entries. For a pure change of use with no construction, no fee was found published anywhere on the city's site — a genuine gap, not an estimate; confirm directly with the Building Department at (435) 656-6326.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Washington City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-04)View current record →All versions →