This is PermitBase’s published record for Riverdale as of 2026-07-19. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Riverdale building permits
VerifiedRiverdale, Utah — as published 2026-07-19.
Verified 2026-07-08 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for new single-family and two-family residential construction and any work regulated by the adopted 2024 IBC / 2021 IRC in Riverdale City (2024 IBC current per Utah Code § 15A-2-103(1)(a) effective 7/1/2026; IRC remains 2021 per § 15A-2-103(1)(b) — Riverdale's own Building Inspections page incorrectly states a 2024 IRC, see codesAdopted note). Applications are submitted through the city's cityinspect.com online portal. Fees are calculated from Riverdale's own valuation-based Building and Sign Permit Fee Schedule, plus a 65% Plan Check Fee and a 1% State of Utah Fee.
Verified 2026-07-08 · Source
Requirements
- New single-family or two-family residential construction
- Any work regulated by the adopted 2021 IRC (statute-current edition; Riverdale's own page incorrectly states 2024 — see codesAdopted note)
- Structural modifications regulated by the adopted 2024 IBC / 2021 IRC
- Submission through the city's online portal (utah.cityinspect.com) with project valuation, site/parcel information, and owner information
- Owner-Builder Affidavit required if the property owner is acting as their own contractor (per Riverdale's official Owner-Builder Form, acknowledging Utah Construction Trades Licensing Act liability)
Required documents
- RequiredBuilding Permit ApplicationRiverdale City's official Building Permit form, capturing job site information (address, subdivision/lot, parcel number, zone, setbacks), owner information, valuation, square footage, occupancy group, construction type, and flood plain status. Submitted via the cityinspect.com online portal.
- RequiredSite PlanSite plan showing lot dimensions, setbacks, and structure placement, referenced on the Building Permit application form (Minimum Setbacks F/S/S/R field).
- OptionalOwner-Builder AffidavitRequired only when the property owner is pulling the permit as their own general contractor rather than using a licensed contractor; the signed form acknowledges $2,000/day liability for violating the Utah Construction Trades Licensing Act.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation-based (Riverdale City Building and Sign Permit Fee Schedule) | $1–$1,100: $48.36. Scales up through published valuation brackets (e.g., $23,001–$25,000: $469.50; $50,000: $773.10; $99,001–$100,000: $1,192.50). $100,000–$500,000: $1,192.50 for the first $100,000 plus $6.75 per additional $1,000 or fraction thereof. $500,001–$1,000,000: $3,880.50 for the first $500,000 plus $5.70 per additional $1,000 or fraction thereof. $1,000,001 and up: $6,730.50 for the first $1,000,000 plus $4.40 per additional $1,000 or fraction thereof. | Riverdale City Building and Sign Permit Fee Schedule (official PDF, Community Development Department). Full valuation table retrieved directly from the city's own fee-schedule document. |
| Plan Check Fee | 65% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'Plan Check Fee: 65% of Permit Fee.' |
| State of Utah Fee | 1% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'State of Utah Fee: 1% of Permit Fee.' This is the statewide Uniform Building Standards Act surcharge collected by all Utah municipalities. |
Commercial Building Permit
VerifiedRequired for new commercial or manufacturing construction in Riverdale. The city's 'Building and Sign Permit Fee Schedule' is a single valuation-based table shared by all building permit types, including commercial — Riverdale does not publish a separate commercial valuation tier or plan-check percentage. New commercial and manufacturing projects additionally require a distinct Planning Commission and City Council Site Plan Review, which is a materially larger and slower process than the building permit fee itself.
Verified 2026-07-19 · Source
Requirements
- New commercial or manufacturing construction, regulated by the adopted 2024 IBC (Utah Code § 15A-2-103(1)(a); the 2021 IRC does not apply to commercial structures)
- Application for Commercial or Manufacturing Site Plan Review — a Preliminary Plat with three full-size (24x36) print sets and one 11x17 print set submitted to the Department of Community Development at least fourteen (14) calendar days prior to the scheduled Planning Commission meeting, per the city's official Final Site Plan Standards Check List
- Both Planning Commission and City Council review and approval of the site plan (each may hold a public hearing), per the official Commercial or Manufacturing Site Plan Review application
- Submission of the building permit itself through the city's online portal (utah.cityinspect.com), once site plan approval is obtained
Required documents
- RequiredApplication for Commercial or Manufacturing Site Plan ReviewOfficial Riverdale Community Development form (Acct #10-34-1500); a fee of $400 per acre (or portion of an acre) is charged at submittal; requires Planning Commission and City Council approval, each potentially with a public hearing.
- RequiredFinal Site Plan Standards Check ListDetailed cover-sheet, plat-sheet, and plan-and-profile-sheet requirements (title blocks, vicinity map, contours, utilities, fire protection access/hydrants, signage, parking, landscaping) that must accompany the Preliminary Plat submittal.
- RequiredBuilding Permit ApplicationSubmitted via the city's cityinspect.com portal (utah.cityinspect.com) after site plan approval.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Commercial or Manufacturing Site Plan Review Fee | $400.00 per acre or portion of an acre | Riverdale City 'Application for Commercial or Manufacturing Site Plan Review' (Community Development Dept, Acct #10-34-1500): 'A fee will be charged at the time the site plan is submitted for review… Show full citationHideRiverdale City 'Application for Commercial or Manufacturing Site Plan Review' (Community Development Dept, Acct #10-34-1500): 'A fee will be charged at the time the site plan is submitted for review — $400 per acre or portion of.' A Planning-stage fee, separate from and in addition to the Building Permit Fee below. |
| Building Permit Fee — valuation-based (Riverdale City Building and Sign Permit Fee Schedule) | $1–$1,100: $48.36. Scales up through published valuation brackets (e.g., $23,001–$25,000: $469.50; $50,000: $773.10; $99,001–$100,000: $1,192.50). $100,000–$500,000: $1,192.50 for the first $100,000 plus $6.75 per additional $1,000 or fraction thereof. $500,001–$1,000,000: $3,880.50 for the first $500,000 plus $5.70 per additional $1,000 or fraction thereof. $1,000,001 and up: $6,730.50 for the first $1,000,000 plus $4.40 per additional $1,000 or fraction thereof. | Riverdale City Building and Sign Permit Fee Schedule (official PDF, Community Development Department) — same table used for the Residential Building Permit; the schedule's title ('Building and Sign Permit Fee Schedule') is generic and not split by residential/commercial. |
| Plan Check Fee | 65% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'Plan Check Fee: 65% of Permit Fee.' |
| State of Utah Fee | 1% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'State of Utah Fee: 1% of Permit Fee.' |
Commercial Tenant Improvement / Tenant Finish Permit
Required for tenant improvement and interior remodel work in an existing, already-approved commercial building in Riverdale. Uses the same shared Building and Sign Permit Fee Schedule as new commercial construction. Riverdale separately publishes an 'Application for Amended Commercial or Manufacturing Site Plan Approval' for changes to a previously approved commercial site plan — the city's public materials do not specify a scope threshold for when interior-only tenant improvements trigger this amendment, so that determination is noted here rather than assumed.
Reviewed 2026-07-19 · Source
Requirements
- Tenant improvement / interior remodel work in an existing commercial building
- Building Permit Application submitted through the city's cityinspect.com portal
- If the tenant improvement alters elements of a previously approved site plan (e.g., footprint, parking, access), an Application for Amended Commercial or Manufacturing Site Plan Approval is required, per Riverdale's Forms & Permits page — the scope threshold for when this applies to interior-only work is not published, so it should be confirmed with Community Development (801-394-5541 ext. 1276) before assuming a straightforward interior tenant improvement is exempt
Required documents
- RequiredBuilding Permit ApplicationSubmitted via the city's cityinspect.com portal.
- OptionalApplication for Amended Commercial or Manufacturing Site Plan ApprovalRequired only if the tenant improvement changes elements of a previously approved site plan; listed on Riverdale's Forms & Permits page. The scope threshold for when this applies to interior-only tenant-improvement work is not published — confirm with Community Development.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation-based (Riverdale City Building and Sign Permit Fee Schedule) | $1–$1,100: $48.36, scaling through published valuation brackets. $100,000–$500,000: $1,192.50 for the first $100,000 plus $6.75 per additional $1,000. $500,001–$1,000,000: $3,880.50 for the first $500,000 plus $5.70 per additional $1,000. $1,000,001 and up: $6,730.50 for the first $1,000,000 plus $4.40 per additional $1,000. | Riverdale City Building and Sign Permit Fee Schedule — same shared table used for new commercial construction and residential permits; Riverdale does not publish a distinct tenant-improvement valuation table or fee tier. |
| Plan Check Fee | 65% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'Plan Check Fee: 65% of Permit Fee.' |
| State of Utah Fee | 1% of the Building Permit Fee | Riverdale City Building and Sign Permit Fee Schedule: 'State of Utah Fee: 1% of Permit Fee.' |
| Amended Commercial or Manufacturing Site Plan Approval Fee | Not found published | Riverdale's Forms & Permits page lists an 'Application for Amended Commercial or Manufacturing Site Plan Approval' as a distinct document, but no dollar amount for this specific amendment fee (as… Show full citationHideRiverdale's Forms & Permits page lists an 'Application for Amended Commercial or Manufacturing Site Plan Approval' as a distinct document, but no dollar amount for this specific amendment fee (as opposed to the $400/acre new Site Plan Review fee) was located as of 2026-07-19. Omitted rather than assumed equal to the new-application fee. |
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.