Kirkland building inspections
Inspection sequence, scheduling, and re-inspection fees for building permits in Kirkland, Washington.
Reviewed 2026-09-16 · Source
How to schedule
Inspections are requested through the building department below.
- Phone
- 425-587-3000
- Website
- Official site
Inspection sequence
Applies to: Building Permit
- 1
Footing and foundation inspection
KMC 21.06.440: made "after poles or piers are set or trenches or basement areas are excavated and all required hold-down anchor bolts, hold-down straps, any forms erected" and other required items are in place.
- 2
Concrete slab and under-floor inspection
KMC 21.06.445: made "after in-slab or under-floor reinforcing steel and building service equipment, conduit, slab insulation, piping accessories and other ancillary equipment" are in place.
- 3
Exterior wall sheathing inspection
KMC 21.06.455: "Exterior wall sheathing shall be inspected after all wall framing is complete, strapping and nailing is properly installed, but prior to being covered."
- 4
Roof sheathing inspection
KMC 21.06.460: "The roof sheathing shall be inspected after all roof framing is complete. No roof coverings shall be installed until inspections are made and approved."
- 5
IMC/UPC/GAS/NEC rough in inspection
KMC 21.06.465: "Rough in mechanical, gas piping, plumbing and electrical shall be inspected when the rough in work is complete and, if required, under test. No connections to primary utilities shall be made until the rough in work" is approved.
- 6
Frame inspection
KMC 21.06.470: made "after the roof deck or sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete" and the rough electrical, plumbing and fire suppression work is in place.
- 7
Flashing and exterior weather barrier inspection
KMC 21.06.475: made "after flashing and weather barrier materials have been installed, but prior to any of the work being covered."
- 8
Energy code inspection
KMC 21.06.490: required IN ADDITION to the inspections required by Chapters 51-11C and 51-11R WAC, and includes verifying footing and/or foundation insulation R-values.
- 9
Final inspection
KMC 21.06.515: "The final inspection shall be made after all work required by the permit(s) is completed."
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kirkland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Kirkland building permits
Get alerts for Kirkland
We'll email you when Kirkland's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.