Sammamish building permits
Sammamish, Washington — as published 2026-09-16.
Reviewed 2026-09-16 · Source
Codes adopted
Permit types & fees
Building Permit
Required for construction in Sammamish. The city adopts the 2021 IBC and IRC as adopted by the State Building Code Council, supplies its own administrative code in place of Chapter 1, and publishes an ordered, binding inspection sequence.
Reviewed 2026-09-16 · Source
Requirements
- Built to the 2021 IBC and 2021 IRC as adopted by the State Building Code Council
- IRC Appendix Q (Tiny Houses) IS adopted; IRC Chapters 1, 11 and 25 through 43 are excluded
- IBC Appendix E (Accessibility), ICC A117.1-2017 and Appendix H (Signs) are included
- Administration is governed by SMC Chapter 16.20, not by model-code Chapter 1
- Plan review is a separate and additional fee, payable when submittal documents are lodged
Required documents
- RequiredSubmittal documents for plan reviewSubmittal documents required by SMC 16.20.250 through 16.20.310 and Chapter 16.05 SMC; a plan review fee is payable when they are lodged.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (set by council fee resolution) | Set by council fee resolution; see notes | SAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. Show full citationHideSAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. SMC 16.20.340 directs the reader to "the fee schedule as established in the City of Sammamish fee resolution", which is a separate council instrument not read for this entry. WHAT THE CODE DOES FIX IS A FLOOR, AND IT IS AN UNUSUAL ONE: "In no case shall the building permit fee be less than the City's hourly inspection fee multiplied by the number of inspections expected to be performed for work authorized by the permit." The minimum is therefore tied to an expected inspection COUNT, not to a dollar amount - which matters here because the city publishes twelve required inspection stages. Plan review is a SEPARATE and ADDITIONAL fee (SMC 16.20.345), payable when submittal documents are lodged; the permit centre may take a deposit in lieu where the full amount is not yet known, applied against the total. Incomplete or changed submittals, and deferred submittal items, draw a further plan review fee. A reinspection fee may be assessed where work is not complete or previous corrections were not made (SMC 16.20.450). |
Residential Building Permit
Residential work in Sammamish follows the 2021 IRC with city design criteria, and Appendix Q (Tiny Houses) is adopted.
Reviewed 2026-09-16 · Source
Requirements
- Built to the 2021 IRC as adopted by the State Building Code Council in Chapter 51-51 WAC
- Appendix Q, Tiny Houses, is adopted
- Design criteria in SMC 16.05.080 amend IRC Table R301.2(1)
- Ground and roof snow load 25 PSF, with a 5 psf rain-on-snow surcharge below 5 degrees
Required documents
- RequiredSubmittal documents for plan reviewSubmittal documents required by SMC 16.20.250 through 16.20.310 and Chapter 16.05 SMC; a plan review fee is payable when they are lodged.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (set by council fee resolution) | Set by council fee resolution; see notes | SAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. Show full citationHideSAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. SMC 16.20.340 directs the reader to "the fee schedule as established in the City of Sammamish fee resolution", which is a separate council instrument not read for this entry. WHAT THE CODE DOES FIX IS A FLOOR, AND IT IS AN UNUSUAL ONE: "In no case shall the building permit fee be less than the City's hourly inspection fee multiplied by the number of inspections expected to be performed for work authorized by the permit." The minimum is therefore tied to an expected inspection COUNT, not to a dollar amount - which matters here because the city publishes twelve required inspection stages. Plan review is a SEPARATE and ADDITIONAL fee (SMC 16.20.345), payable when submittal documents are lodged; the permit centre may take a deposit in lieu where the full amount is not yet known, applied against the total. Incomplete or changed submittals, and deferred submittal items, draw a further plan review fee. A reinspection fee may be assessed where work is not complete or previous corrections were not made (SMC 16.20.450). |
Verify a Contractor Licence
Washington contractors register with the Department of Labor & Industries. Registration is a STATE record; Sammamish does not issue it.
Reviewed 2026-09-16 · Source
Requirements
- Check contractor registration with Washington State Labor & Industries
Required documents
- OptionalNo city document requiredNo city document - check the state register.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building permit fee (set by council fee resolution) | Set by council fee resolution; see notes | SAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. Show full citationHideSAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. SMC 16.20.340 directs the reader to "the fee schedule as established in the City of Sammamish fee resolution", which is a separate council instrument not read for this entry. WHAT THE CODE DOES FIX IS A FLOOR, AND IT IS AN UNUSUAL ONE: "In no case shall the building permit fee be less than the City's hourly inspection fee multiplied by the number of inspections expected to be performed for work authorized by the permit." The minimum is therefore tied to an expected inspection COUNT, not to a dollar amount - which matters here because the city publishes twelve required inspection stages. Plan review is a SEPARATE and ADDITIONAL fee (SMC 16.20.345), payable when submittal documents are lodged; the permit centre may take a deposit in lieu where the full amount is not yet known, applied against the total. Incomplete or changed submittals, and deferred submittal items, draw a further plan review fee. A reinspection fee may be assessed where work is not complete or previous corrections were not made (SMC 16.20.450). |
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sammamish building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.