This is PermitBase’s published record for Page as of 2026-08-01. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Page building permits
VerifiedPage, Arizona — as published 2026-08-01.
Verified 2026-07-06 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for new single-family and two-family dwelling construction in the City of Page. Reviewed against the 2018 IRC as adopted by the City. Applications are submitted via the City of Page Building Permit Application (paper) or the online iWorQ portal, and single-family dwellings are reviewed directly by the Chief Building Official rather than going through the commercial Site Plan Review Committee process.
Verified 2026-07-06 · Source
Requirements
- Building permit required for new single-family and two-family dwelling construction within Page city limits
- Plans must comply with the 2018 IRC as adopted by the City of Page and local design criteria (115 MPH wind, Exposure C; Seismic Zone 2, Site Class D or per geotechnical report; 18-inch frost depth; 20 PSF snow load, no reduction)
- Site/plot plan required showing property dimensions, distances between existing/proposed structures, distance from building to property lines, utility hook-up locations, street identification, and north arrow
- House plans required: foundation plan with details, electrical plans with service panel location/size, fully dimensioned floor plan, equipment locations, floor framing (all levels), roof framing, elevation drawings, cross-sections, deck framing details, and livable square footage
- Two sets of truss calculations from the manufacturer required
- Two stamped sets of engineering specifications by an Arizona-registered engineer required where applicable
- A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department
- Owner/Builder permits are allowed for residential projects only; any hired contractor must be licensed per A.R.S. § 32-1169
- Wood sill-plates on concrete must be pressure-treated or foundation-grade redwood; footing reinforcing steel cannot be tied to metal grade stakes due to corrosive soil
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form listing property/owner info, contractor/subcontractor licensing, valuation, and required approvals (Fire Dept, Zoning, Public Works, Utilities, PUE, County Health)
- RequiredSite/Plot PlanProperty dimensions, structure setbacks, utility hook-up locations, street ID and north arrow
- RequiredHouse Plans (Foundation, Electrical, Floor, Framing, Elevations)Fully dimensioned construction drawings per Building Safety Department residential plan review requirements
- RequiredTruss Calculations (2 sets)Manufacturer-prepared truss calculation sets
- OptionalEngineering Specifications (2 stamped sets)Arizona-registered engineer stamped specifications, where required by scope
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500); $23.50 + $3.05 per additional $100 (or fraction) to $2,000; $69.25 + $14.00 per additional $1,000 (or fraction) to $25,000; $391.25 + $10.10 per additional $1,000 to $50,000; $643.75 + $7.00 per additional $1,000 to $100,000; $993.75 + $5.60 per additional $1,000 to $500,000; $3,233.75 + $4.75 per additional $1,000 to $1,000,000; $5,608.75 + $3.65 per additional $1,000 above $1,000,000 | City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department — Table 1-A, Building Permit Fees, p.4 |
| Plan Review Fee | 65% of the calculated Building Permit Fee | City of Page Consolidated Fee Schedule, p.5 note: 'Plan Review Fees: When submittal documents are required, a plan review fee shall be paid at the time of submitting documents for plan review. Said plan review shall be 65 percent of the building permit fee.' |
| Additional Plan Review (changes/additions/revisions to plans) | $47.00 per hour | City of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees item 4 |
| Re-inspection Fee | $47.00 per hour (minimum charge one-half hour for inspections with no specifically indicated fee; $54.00 per hour cited for other inspections/fees under item 6) | City of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees items 2, 3, and 6 |
| Inspection Outside Normal Business Hours | $47.00 per hour, 2-hour minimum charge | City of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees item 1 |
Residential Addition / Remodel Permit
VerifiedRequired for room additions, remodels, and alterations to existing one- and two-family dwellings in Page. Reviewed against the 2018 IRC as adopted by the City, billed on the same Table 1-A valuation basis as new construction.
Verified 2026-07-06 · Source
Requirements
- Building permit required for room additions, remodels, and alterations affecting structural or life-safety elements
- Detached accessory structures for storage that are one-story and under 120 sq ft do not require a permit, but zoning setback rules may still apply
- Interior finish work alone (painting, papering, tiling, carpeting, cabinets, countertops) is exempt from a permit
- Plans must comply with City of Page local design criteria (115 MPH wind, Exposure C; Seismic Zone 2; 18-inch frost depth; 20 PSF snow load)
- Site/plot plan showing existing structure, addition footprint, and setbacks required
- Owner/Builder permits allowed for residential projects only; hired contractors must be licensed per A.R.S. § 32-1169
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form
- RequiredSite/Plot PlanShowing existing structure, addition footprint, and setbacks
- RequiredConstruction DrawingsFoundation, framing, electrical, and elevation drawings for the addition/remodel scope
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 (same Table 1-A schedule as new construction) | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4 |
| Plan Review Fee | 65% of the calculated Building Permit Fee | City of Page Consolidated Fee Schedule, p.5 |
Electrical Permit
VerifiedRequired for electrical installation, alteration, or repair work in Page, governed by the 2017 National Electrical Code (NEC) as adopted by the City. Uses a dedicated fee formula separate from the general Table 1-A valuation schedule.
Verified 2026-07-06 · Source
Requirements
- Electrical permit required for electrical installation, alteration, or repair work
- Governed by the 2017 NEC (Chapters 1-9, Annexes A-E) as adopted by the City of Page
- Electrical contractor information (name, address, contact, phone, license #) required on the Building Permit Application
- Apply via paper Building Permit Application or the online iWorQ Building Permit Application Portal
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form listing contractor licensing information for the electrical subcontractor
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee — Based on Valuation of Construction Costs | $27.00 for the first $500.00 of valuation; plus $3.75 for each additional $1,000.00 of valuation of construction costs | City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department — Table 1-A page, item 5, p.4 |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Plumbing Permit
VerifiedRequired for plumbing installation, alteration, or repair work in Page, governed by the 2018 International Plumbing Code (IPC) as adopted by the City, including local backwater-valve and grease-interceptor amendments.
Verified 2026-07-06 · Source
Requirements
- Plumbing permit required for installation, alteration, or repair of plumbing systems and fixtures
- Governed by the 2018 IPC (Chapters 1-15, with Appendix E) as adopted by the City of Page
- Backwater valves required on all sewer lines per City Code Section 11-4-1(B); grease interceptors required per City Code Section 11-5-2
- A building permit (including plumbing scope) may not be issued prior to receiving verbal approval from Coconino County Health Department where onsite wastewater is involved
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form listing plumbing subcontractor licensing information
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No separately itemized plumbing-only fee line was found; plumbing work is billed on the same general valuation schedule as other Building Department permits. |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Mechanical / HVAC Permit
VerifiedRequired for heating, ventilation, and air conditioning installations in Page, governed by the 2018 International Mechanical Code (IMC) as adopted by the City.
Verified 2026-07-06 · Source
Requirements
- Mechanical permit required for installation, replacement, or relocation of HVAC equipment, furnaces, and ventilation systems
- Governed by the 2018 IMC (Chapters 1-15, with Appendix Chapters A and B) as adopted by the City of Page
- 2018 International Fuel Gas Code (Chapters 1-8, Appendix A, B, C) governs associated gas-fired equipment and piping
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form listing mechanical subcontractor licensing information
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. Show full citationHideCity of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No separately itemized mechanical/HVAC-only fee line (e.g., a flat AC-replacement fee) was found; mechanical work is billed on the same general valuation schedule as other Building Department permits. |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Re-Roofing Permit
VerifiedRequired for residential and commercial re-roofing in Page. Governed by the 2018 IBC/IRC roofing provisions, with roof drain sizing based on the City's local 3-inch-per-hour rainfall design criterion for flat roofs.
Verified 2026-07-06 · Source
Requirements
- Building permit required for re-roofing (no published permit-exempt re-roofing scope was found on the City's Building Safety Department page, unlike the exemptions published for accessory structures, fences, and interior finish work)
- Roof drain sizing for flat roofs must be calculated using the City's local 3 inch per hour rainfall design criterion
- Plans/material listing showing existing framing, proposed material, and drainage slope required for plan review where applicable
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form
- RequiredRoof Plan / Material ListingExisting framing, proposed roofing material, and drainage slope calculations (3 in/hr rainfall design for flat roofs)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No separately itemized re-roofing-only fee line was found; re-roofing is billed on the general valuation schedule. |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Residential Solar Photovoltaic (PV) Permit
VerifiedRequired for installation of rooftop residential solar photovoltaic systems in Page. No dedicated streamlined PV procedure or PV-specific fee schedule was found published by the City; systems are subject to the state-law baseline (A.R.S. § 9-468) and the City's standard Building/Electrical Permit process under the 2018 IBC/IRC and 2017 NEC.
Verified 2026-07-06 · Source
Requirements
- Residential PV systems must meet the minimum standards set by Arizona Revised Statutes § 9-468 (Solar construction permits; standards; definition), which all Arizona municipalities must follow at minimum for residential solar permit review
- Construction plans showing PV system location, roof plan and elevation views, panel mounting/racking details, and a one-line or three-line electrical diagram are required per the state-law baseline
- Electrical work must comply with the 2017 NEC as adopted by the City of Page
- No City of Page-specific streamlined review procedure, dedicated PV checklist, or PV-specific fee schedule (comparable to some other Arizona cities' dedicated residential PV procedures) was found published on the City's Building and Safety Department page or in the Consolidated Fee Schedule as of July 2026
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form, submitted with construction/electrical plans for the PV system
- RequiredPV Construction Plans (roof plan, elevation, racking/mounting details, electrical diagram)Minimum plan content required under A.R.S. § 9-468 for residential solar permit review
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) and/or Electrical Permit Fee (valuation-based) | Building Permit Fee per Table 1-A ($23.50 for valuation $1-$500 up through $5,608.75 + $3.65 per additional $1,000 above $1,000,000) and/or Electrical Permit Fee ($27.00 for the first $500 + $3.75 per additional $1,000 of valuation) | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. Show full citationHideCity of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No dedicated 'Photovoltaic System' fee line was found in the published fee schedule; a residential PV system is billed under the general Building Permit Fee and/or the Electrical Permit Fee formula depending on how the City classifies the work at intake. |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Demolition Permit
VerifiedRequired for demolition of any residential or commercial structure in the City of Page, processed through the standard Building Permit Application. No demolition-specific published fee line was found; demolition is billed on the same Table 1-A valuation basis as other Building Department permits.
Verified 2026-07-06 · Source
Requirements
- Building permit required before demolishing a residential or commercial structure within Page city limits (application 'Class of Work' includes a 'Remove' option on the standard Building Permit Application)
- Property owner and general contractor information required on the Building Permit Application
- Coordination with utility providers (Water/Sewer: 928-645-4214; Electrical/PEU: 928-645-2419; Propane/SemStream: 928-645-2391) for service termination is expected as part of standard demolition practice, though no City of Page-published demolition-specific checklist was found
- Call Arizona Blue Stake (1-800-STAKE-IT / 811) before any excavation, per the notice printed on the City of Page Building Permit Application
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form; select 'Remove' under Class of Work
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 | City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No separately itemized demolition-only fee line was found; demolition is billed on the general valuation schedule based on the value/scope of the demolition work. |
EV Charger / EVSE Permit
VerifiedThe City of Page does not publish a dedicated EV charger/EVSE permit. Installation of a Level 2 EV charging circuit is permitted as electrical work under the City's standard Electrical Permit, governed by the 2017 National Electrical Code as adopted by the City. The City's Consolidated Fee Schedule (Resolution 1296-23) uses a dedicated valuation-based formula for all electrical permits — there is no separate EV-specific line item.
Verified 2026-07-20 · Source
Requirements
- Electrical permit required for the EV charging circuit installation, alteration, or repair work
- Governed by the 2017 NEC (Chapters 1-9, Annexes A-E) as adopted by the City of Page
- Electrical contractor information (name, address, contact, phone, license #) required on the Building Permit Application
- Apply via paper Building Permit Application or the online iWorQ Building Permit Application Portal
Required documents
- RequiredCity of Page Building Permit ApplicationOfficial application form listing contractor licensing information for the electrical subcontractor
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee — Based on Valuation of Construction Costs | $27.00 for the first $500.00 of valuation; plus $3.75 for each additional $1,000.00 of valuation of construction costs | City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department Table 1-A page, item 5, p.4 — the same formula applied to EV charger circuit installation; no separate EV-specific line item exists |
| Plan Review Fee (where plan review is required) | 65% of the calculated permit fee | City of Page Consolidated Fee Schedule, p.5 |
Commercial Building Permit
VerifiedRequired for new commercial building construction and for exterior remodeling/expansion of commercial uses in the City of Page, reviewed against the 2018 IBC and City amendments. Unlike residential construction, most commercial development must first pass Site Plan Review Committee (SPRC) approval — required by Zoning Code § 152.095(B) before any building permit can even be submitted — before the same generic City of Page Building Permit Application and Table 1-A valuation fee schedule used for every other permit type in this record is used to pull the actual building permit. Tenant improvement (interior remodeling of an existing commercial building) is not a separate permit type or fee schedule: it uses the identical Building Permit Application and Table 1-A fees as new commercial construction, and Zoning Code § 152.095(A)(1)(b) explicitly exempts 'interior remodeling only of commercial and multi-family structures' from the SPRC gate entirely (as does an exterior addition/modification under 500 sq ft or 10% of gross floor area, whichever is less, per § 152.095(A)(1)(c)).
Verified 2026-08-01 · Source
Requirements
- Building permit required for all new commercial building construction and for exterior remodeling/expansion of commercial uses, reviewed against the 2018 IBC (Chapters 1-35, with City of Page amendments) and ICC A117.1 (2009) accessibility standards as adopted by the City of Page
- 'Commercial development' is defined by Zoning Code § 152.095(B) as 'any residential development larger than a single-family detached residence on a single lot, and any commercial or industrial building or development'
- Per § 152.095(A)(1) and (B): commercial developments (new construction, major subdivisions, and exterior remodeling/expansion of commercial uses) require Site Plan Review Committee (SPRC) review and approval before any building permit can be submitted for review. Exempt from SPRC (but not from the underlying building permit): interior remodeling only of commercial structures (§ 152.095(A)(1)(b)); exterior modifications/additions that do not increase gross floor area by more than 500 sq ft or 10%, whichever is less (§ 152.095(A)(1)(c))
- Complete SPRC site plan package required per § 152.095(B)(1)-(2): a completed City of Page application for construction plan submittal; one electronic PDF of the complete site plan; two bound sets on 24"x36" white-background paper; supporting documentation/studies/reports; and, if the development requires fire sprinklers or fire protection, a third complete paper set for the Fire Marshal's review and approval. Partial or incomplete submittals, or submittals split across entities, are rejected and returned to the applicant at their expense
- SPRC review covers: compliance with the Zoning Code, Maricopa Association of Governments (MAG SPEC) design standards, ADA specifications, and the adopted IBC (SPRC as a whole); street plans, drainage, and floodplain (Public Works Director); water/sewer and electric utilities (Page Utility Enterprises); easement work (Western Area Power Authority); rights-of-way/intersection design where the site abuts a state highway (ADOT); and Fire, Police, and Ambulance Departments as appropriate
- Per § 152.095(B)(3), city staff schedule a formal SPRC meeting to be held within 14 days of determining the site plan application complete, held on the closest Thursday or another day the SPRC deems appropriate; the applicant or their civil engineer must attend in person or via videoconference to answer committee questions
- Once SPRC (and the Fire Marshal and any other required outside agency) approve the site plan, the applicant works with the City's Chief Building Official (CBO) to pull the building permit(s) required for construction, submitted on the same generic City of Page Building Permit Application used for every other permit type in this record, with 'NEW' (or 'ADDITION'/'ALTERATION' for remodel/TI scope) selected under Class of Work
- Per § 152.095(D): a site plan approval becomes void if a building permit has not been issued within one year of approval; a one-time three-month extension may be granted by the Director if requested before the one-year deadline, and additional extensions require Planning and Zoning Commission approval
- Per § 152.095(G): the CBO may issue a Temporary Certificate of Occupancy (30, 60, or 90 days, at the CBO's discretion) or a final Certificate of Occupancy; no occupancy of any structure is allowed until all required improvements are complete and CBO-approved
- Automatic fire sprinkler systems are required in any building (commercial included) exceeding 4,000 sq ft, per City Ordinances 548-09, 566-10, and 666-19 (City Code Chapter 92) — a threshold many hotel/hospitality and larger retail projects in Page will exceed
- Hotel/Motel-specific zoning standards apply during site plan/SPRC review (Zoning Code Table 4.2 series): off-street parking is calculated as 1 space per guest room, plus 1 space per 4 persons of the banquet room's maximum capacity (if a banquet room is present), plus 2 spaces per 3 employees, plus 1 RV/boat/bus space per 6 guest rooms (3-space minimum); hotel/motel parking stalls are allowed a reduced 9-foot width; and 4 passenger loading/unloading spaces are required for a Hotel or Motel use (Table 4.2-4). 'HOTEL or MOTEL' is defined in the Zoning Code as 'a facility with continuous on-site management with nine or more sleeping rooms that are intended to be occupied by guests for a fee'
- Owner/Builder permits are allowed for residential projects only (per this file's localAmendments); commercial project work must be performed by licensed contractors per A.R.S. § 32-1169
Required documents
- RequiredCity of Page Building Permit ApplicationSame generic application form used for every permit type in this record; select 'NEW', 'ADDITION', or 'ALTERATION' under Class of Work as applicable to the commercial scope
- OptionalCity of Page Application for Construction Plan Submittal (SPRC Site Plan Package)Required only where SPRC review applies (new commercial construction or exterior remodel/expansion exceeding the 500 sq ft / 10% GFA exemption threshold) — one electronic PDF plus two bound 24"x36" sets of the complete site plan, per § 152.095(B)(1)
- RequiredSite PlanMust show, at minimum, all buildings/structures/utilities, rights-of-way/easements/open space, sidewalks and travel ways, parking/driveways/loading areas, ADA parking and routes, landscaping, drainage/retention, signage, property boundaries, and topographic/geologic issues, per § 152.095(B)(2)
- RequiredConstruction / Building PlansFull construction drawing set meeting the most current adopted IBC, IRC, Fire, Electrical, and Plumbing Codes, MAG SPECS, and City Zoning/Subdivision Codes, per § 152.095(F)(2)
- OptionalFire Marshal Plan Set (3rd paper set)Required only if the development requires fire sprinklers or fire protection, per § 152.095(B)(1)(e) and (F)(1)(e)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Commercial Building Permit Fee — Table 1-A (Total Valuation) | $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000 — identical schedule to residential | City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department — Table 1-A, p.4. Show full citationHideCity of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department — Table 1-A, p.4. No separate commercial-only valuation chart was found; commercial building permits (new construction and tenant improvement/remodel alike) are billed on the same Table 1-A schedule used for every other permit type in this record. |
| Plan Review Fee | 65% of the calculated Building Permit Fee | City of Page Consolidated Fee Schedule, p.5 note: 'Plan Review Fees: When submittal documents are required, a plan review fee shall be paid at the time of submitting documents for plan review. Said plan review shall be 65 percent of the building permit fee.' |
| Site Plan Review Fee (Commercial/Subdivision Plat/Conditional Use Permit) | $500.00 | City of Page Consolidated Fee Schedule (Resolution 1296-23), Planning & Zoning Code Fees, p.8. Show full citationHideCity of Page Consolidated Fee Schedule (Resolution 1296-23), Planning & Zoning Code Fees, p.8. This is a distinct, commercial-specific fee not charged on residential (single-family) permits — it funds the SPRC review required by Zoning Code § 152.095(B) before a commercial building permit can be submitted; not charged for SPRC-exempt interior tenant-improvement-only work |
| Site Plan Revision Fee (Subsequent Site Plan Reviews Required) | $250.00 | City of Page Consolidated Fee Schedule, Planning & Zoning Code Fees, p.8 |
| Commercial Application Fee — Conditional Use Permit (CUP) | $300.00 | City of Page Consolidated Fee Schedule, Planning & Zoning Code Fees, p.8. Applicable only where the proposed commercial use requires a Conditional Use Permit in the applicable zoning district (not every commercial use or zone requires a CUP) |
| Additional Plan Review / Re-inspection / After-Hours Inspection Fees | $47.00 per hour (2-hour minimum for after-hours inspections; one-half hour minimum for re-inspections with no specifically indicated fee) | City of Page Consolidated Fee Schedule, Building Department — Table 1-A, p.4, Other Inspections and Fees items 1-4 — same schedule applied to every permit type in this record |
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.