Safford building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Safford, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
808 S. 8th Avenue, PO Box 272, Safford, AZ 85546
Phone
928-432-4140
Office hours
Monday - Thursday, 7:00 a.m. - 6:00 p.m.; closed Fridays (City Hall 4/10 schedule). Building Permit Applications (Residential or Commercial) are submitted in person or by mail to the Planning & Community Development Department; a complete set of adopted building code books is available to view in the Building Inspector's office by appointment (call 928-432-4140 to schedule).

Published scheduling rules

  • Inspection requests must be received at least 24 hours in advance; Friday inspections must be requested before 12:00 p.m. the preceding Thursday and occur before 12:00 p.m. Friday, consistent with City Hall's Monday-Thursday 7 a.m.-6 p.m. schedule (closed Fridays). (Residential Building Permit (New Construction))

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Made after excavation for footings is complete and any required reinforcing steel is in place; for concrete foundations, forms must be in place prior to inspection

  2. 2

    Concrete Slab or Under-Floor

    Made after all in-slab or under-floor building service equipment, conduit, piping, and ancillary items are in place, but before concrete is placed or floor sheathing/subfloor is installed

  3. 3

    Frame

    Made after the roof, all framing, fire blocking, and bracing are in place, and rough electrical, plumbing, and heating wires/pipes/ducts are complete and approved

  4. 4

    Lath or Gypsum Board

    Made after all lathing and gypsum board (interior and exterior) is in place, but before plastering or before gypsum board joints and fasteners are taped and finished

  5. 5

    Final

    Made after grading and the building is completed and ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation

    Required before concrete pour for additions with new footings

  2. 2

    Frame

    Structural connections to existing structure, fire blocking, and rough electrical/plumbing/mechanical

  3. 3

    Lath or Gypsum Board

    After lathing/gypsum board is in place, before plaster or taping/finishing of joints and fasteners

  4. 4

    Final

    Completed work verified against approved plans and ready for occupancy

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts; part of the combined 'Concrete Slab or Under-Floor' inspection

  2. 2

    Rough-In

    After pipes are installed, before walls are closed; part of the combined 'Frame' inspection

  3. 3

    Final

    Fixtures connected, water heater and gas connections verified, no leaks

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed; part of the combined 'Frame' inspection for new construction

  2. 2

    Final

    Devices installed, panel labeled, GFCI/AFCI protections verified per the 2014 NEC and City's common electrical code requirements

Applies to: Manufactured / Mobile Home Placement Permit

  1. 1

    Foundation/Tie-Down

    Verifies foundation, blocking, and tie-down/anchoring system before utility connection

  2. 2

    Final

    Utility connections, skirting, and site conditions verified for occupancy

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and equipment placement before walls are closed

  2. 2

    Final

    Equipment operational, clearances and combustion air verified

Applies to: Solar PV Permit

  1. 1

    Frame/Rough-In

    Structural mounting and rough electrical wiring/box placement verified before covering or energizing

  2. 2

    Final

    Completed installation verified against approved plans and the City's common electrical code requirements (GFCI protection, panel labeling) per the 2014 NEC

Safford building permits

Get alerts for Safford

We'll email you when Safford's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.