Residential Building Permit (New Construction)
VerifiedRequired for new single-family and two-family dwelling construction in the City of Eloy. Reviewed against the 2018 IRC, 2018 IBC (non-residential portions), and 2018 IECC as adopted and amended by the City under Chapter 5 of the Eloy City Code (Ordinance No. 20-900, effective December 14, 2020). Applications are submitted electronically through the City's iworq permit portal.
Verified 2026-08-21 · Source
Requirements
- Building permit required for new single-family and two-family dwelling construction within Eloy city limits
- Plans must comply with the 2018 IRC/IBC/IECC and City of Eloy amendments, including Climatic and Geographic Design Criteria (115 mph wind; Seismic Design Category B; 34°F winter design temperature; heavy termite potential; 12-inch minimum foundation/footing depth; 0-inch frost line depth)
- Construction documents (cover sheet, site plan, foundation plan, floor plan, framing plans, elevations, sections, mechanical/electrical/plumbing plans, structural calculations) must be sealed by an Arizona-registered engineer or architect where required and submitted as flattened PDFs (50 MB max per file)
- Water Availability Letter required from Public Works prior to submittal; Right-of-Way/On-Site Civil Permit required separately if within 400 feet of a public water/wastewater line
- Pinal County Dust Control Permit required for earthmoving activity disturbing more than approximately 1,690 sq ft (City of Eloy is in the West Pinal Nonattainment Area)
- Copy of approved Eloy Fire District Permit required as part of the submittal
- 16 SEER minimum air conditioning efficiency and 78%/80% AFUE minimum gas heating efficiency (weatherized/non-weatherized) required per City-amended IECC criteria
- Solar-ready zone (minimum 300 sq ft / 10% of roof area) and electrical panel reserved space for future solar required on new construction
Required documents
- RequiredCity of Eloy Building Permit ApplicationSubmitted through the City's iworq electronic permit portal (eloypermits.portal.iworq.net); paper form also available (rev. 07/14/2025)
- Required2018 International Residential Code Minimum Submittal Checklist (One- and Two-Unit Residential Plans)City of Eloy checklist (rev. 01/22/2025-01/27/2025) detailing required design criteria, site plan, foundation/floor/framing plans, elevations, structural calculations, mechanical/electrical/plumbing plans, energy compliance (RES-check), and required plan notes
- OptionalProperty Owner AuthorizationRequired when the property owner is represented by an agent (lawyer, architect, contractor, engineer, etc.)
- RequiredWater Availability LetterObtained from Public Works (520-466-3082) prior to or with submittal
- RequiredSoils ReportRequired for a single-family custom home (non-Standard-Plan) submittal, or a signed owner soil waiver
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Residential Minimum ($1-$500 valuation) | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Residential and Commercial Permit Fees Based on Total Valuation of Improvements table |
| Building Permit Fee — $500.01 to $2,000 | $70.00 for the first $500.00 plus $4.50 for each additional $100.00 or fraction thereof, to and including $2,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $2,000.01 to $40,000 | $137.50 for the first $2,000.00 plus $15.00 for each additional $1,000.00 or fraction thereof, to and including $40,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $40,000.01 to $100,000 | $707.50 for the first $40,000.00 plus $12.00 for each additional $1,000.00 or fraction thereof, to and including $100,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $100,000.01 to $500,000 | $1,427.50 for the first $100,000.00 plus $8.00 for each additional $1,000.00 or fraction thereof, to and including $500,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $500,000.01 to $1,000,000 | $4,627.50 for the first $500,000.00 plus $6.60 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — over $1,000,000 | $7,927.50 for the first $1,000,000.00 plus $5.25 for each additional $1,000.00 to $5,000,000.00; $28,927.50 for the first $5,000,000.00 plus $5.00 per additional $1,000.00 to $10,000,000.00; $54,427.50 for the first $10,000,000.00 plus $4.50 per additional $1,000.00 above that | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Residential Standard Plan Review (Standard Plans valid only while the City uses the same building code under which the plan was approved) | $1,400.00 plus the Building Permit Plan Review Fee | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Plan Review Fee (general) | 65% of the calculated Building Permit Fee | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule, Basic Plan Review Services section |
| Certificate of Occupancy — R-3 single-family | $35.00 per building | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
Residential Addition / Remodel Permit
VerifiedRequired for room additions, remodels, and alterations to existing one- and two-family dwellings in Eloy. Reviewed against the 2018 IRC as adopted and amended by the City, using the dedicated Residential Addition or Remodel Minimum Submittal Checklist.
Verified 2026-08-21 · Source
Requirements
- Building permit required for room additions, remodels, and alterations to existing single- and two-family residences
- Detached accessory structures 200 sq ft or less with no electrical, plumbing, or mechanical connections do not require a building permit, but Planning and Zoning approval of location is still required
- Cover sheet, site plan, and construction plans (floor plan, foundation plan, framing/deck plan, cross-section, elevations, energy code compliance, electrical/mechanical/plumbing plans as applicable) required per the Residential Addition or Remodel checklist
- Structural plan and calculations, truss calculations/layout, soils report, ResCheck, and Manual J/S/D load calculations required based on project scope
- Demolition plans required separately from new-construction plans when the scope includes demolition; existing, new, and remodeled areas must be clearly identified on the plans
Required documents
- RequiredCity of Eloy Building Permit ApplicationSubmitted through the iworq electronic permit portal
- RequiredResidential Addition or Remodel Building Permit ChecklistCity of Eloy checklist (rev. 05/25/2026) detailing cover sheet, site plan, construction plans, and supporting-document requirements for additions and remodels
- RequiredSite PlanParcel lot lines/address, setbacks, existing structures/fences/retaining walls, existing utilities/easements, location/size of proposed structure, flood table
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (Addition/Remodel, Based on Valuation) | Per the Residential and Commercial Permit Fees valuation table (Residential Minimum $70.00 for $1-$500; scaling tiers as published) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — same valuation table as new construction, per the value of the addition/remodel work or a signed contract, whichever is less. Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — same valuation table as new construction, per the value of the addition/remodel work or a signed contract, whichever is less. The FY 2025-2026 schedule's provision billing existing-R-3 interior alterations, detached garages/carports/sheds, patio covers and gazebos at a Table 1-A valuation fee with a plan review fee capped at $35.00 was not carried into the FY 2026-2027 schedule; habitable room additions remain billed on the full valuation table |
| Residential covered patios, gazebos, and carports (R-3), flat permit fee — over 200 sq ft up to 500 sq ft / over 500 sq ft | $140.00 (over 200 to 500 sq ft); $280.00 (over 500 sq ft) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section — new flat fees introduced in FY 2026-2027; the former $35.00-capped plan review provision for minor existing-R-3 work was removed from the schedule |
| Site/plot plan review (or revision) for a residential lot using a standard plan | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Minor Revisions of Plans after Permit Issuance — Residential (1-hour minimum) | $175.00 for the first hour, plus $140.00 for each additional hour, per review cycle | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
Electrical Permit
VerifiedRequired for electrical installation, alteration, or repair work in Eloy, governed by the 2017 National Electrical Code (NEC) as adopted by the City. Billed per a detailed unit/system fee schedule covering fixtures, services, and appliance circuits, in addition to a flat permit-issuance fee.
Verified 2026-08-21 · Source
Requirements
- Electrical permit required for repair/replacement, added circuits/outlets, new service entrances/upgrades, and new electric meters
- Governed by the 2017 NEC as adopted by the City of Eloy
- Correct ROC (Registrar of Contractors) license class must be listed for the specific electrical work being performed
- Electrical schematic/floor plan required showing circuit locations, GFCI/AFCI requirements, and appliance requirements for specialized equipment (spas, pumps, etc.)
- Load calculations required for EV chargers, hot tubs, HVAC equipment, workshop equipment, and subpanels
- One-line diagram required for service entrance sections (SES) and subpanels on new service/upgrade work; electrical services over 400 amps require an Arizona-engineer-sealed plan review
Required documents
- RequiredCity of Eloy Building Permit Application (Electrical)Submitted through the iworq electronic permit portal
- RequiredMinimal Electrical Only Permit ChecklistCity of Eloy checklist (rev. 05/25/2026) covering repair/replacement, added circuits, new service/upgrades, and new meters
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Minimal Permit — Electrical permit, improvement valuation less than $500 | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 electrical issuance fee and per-item Unit/System Fee Schedule… Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 electrical issuance fee and per-item Unit/System Fee Schedule were deleted in their entirety in the FY 2026-2027 schedule ('Deleted to simplify the Fee Schedule and incorporated into the Minimal Permits') and replaced by flat minimal-permit fees plus the general valuation table for larger jobs |
| Combination Building Permit (any combination of Building, Electrical, Mechanical, or Plumbing permit types), improvement valuation less than $1,000 | $92.50 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees |
| Electrical work with improvement valuation of $500 or more | Per the Residential and Commercial Permit Fees valuation table ($70.00 minimum for $1-$500; $70.00 + $4.50 per $100 to $2,000; scaling tiers as published) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — with the former per-item electrical Unit Fee Schedule deleted, electrical permits above the minimal-permit threshold are billed on the general valuation-based Building Permit Fee table |
| Residential Panel Upgrade (200 amp total maximum panel) | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section (relocated from Plan Review fees; was $60.00 in FY 2025-2026) |
| Temporary Electrical Service, including electrical pole (temporary power) | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section |
Plumbing Permit
VerifiedRequired for plumbing installation, alteration, or repair work in Eloy, including gas piping and water heater work, governed by the 2018 IRC plumbing provisions as adopted by the City.
Verified 2026-08-21 · Source
Requirements
- Plumbing permit required for interior plumbing repair/replacement, new/replacement gas yard lines, new gas appliances, water heater fuel-type changes, and water/sewer yard line repair or replacement
- Governed by the 2018 IRC plumbing provisions as adopted by the City of Eloy
- Correct ROC license class must be listed for the specific plumbing work being performed
- Gas repairs require BTU ratings and total developed length of piping at all gas appliances; gas yard line work requires dielectric union and house-side shutoff details
- Water heater replacement includes a processing fee; storage-tank water heaters require a drain pan and drain line except where no drain is readily available for a replacement unit
Required documents
- RequiredCity of Eloy Building Permit Application (Plumbing)Submitted through the iworq electronic permit portal
- RequiredMinimal Plumbing Permit Only ChecklistCity of Eloy checklist (rev. 05/25/2026) covering interior plumbing repair/replace, gas yard lines, new gas appliances, water heater changes, and water/sewer yard line repair
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Minimal Permit — Plumbing permit, improvement valuation less than $500 | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 plumbing issuance fee and per-fixture Unit Fee Schedule… Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 plumbing issuance fee and per-fixture Unit Fee Schedule (fixtures, sewers, gas piping, water heater replacement lines) were deleted in their entirety in the FY 2026-2027 schedule ('Deleted to simplify the Fee Schedule and incorporated into the Minimal Permits') and replaced by flat minimal-permit fees plus the general valuation table for larger jobs |
| Combination Building Permit (any combination of Building, Electrical, Mechanical, or Plumbing permit types), improvement valuation less than $1,000 | $92.50 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees |
| Plumbing work with improvement valuation of $500 or more | Per the Residential and Commercial Permit Fees valuation table ($70.00 minimum for $1-$500; $70.00 + $4.50 per $100 to $2,000; scaling tiers as published) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — with the former per-fixture plumbing Unit Fee Schedule deleted, plumbing permits above the minimal-permit threshold are billed on the general valuation-based Building Permit Fee table |
Mechanical / HVAC Permit
VerifiedRequired for heating, ventilation, and air conditioning installations in Eloy, governed by the 2018 International Mechanical Code (IMC) as adopted by the City. New/replacement HVAC must meet the City's amended minimum efficiency thresholds (16 SEER, 78%/80% AFUE).
Verified 2026-08-21 · Source
Requirements
- Mechanical permit required for new heating/AC units, new locations or ductwork/curbing, fireplace inserts/replacement, firepits/BBQs/outdoor kitchens with gas connections, and new or replacement wall/ground-mounted equipment
- Governed by the 2018 IMC as adopted by the City of Eloy
- New and replacement HVAC equipment must be sized per ACCA Manual J, S, and D (load calculation, equipment selection, duct design); minimum 16 SEER for air conditioning equipment; minimum 78% AFUE (weatherized) / 80% AFUE (non-weatherized) for gas heating equipment
- New rooftop or attic-space units require a Roof System Confirmation (sealed engineer letter or truss manufacturer verification letter) and RESCheck for all new mechanical units
- Correct ROC license class must be listed for the specific mechanical work being performed
Required documents
- RequiredCity of Eloy Building Permit Application (Mechanical)Submitted through the iworq electronic permit portal
- RequiredMinimal Mechanical Permit Only ChecklistCity of Eloy checklist (rev. 05/25/2026) covering new heating/AC units, fireplace inserts, firepits/outdoor kitchens with gas, and wall/ground-mounted equipment
- RequiredManual J, S, and D Load CalculationsRequired for sizing new or replacement HVAC equipment and duct design
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Minimal Permit — Mechanical permit, improvement valuation less than $500 | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 mechanical issuance fee and per-unit fee schedule (HVAC… Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees — the FY 2025-2026 mechanical issuance fee and per-unit fee schedule (HVAC change-outs, combination units, ductwork, air-conditioning and furnace lines) were deleted in their entirety in the FY 2026-2027 schedule ('Deleted to simplify the Fee Schedule and incorporated into the Minimal Permits') and replaced by flat minimal-permit fees plus the general valuation table for larger jobs |
| Combination Building Permit (any combination of Building, Electrical, Mechanical, or Plumbing permit types), improvement valuation less than $1,000 | $92.50 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees |
| Mechanical work with improvement valuation of $500 or more | Per the Residential and Commercial Permit Fees valuation table ($70.00 minimum for $1-$500; $70.00 + $4.50 per $100 to $2,000; scaling tiers as published) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — with the former mechanical unit-fee schedule deleted, mechanical permits above the minimal-permit threshold are billed on the general valuation-based Building Permit Fee table |
Re-Roofing Permit
Required for residential re-roofing in Eloy only when 100% of the roof sheathing is being replaced; if 50% or less of the sheathing is replaced, no permit is required. Billed as a flat fee for one- and two-dwelling structures.
Reviewed 2026-08-21 · Source
Requirements
- A roofing permit is required only if 100% of the roof sheathing is being replaced; if 50% or less of the sheathing is being replaced, no permit is required (a narrow middle ground between 50% and 100% sheathing replacement is not explicitly addressed in the published fee-schedule language)
- Applies to one- and two-dwelling (residential) structures per the published flat-fee category
- Governed by 2018 IBC/IRC roofing provisions as adopted by the City of Eloy
Required documents
- RequiredCity of Eloy Building Permit Application (Re-Roof)Submitted through the iworq electronic permit portal
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Re-Roof (One- and Two-Dwelling Structures Only) — roofing permit when 100% of roof sheathing is being replaced | $210.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section — raised from $180.00 in FY 2025-2026; no permit required if 50% or less of the roof sheathing is being replaced |
Residential Solar Photovoltaic (PV) Permit
VerifiedRequired for installation of rooftop residential solar photovoltaic systems on existing residential (R-3) buildings in Eloy. Governed by the 2018 IRC/IECC solar-ready provisions and the 2017 NEC as adopted by the City, with a dedicated Solar System Minimum Submittal Checklist.
Verified 2026-08-21 · Source
Requirements
- Governed by the 2018 IRC (Appendix RA103, Solar-Ready Provisions) and 2017 NEC as adopted by the City of Eloy
- Cover sheet, site plan, solar plans (roof layout with fire pathways, roof support/racking detail, placard/label locations, one-line diagram), and electrical plan (battery install information, equipment specs) required, sealed by an Arizona-registered engineer or architect
- Structural design analysis for panel modules and mounting system required for residential systems built prior to 2021; all commercial systems require a sealed structural analysis regardless of build date
- Correct ROC license class must be listed on the application for the work being performed
- Fee is calculated per system, up to and including 10kW, for residential (R-3) buildings
Required documents
- RequiredCity of Eloy Building Permit Application (Solar)Submitted through the iworq electronic permit portal
- RequiredResidential Solar System Permit ChecklistCity of Eloy checklist (rev. 05/25/2026) covering cover sheet, site plan, solar plans, and electrical plan requirements, all sealed by an Arizona-registered engineer or architect
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Photovoltaic Systems on Existing Residential (R-3) Buildings, per system 10kW or less — Building Permit | $140.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section — raised from $135.00 in FY 2025-2026 and relocated from the Plan Review fees section to the Permits section. |
| Residential Photovoltaic Systems on Existing Residential (R-3) Buildings, per system 10kW or less — Plan Review | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — raised from $60.00 in FY 2025-2026. |
EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished)
VerifiedRequired for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Eloy, governed by the 2017 NEC (Article 625) as adopted by the City. History: the FY 2025-2026 schedule carried a NAMED 'Electrical Vehicle Charging Stations (Residential) - per station' fee row whose dollar cell was genuinely blank in both the January 12, 2026 and February 16, 2026 amended versions — a confirmed gap in the City's own document. The Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) DELETED that row outright, with the stated justification that it was not applicable to plan review fees and was duplicative of the electrical line-item fees — so an EV charger circuit is now simply ordinary electrical work: a flat $70.00 Minimal Electrical Permit when the improvement valuation is under $500 ($92.50 as a combination permit under $1,000), or the general valuation-based fee table above that. The City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026) explicitly lists 'EV charger' among the equipment types requiring Load Calculations under the general 'Adding Circuits or Outlets' electrical-permit submittal category.
Verified 2026-08-21 · Source
Requirements
- Electrical permit required for the EV charger circuit installation, filed via the City's iworq electronic permit portal
- Load Calculations required for the EV charger circuit, per the City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026), 'Adding Circuits or Outlets' section
- Electrical schematic/floor plan showing new and existing circuit/outlet locations, circuit amperage, and GFCI/AFCI requirements
- Correct ROC (Registrar of Contractors) license class must be listed for the electrical work being performed
- Governed by the 2017 NEC as adopted by the City of Eloy, including Article 625 (Electric Vehicle Power Transfer System)
Required documents
- RequiredCity of Eloy Building Permit Application (Electrical)Submitted through the iworq electronic permit portal
- RequiredMinimal Electrical Only Permit ChecklistCity of Eloy checklist (rev. 05/25/2026) explicitly listing 'EV charger' as requiring Load Calculations under 'Adding Circuits or Outlets'
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Minimal Permit — Electrical permit, improvement valuation less than $500 (typical residential EV charger circuit) | $70.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees. Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees. The named 'Electrical Vehicle Charging Stations (Residential) - per station' row — which carried a blank fee cell in both the January 12, 2026 and February 16, 2026 amended FY 2025-2026 schedules — was DELETED in the FY 2026-2027 schedule with the stated justification that it was duplicative of the electrical line-item fees; EV charger circuits are now billed as ordinary electrical work |
| Combination Building Permit (any combination of Building, Electrical, Mechanical, or Plumbing permit types), improvement valuation less than $1,000 | $92.50 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Minimal Permit Fees |
| EV charger work with improvement valuation of $500 or more | Per the Residential and Commercial Permit Fees valuation table ($70.00 minimum for $1-$500; $70.00 + $4.50 per $100 to $2,000; scaling tiers as published) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — the former electrical issuance-plus-unit-fee model was deleted in FY 2026-2027 |
Demolition Permit
VerifiedRequired for demolition of residential and other structures in Eloy. Billed as a flat fee tiered by structure type (accessory/garage, R-3 single-family/two-family, or other), plus a Demo Plan Review fee, per the City's Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026).
Verified 2026-08-21 · Source
Requirements
- Building permit required before demolishing a structure within Eloy city limits
- Fee is tiered by structure category: residential accessory building/garage, single-family residence, or structures other than residential single-family
- Pinal County Dust Control Permit coordination expected given the City's location in the West Pinal Nonattainment Area
- Project is not legally complete until an approved final inspection has occurred
Required documents
- RequiredCity of Eloy Building Permit Application (Demolition)Submitted through the iworq electronic permit portal
- RequiredSite PlanShowing the structure(s) to be demolished and other existing structures on the parcel
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition of Buildings Permit — Single-family and Two-Family (R-3) accessory building or garage, per structure | $35.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Miscellaneous Permits — raised from $30.00 in FY 2025-2026 |
| Demolition of Buildings Permit — Single-family and Two-Family (R-3), per structure | $105.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Miscellaneous Permits — raised from $90.00 in FY 2025-2026 |
| Demolition of Buildings Permit — All other structures, per structure | $280.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Miscellaneous Permits — raised from $240.00 in FY 2025-2026 |
| Demo Plan Review | $105.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Plan Review Fees — new line item added in FY 2026-2027 |
Sign Permit
VerifiedRequired for permanent and temporary commercial/business signage in Eloy, administered by the Community Development Department using a dedicated Sign Permit Application separate from the general Building Permit Application. Plan review is billed at 65% of the calculated building permit fee and the permit fee itself is based on total sign(s)/installation valuation using the same Building Permit Fee valuation table used for building permits.
Verified 2026-08-21 · Source
Requirements
- A Sign Permit Application is required before installing permanent signage: attached/wall-mounted, projecting, awning/canopy, freeway pylon, window, electronic message center, or gas-filled signs (building signs), and freestanding/monument signs
- Temporary signage (banner signs, A-frame signs, yard signs, sign walkers) also requires identifying sign type, quantity, and location on the same Sign Permit Application
- Site Plan/Suite Layout Plan showing sign locations, dimensions, aggregate sign area, and street frontage widths required for all applications; freestanding/monument signs additionally require property lines, easements, and sight visibility triangles shown
- Freestanding/monument sign structural and footing details, and any new electrical circuitry plans to accommodate the sign, must be sealed by an Arizona-registered engineer/architect; if existing electrical circuitry will be used instead, the cover sheet must state 'No new electrical circuitry is required or will be provided for the sign(s)'
- Fascia modification or exterior color changes to a building or a fuel/gas/energy station canopy are NOT allowed, approved, or permitted through a Sign Permit — these require a separate Minor Site Plan Application, and building elevations submitted with a sign application must match previously-approved Site Plan elevations
- 'Sign' is defined per Zoning Ordinance Section 21-9-1 to include any visual element or device designed to attract attention or convey information for a business/service/product/organization, including logos, banners, balloons, streamers, inflatable structures, projected picture signs, and holographic projection signs
- Property Owner Authorization (or a notarized Property Owner's Permission Form) is required when the applicant is an agent (lawyer, planner, architect, landscape architect, etc.) rather than the property owner
- Sign Permit Application expires 180 days after the last plan submittal
Required documents
- RequiredSign Permit ApplicationCity of Eloy Community Development Department application (525 North C Street, Suite 102); includes an attached notarized Property Owner's Permission Form for use when an agent applies on the owner's behalf
- RequiredSign Permit Application ChecklistCity of Eloy checklist (rev. 12/21/2024) covering Part I (general requirements: application, fees, property owner authorization) and Part II (site plan, building elevations, color renderings, section details, sign structure/footing details, electrical plans, sign type/quantity for both permanent and temporary signage)
- RequiredSite Plan / Suite Layout PlanLocation, dimensions, and aggregate area of all proposed and existing signs; property lines/easements/sight visibility triangles for freestanding signs
- RequiredColor Sign Elevations and RenderingsRendering/photo rendering of the sign on the building/suite frontage or as a freestanding structure, with materials, paint colors, and illumination methods called out
- OptionalSign Structure and Footing Details / Electrical PlansStructural and footing calculations for freestanding/monument signs, and electrical plans for any new circuitry — both sealed by an Arizona Registrant
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign Permit Fee — Pylon sign / Freestanding-monument sign | $1,050.00 per pylon sign; $210.00 per freestanding/monument sign | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section — FY 2026-2027 replaced the former valuation-based sign permit fee with itemized per-sign fees; Show full citationHideCity of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section — FY 2026-2027 replaced the former valuation-based sign permit fee with itemized per-sign fees; the total permit fee is the sum of all sign fees for all sign types in the application |
| Sign Permit Fee — All other signs, by sign area | $33.00 per sign (over 0 to 20 sq ft); $65.00 per sign (over 20 to 30 sq ft); $98.00 per sign (over 30 sq ft) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Permits section |
| Sign Plan Review Fee — Pylon and freestanding/monument signs greater than 6 feet high or greater than 30 sq ft | $175.00 for the first hour, plus $140.00 for each additional hour, per review cycle | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Plan Review Fees — FY 2026-2027 replaced the former 65%-of-building-permit-fee sign plan review with itemized sign plan review fees |
| Sign Plan Review Fee — All other signs, by sign area | $24.00 per sign (over 0 to 20 sq ft); $48.00 per sign (over 20 to 30 sq ft); $72.00 per sign (over 30 sq ft) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), Plan Review Fees; the total plan review fee is based on the sum of all sign fees of all sign types proposed in the application |
Fire Sprinkler & Fire Alarm Permit (Eloy Fire District)
VerifiedEloy is served by the independent Eloy Fire District (formed August 19, 1946, predating the City of Eloy's own incorporation; serves over 10,300 residents across 55+ square miles), which conducts its own plan review, permitting, invoicing, and inspections for fire protection systems directly through its Fire Marshal's office — a separate process from the City of Eloy Community Development Building Safety Division. A single 'Operational/Special Use Permit' application covers fire alarm systems and automatic fire sprinkler systems (along with kitchen hood suppression, standpipes, and other fire protection systems), but the Fire District publishes genuinely distinct fee line items for each: a flat fee for fire alarm systems and a plan-review-plus-head-count fee structure for sprinkler systems. Governed by the 2018 International Codes and referenced NFPA standards as adopted by the Eloy Fire District.
Verified 2026-07-23 · Source
Requirements
- A dedicated Eloy Fire District permit (submitted to the Fire Marshal's office, separate from the City's iworq building-permit portal) is required before installing an automatic fire sprinkler system, a fire alarm system, a fire pump, standpipes, an automatic kitchen hood extinguishing system, or an above-ground fuel storage tank
- Submit the Eloy Fire District permit application, a one-page site plan, and a complete set of plans/drawings to the Fire Marshal (520-466-3544) — either one electronic set of plans or two paper sets; re-submittals of approved plans should include the plan name or number
- Commercial projects must include documentation for all required fire protection systems (sprinklers, standpipes, fire alarms, kitchen suppression) even if a system is deferred, including calculations and component cut sheets
- All necessary Eloy Fire District permits must be obtained BEFORE commencing construction; starting work without the required permit results in doubled permit and review fees
- A copy of the approved Eloy Fire District Permit is a required submittal item on the corresponding City of Eloy building permit application (confirmed on the City's 2018 IRC Minimum Submittal Checklist, Part III)
- Permits expire if work does not begin within 180 days, or if work is suspended for 180 consecutive days; written extension requests are accepted
- Ongoing fire & life safety system inspection/maintenance reports (for fire sprinkler systems, fire alarm systems, kitchen hood suppression, standpipes, fire pumps, and other tracked systems) must be submitted electronically via The Compliance Engine (contact Brycer, (630) 413-9511, for training/support)
Required documents
- RequiredEloy Fire District Operational/Special Use Permit ApplicationLists Fire Alarm, Fire Extinguishing System (cooking), Sprinkler Plan Review, Fire Suppression System (by head count), Site Plan/Plat Review, and Above Ground Fuel Storage Tank as separate fee line items on one shared form; requires construction address, parcel number, occupancy class/structure type, and owner/contractor information
- RequiredOne-Page Site PlanRequired with every Eloy Fire District permit application per the Fire Permit and Compliance Guide
- RequiredComplete Set of Plans/DrawingsOne electronic set or two paper sets; commercial projects must include calculations and component cut sheets for sprinkler, standpipe, fire alarm, and kitchen suppression systems, even if deferred
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fire Alarm System (Construction Permit) | $250.00 | Eloy Fire District Permit Fees (2024); includes system plans review and acceptance testing. Verified against both the Fire District's published fee schedule and its own Operational/Special Use Permit application form, which lists 'Fire Alarm' as a $250.00 line item. |
| Automatic Fire Sprinkler System — Plan Review | $100.00 per hour (2-hour minimum) | Eloy Fire District Permit Fees (2024) |
| Automatic Fire Sprinkler System — Permit Fee, up to 100 heads | $100.00 | Eloy Fire District Permit Fees (2024) |
| Automatic Fire Sprinkler System — Permit Fee, 101-500 heads | $250.00 | Eloy Fire District Permit Fees (2024); each additional 100 heads above 500 adds $100.00 |
| Automatic Hood Extinguishing System (Kitchen Suppression) | $250.00 | Eloy Fire District Permit Fees (2024); includes system plans review and acceptance testing |
| Site Plan Review (general, applies when required for the project) | $100.00 per hour (2-hour minimum) | Eloy Fire District Permit Fees (2024); Access Roads review is included within this Site Plan Review fee |
| Late-permit penalty | Permit and review fees are doubled | Eloy Fire District Permit Fees (2024) and Fire Permit and Compliance Guide — applies when construction begins before the required Fire District permit is obtained |
Certificate of Occupancy / Change of Occupancy
VerifiedCovers two related City of Eloy processes administered by the Community Development / Building Safety Division: (1) the standard Certificate of Occupancy (full, or temporary/partial/conditional) issued at completion of a building permit project, requiring sign-off from the City Engineer, Planning/Zoning, the Eloy Fire District, Water/Sewer, and the Water Department before the Building Inspector and Chief Building Official issue it; and (2) the standalone 'C of O / Occupancy Change' administrative process (also covering Home Occupation) for an existing building changing tenant, business name, or use where no work requiring a building permit (mechanical, plumbing, electrical, partitions, signs, etc.) is being performed.
Verified 2026-08-21 · Source
Requirements
- A structure may not be used, occupied, or furnished in whole or in part prior to issuance of the Certificate of Occupancy
- A FULL Certificate of Occupancy requires the entire project to be completed with no conditions; a TEMPORARY Certificate of Occupancy may be issued once a published minimum item list is met (parking lots installed, roofing/siding complete, heating/cooling installed, electric outlets/panels/light fixtures installed, address visible from the street, water/plumbing fixtures in, smoke detectors and sprinklers operative, handrails/guardrails, emergency lights, fire-rated doors, fire alarms operative, exit signs lit, exit hardware installed, fire extinguishers if required, handicap items installed, and at least 85% of landscaping complete)
- All department approvals (City Engineer, Planning/Zoning, Eloy Fire District, Water/Sewer, Water Department) must be received before the Building Inspector can conduct the final inspection; utility clearance and the Certificate of Occupancy cannot be issued without all department approvals
- The 'C of O / Occupancy Change' form is used for a Certificate of Occupancy, a Home Occupation, or a Change of Occupancy (check one box); it requires property owner and renter/tenant information, square footage of floor area, prior use vs. proposed use, whether hazardous materials are stored on site, and whether an existing fire sprinkler system is present
- Signing the Change of Occupancy form certifies that no changes or alterations requiring a building permit (mechanical, plumbing, electrical, partitions, signs, etc.) are being made to the structure; any sign changes require separate approvals and permits regardless
- Two copies of a floor plan are required at time of Change of Occupancy application
Required documents
- RequiredCertificate of Occupancy ApplicationCity of Eloy form routing sign-off through City Engineer (520-466-3082), Planning/Zoning (520-466-2578), Fire District (520-466-3544), Water/Sewer (520-464-1392), and Water Dept. (520-466-9201) before Building Inspector and Chief Building Official final signatures
- RequiredC of O / Occupancy Change FormCity of Eloy Community Development Department / Building Safety form used for a Certificate of Occupancy, Home Occupation, or Change of Occupancy (existing building, new tenant/use, no permitted work) — includes prior/proposed use, hazardous materials disclosure, and existing fire sprinkler system disclosure
- RequiredFloor Plan (2 copies)Required at time of Change of Occupancy application submittal
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Certificate of Occupancy — non-residential | $70.00 per building | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — raised from $60.00 in FY 2025-2026; fee collected at time of permit issuance. |
| Certificate of Occupancy — non-residential tenant improvement | $35.00 per tenant | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) — raised from $30.00 in FY 2025-2026; fee collected at time of permit issuance. |
| Certificate of Occupancy — R-3 single-family | $35.00 per building | From the City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; the same figure applies to Eloy's residential building permit. |
| Temporary, Partial, or Conditional Certificate of Occupancy — refundable compliance deposit | Greater of $1,500.00 or the sum of all permit fees issued to the project (foundation, building, electrical, mechanical, and plumbing) | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; deposit (cash or irrevocable letter of credit) paid to the City before staff conducts the related inspection, generally refunded within 30 days of Certificate of Occupancy issuance |
| Temporary, Partial, or Conditional Certificate of Occupancy — processing fee | $210.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; charged in addition to the compliance deposit, at the time each certificate is applied for |
| Change of Occupancy (existing building, no permitted work) — administrative processing fee | Not found | Re-checked against the Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) on 2026-08-21 — still no dedicated line item. Show full citationHideRe-checked against the Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026) on 2026-08-21 — still no dedicated line item. Previously exhausted the FY 2025-2026 schedule (all 19 pages checked page-by-page), the Building Permits/checklists/forms page, and the Community Development page/site search — no dedicated fee line item for the standalone 'Change of Occupancy' or 'Home Occupation' form was found distinct from the Certificate of Occupancy fees above. This appears to be a no-fee administrative process when no building-permit-triggering work is involved, but that is not explicitly stated anywhere found; omitted rather than invented. Confirm directly with Community Development (520-466-2578). |
Commercial Building Permit
VerifiedRequired for new commercial/industrial construction, building shells, additions, alterations, and tenant improvements to non-residential occupancies in the City of Eloy. Reviewed against the 2018 IBC (and applicable 2018 IFC, 2018 IECC, and 2017 NEC provisions) as adopted and amended under Chapter 5 of the Eloy City Code (Ordinance No. 20-900). There is no separate tenant-improvement permit type or checklist published by the City: TI work uses the same 'COMMERCIAL/INDUSTRIAL' project-type option on the standard City of Eloy Building Permit Application and the same valuation-based fee table as new commercial construction; the only TI-specific line item found is a distinct, lower Certificate of Occupancy fee.
Verified 2026-08-21 · Source
Requirements
- Building permit required for new commercial/industrial construction, building shells, additions, alterations, and tenant improvements to non-residential occupancies within Eloy city limits
- Selected via the 'COMMERCIAL/INDUSTRIAL' project-type checkbox on the City's standard Building Permit Application (rev. 07/14/2025, agent-authorization portion rev. 08/05/2025) — the same application form used for residential, solar, and all other project types, with fields for Occupancy Type, Construction Type/Classification, square footage, Fire District Permit #, and estimated construction value
- Plans must comply with the 2018 IBC/IFC/IECC and City of Eloy amendments; construction documents must be submitted as flattened PDFs (50 MB max per file) through the City's iworq electronic permit portal per the City's Electronic File Submittal Requirements
- Building Shell Permits are valued at 80% of the ICC Building Valuation Table (or signed construction contract cost, whichever is less); foundation-only permits are valued at 25% of the ICC table (or contract cost, whichever is less)
- A Fire District Permit is a required field/attachment on the Building Permit Application, and fire/life-safety systems (fire alarms, sprinklers, exit signage, exit hardware, fire extinguishers where required) must be installed and operative before occupancy
- Outdoor Lighting Compliance Worksheet required for multi-family and non-residential land uses (fully shielded fixtures per City Code § 21-4-5)
- Tenant improvement work to an existing non-residential building is not a distinct permit type in the City's published checklists or fee schedule — it is processed as a Commercial/Industrial building permit using the same valuation-based fee table; the only tenant-improvement-specific fee found is the Certificate of Occupancy line (see fees)
- A Certificate of Occupancy requires sign-off from the City Engineer, Planning/Zoning, the Eloy Fire District, Water/Sewer, and the Water Department before the Building Inspector and Chief Building Official can issue it; you may not occupy or use the structure before it is issued
Required documents
- RequiredCity of Eloy Building Permit ApplicationSubmitted through the City's iworq electronic permit portal (eloypermits.portal.iworq.net) or in person; select 'COMMERCIAL/INDUSTRIAL' as the project type. Paper form rev. 07/14/2025
- OptionalProperty Owner Authorization FormRequired when the applicant is an agent (contractor, architect, engineer, etc.) rather than the property owner
- RequiredConstruction Documents (site plan, floor plan, structural/MEP plans, elevations)Sealed by an Arizona-registered engineer or architect where required; submitted as flattened electronic PDFs per the City's Electronic File Submittal Requirements
- RequiredOutdoor Lighting Compliance Worksheet — Multiple-family and Non-residential Land UsesCity of Eloy worksheet documenting compliance with the City's outdoor/exterior lighting shielding requirements for non-residential land uses
- RequiredCertificate of Occupancy ApplicationSubmitted at project completion to close out the building permit; the Certificate of Occupancy / Change of Occupancy permit type covers the full department sign-off sequence.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — Minimum ($1-$500 valuation) | $60.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule (effective July 1, 2026), 'Residential and Commercial Permit Fees Based on Total Valuation of Improvements' table — the same valuation table applies to both residential and commercial permits |
| Building Permit Fee — $500.01 to $2,000 | $70.00 for the first $500.00 plus $4.50 for each additional $100.00 or fraction thereof, to and including $2,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $2,000.01 to $40,000 | $137.50 for the first $2,000.00 plus $15.00 for each additional $1,000.00 or fraction thereof, to and including $40,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $40,000.01 to $100,000 | $707.50 for the first $40,000.00 plus $12.00 for each additional $1,000.00 or fraction thereof, to and including $100,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $100,000.01 to $500,000 | $1,427.50 for the first $100,000.00 plus $8.00 for each additional $1,000.00 or fraction thereof, to and including $500,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — $500,000.01 to $1,000,000 | $4,627.50 for the first $500,000.00 plus $6.60 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00 | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Permit Fee — over $1,000,000 | $7,927.50 for the first $1,000,000.00 plus $5.25 for each additional $1,000.00 to $5,000,000.00; $28,927.50 for the first $5,000,000.00 plus $5.00 per additional $1,000.00 to $10,000,000.00; $54,427.50 for the first $10,000,000.00 plus $4.50 per additional $1,000.00 above that | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule |
| Building Shell Permit — valuation basis | 80% of the ICC Building Valuation Table, or signed construction contract cost, whichever is less | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule, Building Permit Fees section; the resulting valuation is then run through the same fee table above |
| Plan Review Fee (general) | 65% of the calculated Building Permit Fee | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule, Basic Plan Review Services section — applies to commercial and residential alike |
| Minor Revisions of Plans after Permit Issuance — Commercial (2-hour minimum) | $270.00 per hour, plus $30.00 per additional review | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; the commercial rate/minimum is double the residential rate ($135.00/hour, 1-hour minimum) |
| Certificate of Occupancy — non-residential (new building/shell) | $60.00 per building | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; fee collected at time of permit issuance |
| Certificate of Occupancy — non-residential tenant improvement | $30.00 per non-residential tenant improvement | City of Eloy Adopted FY 2026-2027 Consolidated Rate and Fee Schedule; fee collected at time of permit issuance — this is the only tenant-improvement-specific fee found published, distinct from the $60.00 new-building/shell Certificate of Occupancy fee |
Sources & verification
Verified against official sources. Last reviewed 2026-08-21.
Fee schedules
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.