Nogales building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Nogales, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Community Development Department: 777 North Grand Avenue, Nogales, AZ 85621. Project/permit submittal intake (Nogales Information and Development Center, "One Stop"): 1450 N. Hohokam Drive, Nogales, AZ 85621
- Phone
- 520-287-6571 (Community Development main line); 520-287-7245 (Nogales Information and Development Center / One Stop intake, Public Works Department)
- Office hours
- Not published on the City's Community Development or Planning Division pages as of this review. Permit tracking and status checks are available 24/7 online via the City's Accela Citizen Access Portal (aca-prod.accela.com/NOGALES).
- Website
- Official site
Inspection sequence
Applies to: Residential Addition / Remodel Permit
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to existing structure
- 3
Final / Occupancy Inspection
Within 10 working days of notice of completion, per Development Code Sec. 3.103.e.1
Applies to: Residential Building Permit (New Construction, Additions, Repairs)
- 1
Foundation/Footing
Before concrete pour, per 2018 IBC/IRC
- 2
Framing
Structural framing and connections per 2018 IRC/IBC
- 3
Final / Occupancy Inspection
Within 10 working days after the City receives notice that construction is complete and ready for use, the Building Official makes a final inspection to confirm Development Code compliance before issuing an Occupancy Permit (Sec. 3.103.e.1)
Applies to: Alternative Energy System Permit (Solar / Photovoltaic, Geothermal, Wind)
- 1
Rough Electrical / Mounting
Conduit runs, wire sizing, mounting/racking attachment before energizing or final cover, per adopted codes and the Uniform Solar Energy Code
- 2
Final
Final inspection preceding Occupancy Permit / sign-off (10 working days from notice of completion, Sec. 3.103.e.1)
Applies to: Electric Vehicle (EV) Charger Permit
- 1
Rough-In
New EV charger circuit wiring, box placement, and panel connections before walls are closed, per 2017 NEC / NEC Article 625
- 2
Final
Charger circuit, disconnect, and protections verified per 2017 NEC
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed, per 2017 NEC
- 2
Final
Devices installed, panel labeled, protections verified per 2017 NEC; part of the final inspection preceding Occupancy Permit issuance (10 working days from notice of completion, Sec. 3.103.e.1)
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork, gas line, and equipment placement before walls are closed
- 2
Final
Equipment operational, clearances and combustion air verified; part of the final inspection preceding Occupancy Permit issuance (10 working days from notice of completion, Sec. 3.103.e.1)
Applies to: Mobile Home / Manufactured Home Installation Permit
- 1
Foundation/Tie-Down
Site work, slab/footing, and tie-down verification before final placement
- 2
Final / Occupancy Inspection
Within 10 working days of notice of completion, per Development Code Sec. 3.103.e.1
Applies to: Plumbing Permit
- 1
Rough-In
After pipes installed, before walls closed
- 2
Final
Fixtures connected, no leaks; part of the final inspection preceding Occupancy Permit issuance (10 working days from notice of completion, Sec. 3.103.e.1)
Final inspection only: Demolition Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nogales building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Nogales building permits
Get alerts for Nogales
We'll email you when Nogales's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.