Residential Addition / Remodel Permit — Nogales, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.nogalesaz.gov/documentcenter/view/114
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel Permit in Nogales, Arizona
Required under the City of Nogales Development Code for room additions, remodels, and alterations to existing one- and two-family dwellings, unless the narrow 120-sq-ft/no-utility-work exemption applies. Reviewed against the 2018 IRC and City of Nogales Development Code amendments.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for room additions, remodels, and alterations exceeding 120 sq ft of added area, or involving any electric, plumbing, or gas work regardless of size (Development Code Sec. 3.103.d.1-d.2)
- No improvements may be placed on, and no repairs made to, property held to be in non-conformance with the Development Code without a building permit (Sec. 3.103.d.3)
- Site plan for additions to single-family residences in an approved subdivision is submitted together with the Building Permit Application rather than as a standalone Development Site Plan (Sec. 3.105.b.1)
- Applicant must submit the City of Nogales Project Submittal Application with project valuation and required attachments
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to existing structure
- 3
Final / Occupancy Inspection
Within 10 working days of notice of completion, per Development Code Sec. 3.103.e.1
See the full Nogales inspection guide — scheduling & re-inspection fees →
Tips
- The 120-sq-ft no-permit exemption (Sec. 3.103.d.2) is narrower than in many other Arizona cities: it is voided entirely the moment ANY electric, plumbing, or gas work is involved, regardless of the addition's total size.
- As with new construction, a Zoning Compliance Certificate (10-working-day statutory turnaround, Sec. 3.103.c.3) is a prerequisite before the building permit itself can be issued.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nogales building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Nogales
Residential Addition / Remodel Permit in other cities
Compare residential addition / remodel permit fees across Arizona →
Look up this fee in a different city →