Residential Addition / Remodel / Accessory Structure Permit in Benson, Arizona

Required for room additions, remodels, and accessory structures (stick-built or pre-built) to existing one- and two-family dwellings in Benson. Reviewed against the 2024 IRC as adopted by Ordinance 645 (2015 IRC for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for room additions, remodels, and accessory structures (garages, storage sheds, etc.), whether stick-built or pre-built (e.g., prefabricated sheds)
  • Site plan and construction plans required per the same submittal standards as new residential construction (detached site plan at 1"=20' scale; two sets of construction plans)
  • Pre-built accessory structures require setbacks, anchoring/tie-down, and foundation inspections in addition to any applicable electrical/plumbing rough-ins
  • Stick-built accessory structures follow the full framing/lath/sheetrock/final inspection sequence
  • HOA review verification required prior to submittal if applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011
$47.00 (valuation $1-$1,000) up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000 (same valuation table as new residential construction)
Plan Review FeeCity Code of the City of Benson, Chapter 16, Building Division
65 percent of the calculated building permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Remodel / Accessory Structure Permit permit actually take in Benson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Setbacks

    Verifies addition/accessory structure location against approved site plan

  2. 2

    Foundation

    Required before concrete pour for additions and pre-built accessory structure foundations

  3. 3

    Framing (stick-built) / Anchoring-Tie Downs (pre-built)

    Framing Floor Deck and Framing Rough for stick-built structures; anchoring/tie-downs for pre-built accessory structures

  4. 4

    Intermediates / Sheetrock

    Electrical and plumbing rough-ins where applicable, prior to closing walls

  5. 5

    Final

    Completed work verified against approved plans (Final - All Trades for pre-built accessory structures)

See the full Benson inspection guide — scheduling & re-inspection fees →

Tips

  • The City's Required Inspections List treats 'Accessory Structure (Pre-Built)' and 'Accessory Structure (Stick Built)' as two distinct inspection sequences — pre-built units skip the framing/lath/sheetrock steps in favor of anchoring/tie-down and foundation checks.
  • As of July 2026, the City of Benson does not appear to publish permit-specific plan review turnaround times for additions/remodels/accessory structures on its public website. The City states plan reviews are 'first come, first served,' but no category-specific business-day timeline is published. There is no verifiable online source for this figure — call the Building Department at 520-720-6328 directly.

Frequently asked questions

Yes, the City of Benson requires a building permit for accessory structures, whether pre-built (manufactured shed) or stick-built on site, following the City's Required Inspections List sequence for that structure type.

In Benson, the published Building Permit Fee — Based on Valuation is: $47.00 (valuation $1-$1,000) up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000 (same valuation table as new residential construction). Additional published fees: Plan Review Fee — 65 percent of the calculated building permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Benson does not publish a plan-review timeline for this permit. Contact City of Benson Building Department (Community Development) at 520-720-6328 for current turnaround.

You'll need: Online Building Permit Application (iWorQ Citizen Portal); A.R.S. Title 32 Form; Site Plan. See the required-documents checklist on this page for details on each.

Benson requires 5 inspection(s) for a residential addition / remodel / accessory structure permit, in order: Setbacks, Foundation, Framing (stick-built) / Anchoring-Tie Downs (pre-built), Intermediates / Sheetrock, Final. Schedule each through City of Benson Building Department (Community Development) (520-720-6328).

Apply through City of Benson Building Department (Community Development) at 120 W. 6th Street, Benson, AZ 85602 (City Hall / general administration: 101 E. 6th Street, Benson, AZ 85602). Phone: 520-720-6328, email: permits@bensonaz.gov. Office hours: City Hall general office hours: Monday, Tuesday, Thursday, Friday 8:00 AM - 5:00 PM MST; Wednesday 1:00 PM - 5:00 PM MST (Source: City of Benson Contact Us page). Building permit applications are submitted online via the City's iWorQ citizen portal (bensonbuilding.portal.iworq.net); all plan documents, calculations, drawings, and spec sheets must be uploaded in PDF format (image files such as JPEG/TIFF/GIF are not accepted). Plan reviews are performed on a first-come, first-served basis; emergency repairs such as utility or structural failures may take precedence. To request an inspection, email permits@bensonaz.gov at least 24 hours in advance with name, contact number, requested date, permit number, project address, and inspection type.. Official information: https://web.archive.org/web/20251124160757/https://www.bensonaz.gov/departments/building_department/index.php.

Benson, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (Arizona Revised Statutes Title 9). The City of Benson independently adopts and administers its own construction codes through its Building Department. Source: Ordinance 645 (City of Benson, adopted April 13, 2026), whereas clause citing A.R.S. Title 9.; 2024 International Building Code (IBC), as amended by Exhibit A to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, Section 7-1-2 ('Building Codes Adopted'). Per Ordinance 645, all new permit applications received after May 13, 2026 (30 days after the April 13, 2026 adoption date) must comply with this code; plans already in review or approved before that date may remain on the previously adopted 2015 IBC cycle. Source: Ordinance 645, City of Benson (passed and adopted April 13, 2026).; 2024 International Residential Code (IRC), as amended by Exhibit B to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, effective for new applications received on/after May 13, 2026. Source: Ordinance 645, City of Benson.; 2024 International Mechanical Code (IMC), as amended by Exhibit D to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Plumbing Code (IPC), as amended by Exhibit E to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Fuel Gas Code (IFGC), as amended by Exhibit F to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Existing Building Code (IEBC), as amended by Exhibit G to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Swimming Pool and Spa Code (ISPSC), as amended by Exhibit H to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Fire Code (IFC), as amended by Exhibit I to Resolution 11-2026, adopted by reference as the City's uniform fire code. Source: Ordinance 645, City of Benson.; 2024 International Property Maintenance Code (IPMC), as amended by Exhibit J to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2023 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by reference as amended by Exhibit C to Resolution 11-2026 (one edition behind the 2024 ICC set, consistent with the standard NFPA/ICC release-cycle offset). Source: Ordinance 645, City of Benson.; Immediately prior to Ordinance 645 (i.e., for plans submitted and approved before May 13, 2026), the City had adopted the 2015 editions of the International Building, Residential, Mechanical, Plumbing, Fuel Gas, Existing Building, Swimming Pool and Spa, and Property Maintenance Codes, plus the 2015 International Fire Code and 2014 NFPA 70 National Electrical Code, per the former Benson City Code Chapter 7, Section 7-1-1 (Resolution 36-2017). Source: City of Benson Building Department page (Wayback Machine capture, November 24, 2025) and City Code of the City of Benson, Arizona (posting updated April 2023).; Manufactured homes, mobile homes, and factory-built buildings: the City of Benson has an Inspection Services Agreement with the Arizona Department of Housing (ADOH), effective May 3, 2021 for a five-year term, under which the City (as ADOH's local enforcement agency) monitors and enforces ADOH's installation standards (A.R.S. § 41-4004(A)(4); A.A.C. R4-34-102, R4-34-204, R4-34-606, R4-34-801) for manufactured home, mobile home, and factory-built building installations within city limits, including setback and tie-down inspections. Source: Resolution 11-2021 and attached Inspection Services Agreement Between Arizona Department of Housing and City of Benson.; ICC A117.1-2017 Standard and Commentary (Accessible and Usable Buildings and Facilities) is referenced by the City as its accessibility standard, in addition to the federal ADA framework. Source: City of Benson Building Department page.. Local amendments apply — see the Benson overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Benson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.