Residential Solar Photovoltaic (PV) Permit in Benson, Arizona

Required for installation of rooftop residential solar photovoltaic systems in the City of Benson. Governed by the 2024 IRC and 2023 NEC as adopted by Ordinance 645 (2015 IRC / 2014 NEC for applications filed before May 13, 2026). Solar has its own dedicated inspection category on the City's Required Inspections List.

Verified 2026-07-06 · Source

When you need this permit

  • Building/electrical permit required for residential rooftop solar photovoltaic installation
  • Governed by the 2023 NEC (or 2014 NEC for applications filed before May 13, 2026) as adopted by the City of Benson for electrical interconnection work
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form and construction submittals (site plan, roof/racking layout, electrical diagram)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar PV Permit — Based on ValuationCity Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — no separate itemized flat fee for residential solar PV was found; solar is billed under the same valuation-based Building Division fee schedule
Same Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000
Plan Review FeeCity Code of the City of Benson, Chapter 16, Building Division
65 percent of the calculated permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Benson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    The Required Inspections List shows a single Final inspection for the Solar category, covering panel mounting, racking attachment, roof penetration sealing, and electrical connections

See the full Benson inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike Buckeye, Benson has no published dedicated fast-track (e.g., 2-business-day) review procedure specifically for residential solar PV systems as of this review — solar permits go through the same general Building Division review process as other trade permits.
  • As of July 2026, the City of Benson does not appear to publish a permit-specific plan review turnaround time for residential solar PV permits on its public website. There is no verifiable online source for this figure — call the Building Department at 520-720-6328 directly.

Frequently asked questions

Benson requires a residential solar photovoltaic (pv) permit for: Building/electrical permit required for residential rooftop solar photovoltaic installation; Governed by the 2023 NEC (or 2014 NEC for applications filed before May 13, 2026) as adopted by the City of Benson for electrical interconnection work; Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form and construction submittals (site plan, roof/racking layout, electrical diagram). If your project isn't listed, confirm with City of Benson Building Department (Community Development) at 520-720-6328 before starting work.

In Benson, the published Solar PV Permit — Based on Valuation is: Same Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000. Additional published fees: Plan Review Fee — 65 percent of the calculated permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

As of July 2026, the City of Benson does not publish a specific business-day turnaround for solar PV permits. Plan review is performed on a first-come, first-served basis per the Building Department's general process. Call 520-720-6328 for a current estimate.

You'll need: Online Building/Electrical Permit Application (iWorQ Citizen Portal); A.R.S. Title 32 Form. See the required-documents checklist on this page for details on each.

Benson requires 1 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Final. Schedule each through City of Benson Building Department (Community Development) (520-720-6328).

Apply through City of Benson Building Department (Community Development) at 120 W. 6th Street, Benson, AZ 85602 (City Hall / general administration: 101 E. 6th Street, Benson, AZ 85602). Phone: 520-720-6328, email: permits@bensonaz.gov. Office hours: City Hall general office hours: Monday, Tuesday, Thursday, Friday 8:00 AM - 5:00 PM MST; Wednesday 1:00 PM - 5:00 PM MST (Source: City of Benson Contact Us page). Building permit applications are submitted online via the City's iWorQ citizen portal (bensonbuilding.portal.iworq.net); all plan documents, calculations, drawings, and spec sheets must be uploaded in PDF format (image files such as JPEG/TIFF/GIF are not accepted). Plan reviews are performed on a first-come, first-served basis; emergency repairs such as utility or structural failures may take precedence. To request an inspection, email permits@bensonaz.gov at least 24 hours in advance with name, contact number, requested date, permit number, project address, and inspection type.. Official information: https://web.archive.org/web/20251124160757/https://www.bensonaz.gov/departments/building_department/index.php.

Benson, Arizona has adopted: Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (Arizona Revised Statutes Title 9). The City of Benson independently adopts and administers its own construction codes through its Building Department. Source: Ordinance 645 (City of Benson, adopted April 13, 2026), whereas clause citing A.R.S. Title 9.; 2024 International Building Code (IBC), as amended by Exhibit A to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, Section 7-1-2 ('Building Codes Adopted'). Per Ordinance 645, all new permit applications received after May 13, 2026 (30 days after the April 13, 2026 adoption date) must comply with this code; plans already in review or approved before that date may remain on the previously adopted 2015 IBC cycle. Source: Ordinance 645, City of Benson (passed and adopted April 13, 2026).; 2024 International Residential Code (IRC), as amended by Exhibit B to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, effective for new applications received on/after May 13, 2026. Source: Ordinance 645, City of Benson.; 2024 International Mechanical Code (IMC), as amended by Exhibit D to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Plumbing Code (IPC), as amended by Exhibit E to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Fuel Gas Code (IFGC), as amended by Exhibit F to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Existing Building Code (IEBC), as amended by Exhibit G to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Swimming Pool and Spa Code (ISPSC), as amended by Exhibit H to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2024 International Fire Code (IFC), as amended by Exhibit I to Resolution 11-2026, adopted by reference as the City's uniform fire code. Source: Ordinance 645, City of Benson.; 2024 International Property Maintenance Code (IPMC), as amended by Exhibit J to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.; 2023 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by reference as amended by Exhibit C to Resolution 11-2026 (one edition behind the 2024 ICC set, consistent with the standard NFPA/ICC release-cycle offset). Source: Ordinance 645, City of Benson.; Immediately prior to Ordinance 645 (i.e., for plans submitted and approved before May 13, 2026), the City had adopted the 2015 editions of the International Building, Residential, Mechanical, Plumbing, Fuel Gas, Existing Building, Swimming Pool and Spa, and Property Maintenance Codes, plus the 2015 International Fire Code and 2014 NFPA 70 National Electrical Code, per the former Benson City Code Chapter 7, Section 7-1-1 (Resolution 36-2017). Source: City of Benson Building Department page (Wayback Machine capture, November 24, 2025) and City Code of the City of Benson, Arizona (posting updated April 2023).; Manufactured homes, mobile homes, and factory-built buildings: the City of Benson has an Inspection Services Agreement with the Arizona Department of Housing (ADOH), effective May 3, 2021 for a five-year term, under which the City (as ADOH's local enforcement agency) monitors and enforces ADOH's installation standards (A.R.S. § 41-4004(A)(4); A.A.C. R4-34-102, R4-34-204, R4-34-606, R4-34-801) for manufactured home, mobile home, and factory-built building installations within city limits, including setback and tie-down inspections. Source: Resolution 11-2021 and attached Inspection Services Agreement Between Arizona Department of Housing and City of Benson.; ICC A117.1-2017 Standard and Commentary (Accessible and Usable Buildings and Facilities) is referenced by the City as its accessibility standard, in addition to the federal ADA framework. Source: City of Benson Building Department page.. Local amendments apply — see the Benson overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Benson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.