Residential Solar Photovoltaic (PV) Permit in Avondale, Arizona

Required for installation of rooftop residential solar photovoltaic systems in Avondale. Governed by the City's dedicated Solar Plan Review Checklist (rev. 12/23/25), A.R.S. § 9-468 (solar construction permit standards), and the 2023 NEC as adopted and amended by the City of Avondale. Applications are submitted via the Avondale Citizen Portal under Application Type 'Solar'.

Verified 2026-07-06 · Source

When you need this permit

  • Plans must list the current adopted codes in force (2024 IRC/IBC/IFC and 2023 NEC) and indicate scale/north direction on the site plan
  • Photovoltaic installation location must be shown on construction plans, including the roof plan and elevations, with skylight locations and access indicated, per A.R.S. § 9-468
  • Mounting/racking details, structural calculations, and manufacturer cut sheets must accompany plans; a structural engineer's design may still be required
  • Electrical diagrams must include one-line or three-line diagrams; inverter cut sheets/listings required for DC-to-AC conversions
  • A 3-foot wide clear pathway must be maintained around the array for residential installations (6 feet for commercial)
  • A licensed structural engineer's approval is required when the building is more than 30 years old, or when the combined additional roof weight exceeds 5 lbs per square foot
  • Fences and retaining walls associated with a solar installation require a separate permit — not covered under the solar permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Solar Photovoltaic Power Systems — New InstallationCity of Avondale FY2026 Rates and Fees Schedule, Solar category, Resolution 1045-0725, effective 9/1/2025
$230.00
Residential Solar Photovoltaic Power Systems — ModificationCity of Avondale FY2026 Rates and Fees Schedule, Solar category, Resolution 1045-0725
$185.00
Commercial Solar Photovoltaic Power Systems (New Installation or Modification)City of Avondale FY2026 Rates and Fees Schedule, Solar category, Resolution 1045-0725
Per Permit — Based on total project valuation (labor & materials), calculated using Building Permit Tiers A-H

Review timeline

Plan reviewAvondale’s published plan-review target
16–24 business days

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Avondale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final Solar PV

    SELECTXT code 670; panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified

See the full Avondale inspection guide — scheduling & re-inspection fees →

Tips

  • A.R.S. § 9-468 governs solar construction permit standards (required plan content, restrictions on requiring a professional engineer stamp unless justified in writing, and fee limitations tied to actual permit-issuance cost) but does NOT itself set a specific review-time-frame requirement — solar submittals fall under Avondale's general Building Division review timeline (16 business days 1st review, 8 subsequent) per the City's A.R.S. § 9-835 Development Services Review Timelines document, since no separate expedited solar-specific timeline document was found published by the City.
  • The Building Permit Application references 'Review times in accordance with SB 1598 Policy' near the Contractor Information section — this appears to reference Arizona solar-related permitting legislation; the operative statutory review-standard for solar plan content in Avondale's own Solar Plan Review Checklist is A.R.S. § 9-468.
  • MPU/Derate has its own SELECTXT inspection code (665) separate from the standard Final Solar PV inspection (670).

Frequently asked questions

Avondale requires a residential solar photovoltaic (pv) permit for: Plans must list the current adopted codes in force (2024 IRC/IBC/IFC and 2023 NEC) and indicate scale/north direction on the site plan; Photovoltaic installation location must be shown on construction plans, including the roof plan and elevations, with skylight locations and access indicated, per A.R.S. § 9-468; Mounting/racking details, structural calculations, and manufacturer cut sheets must accompany plans; a structural engineer's design may still be required; Electrical diagrams must include one-line or three-line diagrams; inverter cut sheets/listings required for DC-to-AC conversions; A 3-foot wide clear pathway must be maintained around the array for residential installations (6 feet for commercial); A licensed structural engineer's approval is required when the building is more than 30 years old, or when the combined additional roof weight exceeds 5 lbs per square foot; Fences and retaining walls associated with a solar installation require a separate permit — not covered under the solar permit. If your project isn't listed, confirm with City of Avondale Development Services Department — Building Services Division at 623-333-4000 before starting work.

$230.00 for a new installation, or $185.00 for a modification, per the City of Avondale FY2026 Rates and Fees Schedule (Solar category).

No separate expedited solar-specific review-timeline document is published by the City; solar submittals are covered by the City's general Building Division timeline under the A.R.S. § 9-835 Development Services Review Timelines document — 16 business days for first review, 8 business days for each subsequent review.

You'll need: Solar Plan Review Checklist; Building Permit Application. See the required-documents checklist on this page for details on each.

Avondale requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Rough Electrical, Final Solar PV. Schedule each through City of Avondale Development Services Department — Building Services Division (623-333-4000).

Apply through City of Avondale Development Services Department — Building Services Division at 11465 W. Civic Center Drive, Avondale, AZ 85323. Phone: 623-333-4000, email: buildingservices@avondaleaz.gov. Office hours: 7:00 AM – 6:00 PM (Building Services Division, per the City's Building Services Division page); City Hall / Development Services counter hours are Monday–Thursday 7:00 AM – 6:00 PM per the City's Contact Us footer (City Hall operates a compressed 4-day, 10-hour workweek). Applications are submitted electronically via the Avondale Citizen Portal (Accela Citizen Access). Building Official: Benjamin Carr (bcarr@avondaleaz.gov), per the 2025 Arizona Building Officials (AZBO) Directory.. Official information: https://avondaleaz.gov/government/departments/development-services/building-division/.

Avondale, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Avondale independently adopts and administers its own construction codes through its Development Services Department / Building Services Division; it does not defer permitting to Maricopa County. Source: City of Avondale Building Services Division page (avondaleaz.gov/government/departments/development-services/building-division/).; 2024 International Building Code (IBC), as published by the International Code Council, adopted by reference with City of Avondale amendments. Effective January 1, 2026 (per the City's 'Current Adopted Building Codes (effective January 1, 2026)' list). Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document ('Building-Code-Adoption-Final.pdf').; 2024 International Residential Code (IRC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document.; 2024 International Existing Building Code (IEBC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2023 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with City of Avondale amendments (note: electrical code cycle is one edition behind the 2024 ICC set), effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document (Avondale Amendments to the 2023 National Electrical Code).; 2024 International Mechanical Code (IMC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Plumbing Code (IPC), adopted by reference with City of Avondale amendments, effective January 1, 2026, including a burial-depth amendment to G2415.12/IFGC 404.12 and added stub-out/push-to-connect-valve provisions (P2605.1.1, P2605.1.2). Source: City of Avondale Building Code Adoption ordinance document.; 2024 International Fuel Gas Code (IFGC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Energy Conservation Code (IECC), adopted by reference with City of Avondale amendments, effective January 1, 2026 (Manual J design criteria: elevation 1,101 ft, latitude 34°, outdoor summer design dry-bulb 108°F, outdoor winter design dry-bulb 33°F). Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document.; 2024 International Property Maintenance Code (IPMC), adopted by reference, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Swimming Pool and Spa Code (ISPSC), adopted by reference with City of Avondale amendments (including an amended barrier-height provision requiring a minimum 60-inch/5-foot barrier height, up from the model code's 48 inches), effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document (Avondale Amendments to the 2024 ISPSC, Section 305.2.1); City of Avondale Swimming Pool Requirements handout (rev. 10.26.2023).; All work must be performed by a contractor licensed with the Arizona Registrar of Contractors (ROC), unless the property owner qualifies as an owner-builder under A.R.S. § 32-1121 (Building Permit Application, Standard Conditions and Applicant Certification, rev. 05.06.2026). Source: City of Avondale Building Permit Application.. Local amendments apply — see the Avondale overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avondale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.