EV Charger / EVSE Installation Permit in Avondale, Arizona

Avondale has no separate permit type, fee line, or application category for electric vehicle charging station (EVSE) installation. Installing a Level 2 (240V) home or commercial EV charger requires a standard Electrical Permit, governed by the 2023 NEC as adopted and amended by the City of Avondale, the same as any other new dedicated circuit or panel work.

Verified 2026-07-20 · Source

When you need this permit

  • A City of Avondale Electrical Permit is required to install a new dedicated circuit, receptacle, or hardwired connection for an EV charging station (Level 2/240V or commercial Level 3 equipment); this is the same permit type used for any new electrical circuit, not a distinct 'EV charger permit'
  • Governed by the 2023 NEC as adopted by the City of Avondale (no EVSE-specific local amendment was found in the City's Building Code Adoption ordinance document)
  • Per neighboring Maricopa County jurisdictions' common practice (e.g., Pima County), a permit is generally NOT required only where an existing 120V receptacle is used with a UL-listed cord-and-plug charger; new circuits or 240V hardwired installations require a permit — Avondale's own code adoption document does not publish an EVSE-specific exemption, so this should be confirmed with Avondale Building Services Division on a per-project basis
  • Apply via the Avondale Citizen Portal (Accela Citizen Access), Application Type 'Residential' or 'Commercial', Purpose of Work 'Electric'
  • Load calculations may be required by the Building Services Division for service-panel capacity review where the added EV circuit affects total service load

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit (covers EV charger/EVSE circuit installation — no distinct EV/EVSE fee line published)City of Avondale FY2026 Rates and Fees Schedule (effective 9/1/2025), Mechanical/Plumbing/Electrical (MPE) category, Resolution 1045-0725. The published fee schedule was checked directly and contains no separate 'EV charger', 'EVSE', or 'electric vehicle charging station' line item; EV charging circuit work falls under the general flat Electrical Permit fee.
$112.00 flat
Application Processing FeeCity of Avondale FY2026 Rates and Fees Schedule, Building Division Fees, Resolution 1045-0725
$102.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Avondale building department
~16–24 business days

How long did your EV Charger / EVSE Installation Permit permit actually take in Avondale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electric / Final Electrical

    Same inspection process as any electrical permit: SELECTXT code 220 (rough) and 620 (final electrical & clearance to connect)

See the full Avondale inspection guide — scheduling & re-inspection fees →

Tips

  • Avondale does not publish a dedicated EV charger/EVSE permit category, fee, or checklist — homeowners and contractors should apply for a standard Electrical Permit and specify EV charging circuit work in the application scope.
  • Confirmed directly against the City's FY2026 Rates and Fees Schedule PDF and Building Code Adoption ordinance document: neither contains the terms 'EV', 'electric vehicle', 'EVSE', or 'charging station'.
  • The City operates a public dual-port ChargePoint station at the Civic Center Library (11350 Civic Center Dr), unrelated to private-installation permitting.

Frequently asked questions

Yes, in most cases — installing a new dedicated circuit or hardwired connection for a Level 2 or commercial EV charger requires a standard City of Avondale Electrical Permit ($112 flat fee), governed by the 2023 NEC. The City does not publish a separate EV-specific permit category or fee.

In Avondale, the published Electrical Permit (covers EV charger/EVSE circuit installation — no distinct EV/EVSE fee line published) is: $112.00 flat. Additional published fees: Application Processing Fee — $102.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for an ev charger / evse installation permit in Avondale typically runs 16–24 business days. This is an estimate, not a published figure — confirm current review times with City of Avondale Development Services Department — Building Services Division at 623-333-4000.

You'll need: Building/Electrical Permit Application. See the required-documents checklist on this page for details on each.

Avondale requires 1 inspection(s) for an ev charger / evse installation permit, in order: Rough Electric / Final Electrical. Schedule each through City of Avondale Development Services Department — Building Services Division (623-333-4000).

Apply through City of Avondale Development Services Department — Building Services Division at 11465 W. Civic Center Drive, Avondale, AZ 85323. Phone: 623-333-4000, email: buildingservices@avondaleaz.gov. Office hours: 7:00 AM – 6:00 PM (Building Services Division, per the City's Building Services Division page); City Hall / Development Services counter hours are Monday–Thursday 7:00 AM – 6:00 PM per the City's Contact Us footer (City Hall operates a compressed 4-day, 10-hour workweek). Applications are submitted electronically via the Avondale Citizen Portal (Accela Citizen Access). Building Official: Benjamin Carr (bcarr@avondaleaz.gov), per the 2025 Arizona Building Officials (AZBO) Directory.. Official information: https://avondaleaz.gov/government/departments/development-services/building-division/.

Avondale, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Avondale independently adopts and administers its own construction codes through its Development Services Department / Building Services Division; it does not defer permitting to Maricopa County. Source: City of Avondale Building Services Division page (avondaleaz.gov/government/departments/development-services/building-division/).; 2024 International Building Code (IBC), as published by the International Code Council, adopted by reference with City of Avondale amendments. Effective January 1, 2026 (per the City's 'Current Adopted Building Codes (effective January 1, 2026)' list). Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document ('Building-Code-Adoption-Final.pdf').; 2024 International Residential Code (IRC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document.; 2024 International Existing Building Code (IEBC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2023 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with City of Avondale amendments (note: electrical code cycle is one edition behind the 2024 ICC set), effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document (Avondale Amendments to the 2023 National Electrical Code).; 2024 International Mechanical Code (IMC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Plumbing Code (IPC), adopted by reference with City of Avondale amendments, effective January 1, 2026, including a burial-depth amendment to G2415.12/IFGC 404.12 and added stub-out/push-to-connect-valve provisions (P2605.1.1, P2605.1.2). Source: City of Avondale Building Code Adoption ordinance document.; 2024 International Fuel Gas Code (IFGC), adopted by reference with City of Avondale amendments, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Energy Conservation Code (IECC), adopted by reference with City of Avondale amendments, effective January 1, 2026 (Manual J design criteria: elevation 1,101 ft, latitude 34°, outdoor summer design dry-bulb 108°F, outdoor winter design dry-bulb 33°F). Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document.; 2024 International Property Maintenance Code (IPMC), adopted by reference, effective January 1, 2026. Source: City of Avondale Building Services Division page.; 2024 International Swimming Pool and Spa Code (ISPSC), adopted by reference with City of Avondale amendments (including an amended barrier-height provision requiring a minimum 60-inch/5-foot barrier height, up from the model code's 48 inches), effective January 1, 2026. Source: City of Avondale Building Services Division page; City of Avondale Building Code Adoption ordinance document (Avondale Amendments to the 2024 ISPSC, Section 305.2.1); City of Avondale Swimming Pool Requirements handout (rev. 10.26.2023).; All work must be performed by a contractor licensed with the Arizona Registrar of Contractors (ROC), unless the property owner qualifies as an owner-builder under A.R.S. § 32-1121 (Building Permit Application, Standard Conditions and Applicant Certification, rev. 05.06.2026). Source: City of Avondale Building Permit Application.. Local amendments apply — see the Avondale overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avondale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.