Avondale building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Avondale, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 11465 W. Civic Center Drive, Avondale, AZ 85323
- Phone
- 623-333-4000
- Office hours
- 7:00 AM – 6:00 PM (Building Services Division, per the City's Building Services Division page); City Hall / Development Services counter hours are Monday–Thursday 7:00 AM – 6:00 PM per the City's Contact Us footer (City Hall operates a compressed 4-day, 10-hour workweek). Applications are submitted electronically via the Avondale Citizen Portal (Accela Citizen Access). Building Official: Benjamin Carr (bcarr@avondaleaz.gov), per the 2025 Arizona Building Officials (AZBO) Directory.
- Website
- Official site
Published scheduling rules
- Per the City of Avondale Development Services Review Timelines (A.R.S. § 9-835 compliance document, revised 10/31/2024, effective 06/10/2024), Building Division applications get 16 business days for 1st review and 8 business days for each subsequent review; the City's business week is Monday–Thursday. Applications received before 3 p.m. start the clock that day; after 3 p.m. the clock starts the next business day. (Residential Building Permit (New Construction))
- Inspections are scheduled via SELECTXT (text (833) 324-1348 with SCHEDULE/CANCEL/RESCHEDULE/RESULTS) or the Selectron Building Inspection website; next-business-day inspections must be requested by 4:00 p.m. Inspections run Monday–Thursday 7:00 a.m.–4:00 p.m., closed Fridays and City holidays. (Residential Building Permit (New Construction))
- The City's A.R.S. § 9-835 Development Services Review Timelines document (revised 10/31/2024, effective 06/10/2024) sets a SINGLE flat Building Division timeline of 16 business days for 1st review and 8 business days for each subsequent review — Avondale does not publish the tiered 'Residential Standard vs. Residential Misc.' timeline categories seen in some neighboring cities' guideline documents. The City's business week for this calculation is Monday–Thursday, and applications received after 3 p.m. start the clock the next business day. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation (Layout/Setbacks, Footing/Ufer, Stem, Pre-Slab)
SELECTXT codes 100-125; required before concrete pour
- 2
Underground/Soils (Under-Slab Plumbing/Electrical, UG Building Sewer/Water/Electric/Gas Service)
SELECTXT codes 140-180
- 3
Rough (Shear Wall, Roof Truss/Nail, Mechanical, Plumbing, Electric, Framing)
SELECTXT codes 200-245, before walls are closed
- 4
Wall Cover / Insulation
SELECTXT codes 250-340: window/door flashing, water-resistant barrier, drywall/lath nail, insulation
- 5
Final Combination (Mechanical, Plumbing, Electrical, Insulation, Building, Gas)
SELECTXT code 640; Certificate of Occupancy issued after approval
Applies to: Certificate of Occupancy / Change of Occupancy Permit
- 1
Final Building / Final Combination
Verifies any permitted work (if applicable) against approved plans; SELECTXT code 630/640 per this record's other Building Division entries
- 2
Engineering Final (On-Site/Off-Site)
Engineering Division sign-off on the Certificate of Occupancy Sign-Off Sheet; approval provided is limited to C of O processing and does not release separate Engineering permit/subdivision-improvement obligations
- 3
Fire & Medical Final (Site and Occupiable Area)
Coordinated at (623) 333-6020 per the Certificate of Occupancy Sign-Off Sheet
Applies to: Plumbing Permit
- 1
Under-Slab Plumbing / UG Building Sewer / UG Water Service
SELECTXT codes 150, 165, 170; before concrete pour — verify pipe slope, materials, cleanouts
- 2
Rough Plumbing
SELECTXT code 215; after pipes installed, before walls closed
- 3
Final Plumbing
SELECTXT code 615; fixtures connected, no leaks
Applies to: Residential Addition / Remodel / ADU Permit
- 1
Foundation/Footing
Required before concrete pour for additions/ADUs (SELECTXT 100-125)
- 2
Rough (Framing, Electrical, Plumbing, Mechanical)
SELECTXT 200-245
- 3
Final Combination
SELECTXT 640; Certificate of Occupancy required before the ADU may legally be occupied
Applies to: Swimming Pool / Spa Permit
- 1
Underground/Soils
SELECTXT code 140/150-180 combination as applicable for pool plumbing/electrical rough-in before gunite/shotcrete
- 2
Fence (Barrier)
SELECTXT code 130 (rough) and 650 (final fence); verifies the 5-foot minimum barrier height and self-closing/latching gate requirements before the pool holds water unsupervised
- 3
Final Building
SELECTXT code 630; completed pool/spa verified against approved plans and ISPSC barrier requirements
Applies to: Automatic Fire Sprinkler System Permit
- 1
Rough / Underground Sprinkler Piping
Verifies pipe sizing, hangers, and underground supply piping before concealment or backfill
- 2
Final Fire Sprinkler / Fire & Medical Final (Site and Occupiable Area)
Final Fire & Medical sign-off, coordinated at (623) 333-6020 per the City's Certificate of Occupancy Sign-Off Sheet; required before a Certificate of Occupancy can be issued
Applies to: Electrical Permit
- 1
Rough Electric
SELECTXT code 220 (residential) / 220-235 (commercial: includes Service Entrance Section, Distribution Panels, Other Electric); wiring and panel connections before walls are closed
- 2
Final Electrical & Clearance to Connect
SELECTXT code 620; devices installed and panel labeled, protections verified per 2023 NEC
Applies to: Fire Alarm, Detection & Notification System Permit
- 1
Rough Wiring / Device Placement
Verifies conductor type, device spacing, and panel/wiring installation before concealment
- 2
Final Fire Alarm Test / Fire & Medical Final (Site and Occupiable Area)
Functional alarm test and final Fire & Medical sign-off, coordinated at (623) 333-6020 per the City's Certificate of Occupancy Sign-Off Sheet; required before a Certificate of Occupancy can be issued
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical (HVAC)
SELECTXT code 210; ductwork and equipment placement before walls closed
- 2
Final Mechanical HVAC
SELECTXT code 610; equipment operational, clearances and combustion air verified
Applies to: Residential Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final Solar PV
SELECTXT code 670; panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified
Final inspection only: Demolition Permit, EV Charger / EVSE Installation Permit, Re-Roofing Permit, Sign Permit (Permanent / Temporary)
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avondale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Avondale building permits
Get alerts for Avondale
We'll email you when Avondale's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.