EV Charger / EVSE Permit in Apache Junction, Arizona

Required for installation of a residential electric vehicle charging circuit in Apache Junction, governed by the 2017 National Electrical Code (NEC). The City's electrical fee table (City Code Vol. I, Ch. 4, Art. 4-4, § 4-4-1) has no EV-charger/EVSE-specific line item — an EV charger circuit added to an existing dwelling is billed under the 'Electrical Repair/Branch Circuit or Lighting Additions, Residential' category, and a new/upgraded service for the charger would instead fall under the service-upgrade fee tiers.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the new EV charger branch circuit
  • Governed by the 2017 NEC as adopted by the City of Apache Junction
  • Apply via the MyGovernmentOnline (MGO) online permit system
  • If the install also requires a new or upgraded electrical service, the applicable service-upgrade fee tier applies in addition to (or instead of) the branch-circuit fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Repair/Branch Circuit or Lighting Additions, Residential (1 inspection) — covers a standalone EV charger circuit (no EV-specific line item published)Apache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1, Electrical
$120 per dwelling unit (additional inspections $75 each)
New/Replace/Upgrade 1-2 Family Residential Service, not greater than 200 amps (if the EV charger requires a service upgrade)Apache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$200 per service
Mechanical, Electrical and Plumbing (stand-alone permit) Technology FeeApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1, Technology and GIS Fees
2% of permit fee

Review timeline

Plan reviewApache Junction’s published plan-review target
0–20 business days

How long did your EV Charger / EVSE Permit permit actually take in Apache Junction?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring and box placement before walls are closed

  2. 2

    Final

    Charger installed, circuit verified, unit energized

See the full Apache Junction inspection guide — scheduling & re-inspection fees →

Tips

  • Apache Junction has no distinct EV charger/EVSE fee — a standalone EV charger branch circuit is billed under 'Electrical Repair/Branch Circuit or Lighting Additions, Residential' at $120 per dwelling unit, the same category used for other branch-circuit additions.
  • If the EV charger requires a new or upgraded electrical service, the service-upgrade fee tiers ($200 flat up to 200 amps, or $1.00/amp with a $220 minimum above 200 amps) apply instead of or in addition to the branch-circuit fee.
  • Simple, like-for-like scopes may be processed over-the-counter; scopes requiring plan review (larger service upgrades) follow the standard 15-20 business day first-review timeline.

Frequently asked questions

Apache Junction requires an ev charger / evse permit for: Electrical permit required for the new EV charger branch circuit; Governed by the 2017 NEC as adopted by the City of Apache Junction; Apply via the MyGovernmentOnline (MGO) online permit system; If the install also requires a new or upgraded electrical service, the applicable service-upgrade fee tier applies in addition to (or instead of) the branch-circuit fee. If your project isn't listed, confirm with City of Apache Junction Development Services Department — Division of Building Safety and Inspection at 480-474-5156 before starting work.

No EV-charger-specific fee is published. A standalone EV charger branch circuit is billed under the 'Electrical Repair/Branch Circuit or Lighting Additions, Residential' category at $120 per dwelling unit, per Apache Junction City Code Vol. I, Ch. 4, Art. 4-4, § 4-4-1. If the install requires a new/upgraded electrical service, the service-upgrade fee tiers apply instead.

Apache Junction's published plan-review target for an ev charger / evse permit is 0–20 business days.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Apache Junction requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through City of Apache Junction Development Services Department — Division of Building Safety and Inspection (480-474-5156).

Apply through City of Apache Junction Development Services Department — Division of Building Safety and Inspection at 300 E. Superstition Blvd. (Building D), Apache Junction, AZ 85119. Phone: 480-474-5156, email: buildingpermits@apachejunctionaz.gov. Office hours: Building and Safety Manager/Building Official: Adrian Alegria (buildingpermits@apachejunctionaz.gov, 480-474-5156). All building permit applications must be submitted electronically through the MyGovernmentOnline (MGO) online permit system; a public kiosk with an 11x17 flat scanner is available in the Development Services Lobby at the city complex, 300 E. Superstition Blvd. Building D, for applicants who need accommodation. Division main line 480-982-8002; inspections may be scheduled by phone at 480-474-5101 or via the MGO customer portal. Source: City of Apache Junction Division of Building Safety and Inspection staff directory page; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024).. Official information: https://www.apachejunctionaz.gov/622/Permits.

Apache Junction, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Apache Junction independently adopts and administers its own construction codes through its Development Services Department / Division of Building Safety and Inspection. Source: City of Apache Junction Division of Building Safety and Inspection (apachejunctionaz.gov/85/Building-Safety-and-Inspection); Apache Junction City Code, Volume I, Chapter 7 (Buildings).; 2018 International Building Code (IBC), formally adopted by the Apache Junction City Council on June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Apache Junction City Code, Volume I, Article 7-2: Building Code, § 7-2-2 Amendments to the 2018 International Building Code). Source: City of Apache Junction 'Currently Adopted Building Codes' notice (Division of Building Safety and Inspection, 300 E. Superstition Blvd.).; 2018 International Residential Code (IRC), adopted June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Article 7-4: Residential Code), including a City-completed Table R301.2(1) Climatic and Geographic Design Criteria and amendments to R301.5 (Live Loads), R302.1(1), R302.2.6, and R303 (mandatory heating/cooling). Confirmed as the applicable code on the City's own 'New Residential Construction (and Additions) Building Application Guide' coversheet requirement ('Applicable code 2018 IRC'). Source: City of Apache Junction 'Currently Adopted Residential Code & Design Criteria' notice; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024), p.2.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted June 18, 2019, effective July 18, 2019 — one edition behind the 2018 ICC set (the City has not since adopted the 2020 or 2023 NEC per the City's own currently-adopted-codes notice and FAQ page). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; City of Apache Junction Building Division FAQ (apachejunctionaz.gov/faq.aspx?TID=20).; 2018 International Plumbing Code (IPC), adopted June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Article 7-6: Plumbing Code, § 7-6-2 Amendments to the 2018 International Plumbing Code). Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Mechanical Code (IMC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Fuel Gas Code (IFGC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Existing Building Code (IEBC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Energy Conservation Code (IECC), adopted June 18, 2019, effective July 18, 2019, governs energy-efficiency requirements for new residential and commercial construction (Manual J/D/S calculations required per the City's Residential Building Application Guide). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted June 18, 2019, effective July 18, 2019, governs residential and public/semi-public pool and spa construction. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Fire Code (IFC), adopted as the City's uniform fire code (Article 7-1 references the 'Technical Codes' collectively); administered in coordination with the Building Safety and Inspection Division. Source: Apache Junction City Code, Volume I, Article 7-1: Division of Building Safety and Inspection Administrative Code.; Accessibility: 2010 ADA Standards for Accessible Design, as published by the U.S. Department of Justice, Civil Rights Division (appendices B and D to 36 CFR 1191 (2009) and 28 CFR part 35.151 (2011) for public entities; 28 CFR 36.401-36.406 (2011) for places of public accommodation and commercial facilities), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; Fee schedules were revised in conjunction with the 2018/2019 code adoption, effective July 1, 2019, and the Development Services Fees (Apache Junction City Code, Volume I, Chapter 4, Article 4-4) were most recently revised October 31, 2022. The ICC codes' own fee/valuation sections are superseded for practical billing purposes by Article 4-4, which is the City's operative fee authority (though commercial valuation itself is still calculated per the ICC Building Valuation Data table). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; Apache Junction City Code, Vol. I, Chapter 4, Article 4-4: Development Services Fees (rev. 10/31/22).. Local amendments apply — see the Apache Junction overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Apache Junction building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.