Required for electrical installation, alteration, or repair work in Apache Junction, governed by the 2017 National Electrical Code (NEC) as adopted by the City. Covers meter clearances, service upgrades, panel work, generators, and residential photovoltaic systems.

Verified 2026-07-06 · Source

When you need this permit

  • Electrical permit required for meter clearances, new/replace/upgrade electrical service, panel derates, generators, and photovoltaic system installation
  • Governed by the 2017 NEC as adopted by the City of Apache Junction (per Article 7-1, § 7-1-6 and the Currently Adopted Building Codes notice)
  • Trade-only electrical permits (mechanical/HVAC, electrical, or plumbing) each have an 'over-the-counter' type and a 'review required' type per the City's Trade Permit Guide
  • Minor electrical work is exempt from a permit per Article 7-1, § 7-1-6(B)(2): e.g., repair/replacement of fixed motors/transformers/appliances of the same type and rating, re-installation of attachment-plug receptacles, replacement of branch-circuit overcurrent devices of the required capacity in the same location — but installation of an interconnected photovoltaic system or battery system always requires a permit
  • Apply via the MyGovernmentOnline (MGO) online permit system

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Meter Clearance, Existing Service — ResidentialApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1, Electrical
$100 per service
New/Replace/Upgrade 1-2 Family Residential Service, not greater than 200 ampsApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$200 per service
New/Replace/Upgrade 1-2 Family Residential Service, greater than 200 ampsApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$1.00 per amp ($220 minimum)
Electrical Panel De-rate, ResidentialApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$100 per service
Electrical Repair/Branch Circuit or Lighting Additions, Residential (1 inspection)Apache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$120 per dwelling unit (additional inspections $75 each)
Generator, Permanent Residential (includes transfer switch)Apache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1
$200 per dwelling unit
Mechanical, Electrical and Plumbing (stand-alone permit) Technology FeeApache Junction City Code, Vol. I, Ch. 4, Art. 4-4, § 4-4-1, Technology and GIS Fees
2% of permit fee

Review timeline

Plan reviewApache Junction’s published plan-review target
0–20 business days

How long did your Electrical Permit permit actually take in Apache Junction?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2017 NEC

See the full Apache Junction inspection guide — scheduling & re-inspection fees →

Tips

  • The City's Trade Permit Guide distinguishes an 'over-the-counter' track (same-day/no plan review) from a 'review required' track for mechanical/HVAC, electrical, and plumbing permits — simple meter clearances and like-for-like replacements are typically over-the-counter, while new service upgrades, panel work, and PV systems needing engineering review go through the standard plan-review queue.
  • Where plan review is required, the same review timeline as the New Residential Construction Guide applies: allow 3-4 weeks (15-20 business days) for first review and 1-2 weeks (5-10 business days) for subsequent reviews — hence the 0-20 business day range depending on whether the specific scope is over-the-counter or review-required.
  • Installation of an interconnected photovoltaic system or battery system always requires an electrical permit, even though many other minor electrical repairs are permit-exempt under Article 7-1, § 7-1-6(B)(2).

Frequently asked questions

Apache Junction requires an electrical permit for: Electrical permit required for meter clearances, new/replace/upgrade electrical service, panel derates, generators, and photovoltaic system installation; Governed by the 2017 NEC as adopted by the City of Apache Junction (per Article 7-1, § 7-1-6 and the Currently Adopted Building Codes notice); Trade-only electrical permits (mechanical/HVAC, electrical, or plumbing) each have an 'over-the-counter' type and a 'review required' type per the City's Trade Permit Guide; Minor electrical work is exempt from a permit per Article 7-1, § 7-1-6(B)(2): e.g., repair/replacement of fixed motors/transformers/appliances of the same type and rating, re-installation of attachment-plug receptacles, replacement of branch-circuit overcurrent devices of the required capacity in the same location — but installation of an interconnected photovoltaic system or battery system always requires a permit; Apply via the MyGovernmentOnline (MGO) online permit system. If your project isn't listed, confirm with City of Apache Junction Development Services Department — Division of Building Safety and Inspection at 480-474-5156 before starting work.

In Apache Junction, the published Electrical Meter Clearance, Existing Service — Residential is: $100 per service. Additional published fees: New/Replace/Upgrade 1-2 Family Residential Service, not greater than 200 amps — $200 per service; New/Replace/Upgrade 1-2 Family Residential Service, greater than 200 amps — $1.00 per amp ($220 minimum); Electrical Panel De-rate, Residential — $100 per service; Electrical Repair/Branch Circuit or Lighting Additions, Residential (1 inspection) — $120 per dwelling unit (additional inspections $75 each); Generator, Permanent Residential (includes transfer switch) — $200 per dwelling unit; Mechanical, Electrical and Plumbing (stand-alone permit) Technology Fee — 2% of permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Straightforward meter clearances and like-for-like replacements are typically issued over-the-counter with no plan-review wait. Electrical work requiring plan review (new/upgraded service, panel work, PV systems) follows the City's standard review timeline of 3-4 weeks (15-20 business days) for first review and 1-2 weeks (5-10 business days) for subsequent reviews, per the City's New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024), which the Building Safety and Inspection Division applies uniformly across permit types requiring plan review.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Apache Junction requires 2 inspection(s) for an electrical permit, in order: Rough-In, Final. Schedule each through City of Apache Junction Development Services Department — Division of Building Safety and Inspection (480-474-5156).

Apply through City of Apache Junction Development Services Department — Division of Building Safety and Inspection at 300 E. Superstition Blvd. (Building D), Apache Junction, AZ 85119. Phone: 480-474-5156, email: buildingpermits@apachejunctionaz.gov. Office hours: Building and Safety Manager/Building Official: Adrian Alegria (buildingpermits@apachejunctionaz.gov, 480-474-5156). All building permit applications must be submitted electronically through the MyGovernmentOnline (MGO) online permit system; a public kiosk with an 11x17 flat scanner is available in the Development Services Lobby at the city complex, 300 E. Superstition Blvd. Building D, for applicants who need accommodation. Division main line 480-982-8002; inspections may be scheduled by phone at 480-474-5101 or via the MGO customer portal. Source: City of Apache Junction Division of Building Safety and Inspection staff directory page; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024).. Official information: https://www.apachejunctionaz.gov/622/Permits.

Apache Junction, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Apache Junction independently adopts and administers its own construction codes through its Development Services Department / Division of Building Safety and Inspection. Source: City of Apache Junction Division of Building Safety and Inspection (apachejunctionaz.gov/85/Building-Safety-and-Inspection); Apache Junction City Code, Volume I, Chapter 7 (Buildings).; 2018 International Building Code (IBC), formally adopted by the Apache Junction City Council on June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Apache Junction City Code, Volume I, Article 7-2: Building Code, § 7-2-2 Amendments to the 2018 International Building Code). Source: City of Apache Junction 'Currently Adopted Building Codes' notice (Division of Building Safety and Inspection, 300 E. Superstition Blvd.).; 2018 International Residential Code (IRC), adopted June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Article 7-4: Residential Code), including a City-completed Table R301.2(1) Climatic and Geographic Design Criteria and amendments to R301.5 (Live Loads), R302.1(1), R302.2.6, and R303 (mandatory heating/cooling). Confirmed as the applicable code on the City's own 'New Residential Construction (and Additions) Building Application Guide' coversheet requirement ('Applicable code 2018 IRC'). Source: City of Apache Junction 'Currently Adopted Residential Code & Design Criteria' notice; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024), p.2.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted June 18, 2019, effective July 18, 2019 — one edition behind the 2018 ICC set (the City has not since adopted the 2020 or 2023 NEC per the City's own currently-adopted-codes notice and FAQ page). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; City of Apache Junction Building Division FAQ (apachejunctionaz.gov/faq.aspx?TID=20).; 2018 International Plumbing Code (IPC), adopted June 18, 2019, effective July 18, 2019, with City of Apache Junction amendments (Article 7-6: Plumbing Code, § 7-6-2 Amendments to the 2018 International Plumbing Code). Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Mechanical Code (IMC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Fuel Gas Code (IFGC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Existing Building Code (IEBC), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Energy Conservation Code (IECC), adopted June 18, 2019, effective July 18, 2019, governs energy-efficiency requirements for new residential and commercial construction (Manual J/D/S calculations required per the City's Residential Building Application Guide). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; New Residential Construction (and Additions) Building Application Guide (rev. 03/11/2024).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted June 18, 2019, effective July 18, 2019, governs residential and public/semi-public pool and spa construction. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; 2018 International Fire Code (IFC), adopted as the City's uniform fire code (Article 7-1 references the 'Technical Codes' collectively); administered in coordination with the Building Safety and Inspection Division. Source: Apache Junction City Code, Volume I, Article 7-1: Division of Building Safety and Inspection Administrative Code.; Accessibility: 2010 ADA Standards for Accessible Design, as published by the U.S. Department of Justice, Civil Rights Division (appendices B and D to 36 CFR 1191 (2009) and 28 CFR part 35.151 (2011) for public entities; 28 CFR 36.401-36.406 (2011) for places of public accommodation and commercial facilities), adopted June 18, 2019, effective July 18, 2019. Source: City of Apache Junction 'Currently Adopted Building Codes' notice.; Fee schedules were revised in conjunction with the 2018/2019 code adoption, effective July 1, 2019, and the Development Services Fees (Apache Junction City Code, Volume I, Chapter 4, Article 4-4) were most recently revised October 31, 2022. The ICC codes' own fee/valuation sections are superseded for practical billing purposes by Article 4-4, which is the City's operative fee authority (though commercial valuation itself is still calculated per the ICC Building Valuation Data table). Source: City of Apache Junction 'Currently Adopted Building Codes' notice; Apache Junction City Code, Vol. I, Chapter 4, Article 4-4: Development Services Fees (rev. 10/31/22).. Local amendments apply — see the Apache Junction overview page for the full list.