Electrical Permit in Casa Grande, Arizona
Required for electrical installation, alteration, or repair work in Casa Grande, governed by the 2017 National Electrical Code (NEC) as adopted and amended by the City. Billed as a flat fee per the Consolidated Fee Schedule's 'Electrical, Mechanical, Plumbing Permit' category.
Verified 2026-07-06 · Source
When you need this permit
- Electrical permit required for panel work, service changes, wiring, and other hard-wired electrical work
- Governed by the 2017 NEC as adopted by the City of Casa Grande
- Arc-fault and tamper-resistant outlet protection required at most locations per the 2017 NEC
- Apply at the Development Center, 510 E. Florence Blvd.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified per 2017 NEC
See the full Casa Grande inspection guide — scheduling & re-inspection fees →
Tips
- Electrical (and mechanical/plumbing) single-trade permits are classified 'Single Trade (MPE Permit)' under the Miscellaneous category on the City's A.R.S. § 9-835 review timeframe chart: 2-business-day Administrative Completeness Review, plus 10 business days each for Initial and Resubmittal Substantive Review, for a 24-business-day Over-All Timeframe maximum — though simple single-trade permits are frequently issued much faster over the counter once completeness review clears (2 business days).
- Residential electrical, mechanical, and plumbing trade permits are billed as one consolidated flat fee ($75) rather than separately itemized dollar amounts per trade.
- A gas/electric reconnect inspection ($40) is billed separately from the trade permit fee itself.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casa Grande
Electrical Permit in other cities
Compare electrical permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Casa Grande project checklist
Describe your project once and get every permit, document, and fee it triggers in Casa Grande — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →