Re-Roofing Permit in Casa Grande, Arizona
Required for residential and commercial re-roofing in Casa Grande, governed by the 2018 IBC/IRC roofing provisions. The City offers both an in-person-inspection track and a lower-cost drone-inspection track, each billed as a flat fee inclusive of plan review.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for re-roofing (Casa Grande does not publish a like-for-like no-permit exemption comparable to some other Arizona cities; confirm scope-specific exemptions directly with the Development Center)
- Maximum of two layers of roof covering permitted; no more than two total layers of any roofing material may be applied
- Ice barrier underlayment is not required per the City's adopted design criteria (consistent with Casa Grande's desert climate — no ice-shield requirement)
- Applicant chooses between an in-person building inspection track or a drone building inspection track at time of permit application; both include plan review in the flat fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Roof Inspection
Verifies sheathing, underlayment, and proposed roofing material/weight before final cover; conducted either in-person or via drone depending on the permit track selected
See the full Casa Grande inspection guide — scheduling & re-inspection fees →
Tips
- Casa Grande's fee schedule publishes two distinct re-roof permit tracks at different flat fees: standard in-person inspection ($125, includes plan review) versus drone inspection ($400, includes plan review) — the drone track costs more but may offer scheduling flexibility for hard-to-access roofs.
- Re-roofing is capped at a maximum of two layers of roof covering per the City's adopted design criteria; ice barrier underlayment is not required given the local desert climate (0 freezing index value).
- Review timeframe is drawn from the City's A.R.S. § 9-835 chart; re-roofing without other structural scope is treated as a residential building permit item, tracking the Single/Two-Family Residential 'Standard Plan' timeframe (2-business-day completeness + 20/20 business-day substantive review = 44 business days maximum) unless the Development Center processes it as a faster Miscellaneous/Single Trade item at the counter — confirm the specific track when applying, since the fee schedule treats it as a flat-fee Building Permit Fee line rather than a Miscellaneous single-trade line.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Casa Grande's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Casa Grande yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Casa Grande lands. Privacy.
Other permits in Casa Grande
Re-Roofing Permit in other cities
Compare re-roofing permit fees across Arizona →
Look up this fee in a different city →