Mechanical / HVAC Permit — Casa Grande, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://casagrandeaz.gov/231/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Mechanical / HVAC Permit in Casa Grande, Arizona
Required for heating, ventilation, and air conditioning installations in Casa Grande, governed by the 2018 International Mechanical Code (IMC) as adopted and amended by the City. New and replacement HVAC equipment must be sized per ACCA Manual J & S with minimum efficiency thresholds published by the Building Department.
Verified 2026-07-06 · Source
When you need this permit
- Mechanical permit required for installation, replacement, or relocation of HVAC equipment, furnaces, and ventilation systems
- Governed by the 2018 IMC as adopted by the City of Casa Grande
- New and replacement HVAC must be sized per ACCA Manual J & S: gas furnaces and boilers minimum 80% AFUE; air conditioners and heat pumps minimum 14 SEER
- Duct sizing/insulation per ACCA Manual D: R-8 within attics or exterior of building, R-6 within other portions of the building
- Attic/crawl space venting requires 1 sq ft of vent per 150 sq ft of space served
- Apply at the Development Center, 510 E. Florence Blvd.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified, efficiency ratings confirmed
See the full Casa Grande inspection guide — scheduling & re-inspection fees →
Tips
- Mechanical/HVAC single-trade permits fall under 'Single Trade (MPE Permit)' on the City's A.R.S. § 9-835 review timeframe chart: 2-business-day Administrative Completeness Review, plus 10 business days each for Initial and Resubmittal Substantive Review (24-business-day Over-All Timeframe maximum).
- Casa Grande's published minimum efficiency thresholds (80% AFUE gas furnace/boiler, 14 SEER AC/heat pump) are the City's own Building Department Residential Energy Efficiency Design Minimums, layered on top of the adopted 2018 IECC.
- Duct insulation values (R-8 attic/exterior, R-6 elsewhere per ACCA Manual D) should be confirmed on the plan cover sheet alongside the wall/ceiling/window/slab insulation values published in the Quick Codes handout.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casa Grande
Mechanical / HVAC Permit in other cities
Compare mechanical / hvac permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Casa Grande project checklist
Describe your project once and get every permit, document, and fee it triggers in Casa Grande — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →