EV Charger / EVSE Permit — Casa Grande, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://casagrandeaz.gov/231/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Casa Grande, Arizona
Casa Grande has no standalone EV-charger/EVSE permit type or fee line item. Installing electric vehicle charging equipment (e.g., a dedicated 240V Level 2 circuit or panel/service work to support a charger) is electrical work, governed by the 2017 National Electrical Code (NEC) as adopted by the City, and is billed under the same flat 'Electrical, Mechanical, Plumbing Permit' consolidated fee category documented in this file's own electrical-permit entry -- not a distinct EV-charger line item. The City's FY 2025-2026 Consolidated Fee Schedule and Building Department page were checked directly and contain no EV-charger, EVSE, or electric-vehicle-specific fee or process, and no evidence was found that Casa Grande participates in SolarAPP+ (gosolarapp.org) or another instant/automated EV-charger permitting platform as of this review.
Verified 2026-07-20 · Source
When you need this permit
- EV charger circuit installation is electrical work; apply at the Development Center, 510 E. Florence Blvd., using the standard Building/Electrical Permit Application
- Governed by the 2017 NEC as adopted by the City of Casa Grande, including arc-fault and tamper-resistant outlet protection requirements at most locations
- Billed under the flat consolidated 'Electrical, Mechanical, Plumbing Permit' fee category (no distinct EV-charger tier), same as any other single-trade electrical permit
- Classified as a 'Single Trade (MPE Permit)' under the Miscellaneous category on the City's A.R.S. Section 9-835 review timeframe chart, same as general electrical permits
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
New circuit wiring, box placement, and panel connections before walls are closed, if applicable
- 2
Final
Charger unit installed, devices connected, protections verified per 2017 NEC
See the full Casa Grande inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate EV-charger fee category in Casa Grande -- an EV charger circuit is billed as the same flat $75 residential / $300 commercial consolidated Electrical, Mechanical, Plumbing Permit fee used for any single-trade electrical work.
- Simple single-trade permits like an EV charger circuit are frequently issued much faster over the counter once completeness review clears (as fast as 2 business days), rather than taking the full 24-business-day maximum timeframe.
- No SolarAPP+ or other automated instant-permitting platform was found for Casa Grande as of this review; do not assume an online instant-issue option exists for EV chargers here.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casa Grande
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Casa Grande project checklist
Describe your project once and get every permit, document, and fee it triggers in Casa Grande — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →