Required for new single-family and two-family dwelling construction in the City of Casa Grande. Reviewed against the 2018 IRC and City of Casa Grande amendments under Title 15, plus the City's Building and Technical Administrative Code (CG-BTAC, 2019 Edition as amended 2022). Applications are submitted at the Development Center (510 E. Florence Blvd.).

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new single-family and two-family dwelling construction within Casa Grande city limits
  • Plans must comply with the 2018 IRC and City of Casa Grande amendments, including the Quick Codes Design Criteria (115 mph ultimate wind speed, Exposure C; Seismic Design Category B; 34°F winter design temperature; heavy termite potential requiring a certificate of soil treatment; 0-inch frost line depth)
  • Structural design criteria for buildings under the IBC must be performed in accordance with IBC Chapter 16, ASCE 7-16, and a project-specific geotechnical investigation (design criteria must be site-specific)
  • Owner may act as their own contractor via a signed owner-builder affidavit, or must use Arizona-licensed contractors Owner-builderContractor
  • Building Permit Application submitted to the Development Center; review of the project does not commence until the plan review fee has been paid in full
  • A City business license is required to conduct business at the permitted location

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Residential Minimum Fee ($1-$1,000 valuation)City of Casa Grande FY 2025-2026 Consolidated Fee Schedule (effective 7/1/2025), Building Permit Fees, Residential and Commercial Construction table
$60.00
Building Permit Fee — $1,001-$10,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$100.00 for first $1,000, plus $10.00 for each additional $1,000 or fraction thereof to $10,000
Building Permit Fee — $10,001-$50,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$240.00 for first $10,000, plus $9.00 for each additional $1,000 or fraction thereof to $50,000
Building Permit Fee — $50,001-$200,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$600.00 for first $50,000, plus $8.00 for each additional $1,000 or fraction thereof to $200,000
Building Permit Fee — $200,001-$1,000,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$1,800.00 for first $200,000, plus $7.00 for each additional $1,000 or fraction thereof to $1,000,000
Building Permit Fee — $1,000,001-$10,000,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$7,400.00 for first $1,000,000, plus $6.00 for each additional $1,000 or fraction thereof to $10,000,000
Building Permit Fee — over $10,000,000 valuationCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule; Maximum Building Permit Fee is capped at $150,000.00 regardless of valuation
$61,400.00 for first $10,000,000, plus $5.00 for each additional $1,000 on the total project valuation
Residential Standard Plan ReviewCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule, Basic Plan Review Services
65% of the construction value per the ICC valuation table or a signed construction contract
Occupancy PermitCity of Casa Grande FY 2025-2026 Consolidated Fee Schedule
$100.00

Review timeline

Plan reviewCasa Grande’s published plan-review target
2–44 business days

How long did your Residential Building Permit (New Construction) permit actually take in Casa Grande?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing, connections, egress, per 2018 IRC and City of Casa Grande design criteria

  3. 3

    Building Final

    For production builders, requires accompanying Planning Final and Development Center Engineering Final inspections before a Certificate of Occupancy is issued

See the full Casa Grande inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's A.R.S. § 9-835 'Over-All Review Timeframes for Building Permits' chart: Single- or Two-Family Residential (IRC-designed) New Construction and Standard Plan carry a 2-business-day Administrative Completeness Review, 20 business days for Review of Initial Submittal, and 20 business days for Review of Resubmittal and Staff Decision — an Over-All Timeframe of 44 business days (2+20+20, with rounding per the source chart).
  • Inspections are scheduled online via the WebPermits portal (rogue.casagrandeaz.gov/WebPermits); same-day inspections are not available unless requested by 11:59 p.m. the prior business day, and inspectors run routes between 6 a.m. and 3:30 p.m.
  • Owner-builders may self-contract by signing an affidavit on the Building Permit Application; a City business license is still required to conduct business at the permitted address. Owner-builder

Frequently asked questions

Casa Grande requires a residential building permit (new construction) for: Building permit required for new single-family and two-family dwelling construction within Casa Grande city limits; Plans must comply with the 2018 IRC and City of Casa Grande amendments, including the Quick Codes Design Criteria (115 mph ultimate wind speed, Exposure C; Seismic Design Category B; 34°F winter design temperature; heavy termite potential requiring a certificate of soil treatment; 0-inch frost line depth); Structural design criteria for buildings under the IBC must be performed in accordance with IBC Chapter 16, ASCE 7-16, and a project-specific geotechnical investigation (design criteria must be site-specific); Owner may act as their own contractor via a signed owner-builder affidavit, or must use Arizona-licensed contractors; Building Permit Application submitted to the Development Center; review of the project does not commence until the plan review fee has been paid in full; A City business license is required to conduct business at the permitted location. If your project isn't listed, confirm with City of Casa Grande Planning & Development Department — Development Center (Building Division) at 520-421-8630 before starting work.

In Casa Grande, the published Building Permit Fee — Residential Minimum Fee ($1-$1,000 valuation) is: $60.00. Additional published fees: Building Permit Fee — $1,001-$10,000 valuation — $100.00 for first $1,000, plus $10.00 for each additional $1,000 or fraction thereof to $10,000; Building Permit Fee — $10,001-$50,000 valuation — $240.00 for first $10,000, plus $9.00 for each additional $1,000 or fraction thereof to $50,000; Building Permit Fee — $50,001-$200,000 valuation — $600.00 for first $50,000, plus $8.00 for each additional $1,000 or fraction thereof to $200,000; Building Permit Fee — $200,001-$1,000,000 valuation — $1,800.00 for first $200,000, plus $7.00 for each additional $1,000 or fraction thereof to $1,000,000; Building Permit Fee — $1,000,001-$10,000,000 valuation — $7,400.00 for first $1,000,000, plus $6.00 for each additional $1,000 or fraction thereof to $10,000,000; Building Permit Fee — over $10,000,000 valuation — $61,400.00 for first $10,000,000, plus $5.00 for each additional $1,000 on the total project valuation; Residential Standard Plan Review — 65% of the construction value per the ICC valuation table or a signed construction contract; Occupancy Permit — $100.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City's A.R.S. § 9-835 Over-All Review Timeframes for Building Permits chart, Single- or Two-Family Residential (IRC-designed) New Construction and Standard Plan review carries a 2-business-day Administrative Completeness Review, plus 20 business days each for Review of Initial Submittal and Review of Resubmittal/Staff Decision, for an Over-All Timeframe of 44 business days maximum.

You'll need: Building Permit Application; Site/Plot Plan; Construction Drawings and Structural Calculations. Depending on your project, Casa Grande may also ask for: Quick Codes Design Criteria Reference. See the required-documents checklist on this page for details on each.

Casa Grande requires 3 inspection(s) for a residential building permit (new construction), in order: Foundation/Footing, Framing, Building Final. Schedule each through City of Casa Grande Planning & Development Department — Development Center (Building Division) (520-421-8630).

Apply through City of Casa Grande Planning & Development Department — Development Center (Building Division) at 510 E. Florence Boulevard, Casa Grande, AZ 85122. Phone: 520-421-8630, email: cgplanning@casagrandeaz.gov. Office hours: Monday - Friday, 7:30 a.m. - 5 p.m. The Development Center is a 'one-stop shop' for building, engineering, fire, and planning plan review/permits/inspections. Building inspections are scheduled online through the WebPermits portal (rogue.casagrandeaz.gov/WebPermits); the City does not offer same-day inspections unless the request is received by 11:59 p.m. the prior business day, and inspectors run routes between 6 a.m. and 3:30 p.m.. Official information: https://casagrandeaz.gov/231/Building.

Casa Grande, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Casa Grande runs its own Planning & Development Department / Development Center and independently adopts and administers its own construction codes under Title 15 (Buildings and Construction) of the Casa Grande Code of Ordinances; it does not defer permitting to Pinal County. Source: City of Casa Grande Building page (casagrandeaz.gov/231/Building) and Casa Grande Code of Ordinances Title 15.; 2018 International Building Code (IBC), adopted by reference with City of Casa Grande amendments (Casa Grande Code of Ordinances § 15.08.010), made a public record by Resolution No. 5170. Source: City of Casa Grande Quick Codes Design Criteria Handout (Building Department, rev. 11/8/2024) and Casa Grande Code of Ordinances § 15.08.010, International Building Code.; 2018 International Residential Code (IRC), adopted by reference with City of Casa Grande amendments under Title 15. Climatic and geographic design criteria (IRC Table R301.2(1)) are published separately by the Building Department. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Mechanical Code (IMC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Plumbing Code (IPC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Fuel Gas Code (IFGC), adopted by reference with City of Casa Grande amendments under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Fire Code (IFC), adopted by reference as the City's uniform fire code under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Energy Conservation Code (IECC) governs residential and commercial energy-efficiency requirements. Residential energy efficiency design minimums published by the Building Department include: new/replacement HVAC sized per ACCA Manual J & S (gas furnaces/boilers 80% AFUE minimum; air conditioners and heat pumps 14 SEER minimum); duct insulation per ACCA Manual D (R-8 within attics/exterior, R-6 within other portions); common insulation values of R-13 walls, R-38 ceilings, U-0.40 windows, R-0 crawlspace/slab-on-grade, R-3 water/refrigerant lines. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Property Maintenance Code (IPMC), adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2017 National Electrical Code (NEC/NFPA 70), adopted by reference with City of Casa Grande amendments (note: electrical code cycle is one edition behind the 2018 ICC set). Arc-fault and tamper-resistant outlet protection is required at most locations per the 2017 NEC. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; NFPA 99 Standards for Health Care Facilities, adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2009 ICC A117.1 Accessible and Usable Buildings and Facilities, adopted by reference under Title 15. Source: City of Casa Grande Quick Codes Design Criteria Handout (rev. 11/8/2024).; 2019 City of Casa Grande Building and Technical Administrative Code (CG-BTAC), made a public record by Resolution No. 5170, with a 2022 Amendment made a public record by Resolution No. 5397. This locally-authored administrative code governs permit administration, fees cross-references, and technical amendments layered on top of the adopted ICC model codes. Source: City of Casa Grande Building and Technical Administrative Code, 2019 Edition (casagrandeaz.gov/DocumentCenter, Resolution 5170) and Casa Grande Code of Ordinances § 15.04.010.. Local amendments apply — see the Casa Grande overview page for the full list.

The 2018 IRC (and 2018 IBC for non-residential portions), as adopted and amended by the City of Casa Grande under Title 15 of the Code of Ordinances, plus the City's Building and Technical Administrative Code (2019 Edition, 2022 Amendment).

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casa Grande building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.