Residential Building Permit (New Construction — Single Family Dwelling) in Bullhead City, Arizona

Required for new single-family dwelling construction in Bullhead City. Reviewed against the 2018 IRC as adopted by the City (effective 07/01/2024) plus City-specific Climatic and Geographic Design Criteria. Applications are submitted in person/by mail to the Building Division at City Hall, 2355 Trane Road.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new single-family dwelling construction within Bullhead City limits
  • Plans must comply with the 2018 IRC and City design criteria: 115 mph ultimate design wind speed (90 mph basic, Exposure C), Seismic Design Category B, 39°F winter design temperature, moderate-to-heavy termite potential, 0 ground snow load, 2 in/hr 100-year 1-hour rainfall
  • Construction documents prepared per the City's Single Family Dwelling Handout submittal checklist
  • Owner-Builder applicants must complete a separate 'Declaration of Intent' form; otherwise a licensed Arizona contractor with a valid AZ Contractors License Number, AZ Transaction Privilege Number, and City of Bullhead City Business License Number must be listed on the Permit Application Owner-builderContractor
  • Permit Application Packet submitted in person or by mail to the Building Division at City Hall, 2355 Trane Road, Bullhead City, AZ 86442
  • Subject to the City's A.R.S. § 9-835 review timeframe: 15 working days Administrative Completeness Review, then 45 working days Substantive Review (60 working days combined)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Valuation Fee (Table A3.40.021.02)City of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.021.02, based on project valuation computed under the Building Valuation Rates of Section A3.40.021.01 (Group R-3, One- and Two-Family, per sq ft rates by construction type)
$21.47 ($1-$500); $21.47 + $2.87 per $100 to $2,000; $64.52 + $12.89 per $1,000 to $25,000; $360.99 + $9.30 per $1,000 to $50,000; $593.49 + $6.42 per $1,000 to $100,000; $914.49 + $4.99 per $1,000 to $500,000; $2,910.49 + $4.30 per $1,000 to $1,000,000; $5,060.49 + $2.86 per $1,000 above $1,000,000
Plan Review Fee, Single-Family ResidentialCity of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.021.04; Standard Plans (repeat/tract plan submittal) are billed 75% for the first submittal and 50% for each additional site-specific submittal instead
65% of the calculated Building Permit Fee
Equipment Rate, Residential Air Conditioning (added to construction valuation)City of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.021.01, Equipment Rates
$2.68 per square foot
Water Resources Fee (Bullhead City Contract Area), single family dwellingCity of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.052.02 (Mohave Water Conservation District Contract Area rate is $721.00 per unit instead, depending on service area)
$405.00 per dwelling unit
Sewer Residential Capacity ChargeCity of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.051.01
$4,304 per dwelling unit, one time

Review timeline

Plan reviewBullhead City’s published plan-review target
45–60 business days

How long did your Residential Building Permit (New Construction — Single Family Dwelling) permit actually take in Bullhead City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing, connections, egress, per 2018 IRC and City Design Criteria

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Wiring, piping, and ductwork before wall closure

  4. 4

    Final

    All work complete per approved plans; utility connections, life-safety systems, and final grading verified

See the full Bullhead City inspection guide — scheduling & re-inspection fees →

Tips

  • The A.R.S. § 9-835 combined review timeframe is 60 working days: 15 working days for Administrative Completeness Review, then 45 working days for Substantive Review. Both clocks are suspended (not counted) while corrections are pending from the applicant.
  • Per A.R.S. § 9-470.01(A)(1)&(2), if the City cannot complete review or respond within 15 business days, the applicant may engage a City-approved third-party plan reviewer at their own additional cost, but only if the City has already approved construction documents/activities for that subdivision or lot.
  • Bullhead City's Building Valuation Rates (Section A3.40.021.01) are explicitly dated to the 'January-February 2008 Building Safety Journal' methodology — this is the City's own long-standing valuation table, not a pass-through of a current ICC valuation figure.
  • Owner-builders must complete a separate 'Declaration of Intent' form; the general Permit Application itself contains the statutory A.R.S. § 9-834 (prohibited licensing acts) and § 9-495 (employee communication) disclosures printed directly on the form. Owner-builder

Frequently asked questions

Bullhead City requires a residential building permit (new construction — single family dwelling) for: Building permit required for new single-family dwelling construction within Bullhead City limits; Plans must comply with the 2018 IRC and City design criteria: 115 mph ultimate design wind speed (90 mph basic, Exposure C), Seismic Design Category B, 39°F winter design temperature, moderate-to-heavy termite potential, 0 ground snow load, 2 in/hr 100-year 1-hour rainfall; Construction documents prepared per the City's Single Family Dwelling Handout submittal checklist; Owner-Builder applicants must complete a separate 'Declaration of Intent' form; otherwise a licensed Arizona contractor with a valid AZ Contractors License Number, AZ Transaction Privilege Number, and City of Bullhead City Business License Number must be listed on the Permit Application; Permit Application Packet submitted in person or by mail to the Building Division at City Hall, 2355 Trane Road, Bullhead City, AZ 86442; Subject to the City's A.R.S. § 9-835 review timeframe: 15 working days Administrative Completeness Review, then 45 working days Substantive Review (60 working days combined). If your project isn't listed, confirm with City of Bullhead City Development Services Department — Building Division at 928-763-0124 before starting work.

In Bullhead City, the published Building Permit Valuation Fee (Table A3.40.021.02) is: $21.47 ($1-$500); $21.47 + $2.87 per $100 to $2,000; $64.52 + $12.89 per $1,000 to $25,000; $360.99 + $9.30 per $1,000 to $50,000; $593.49 + $6.42 per $1,000 to $100,000; $914.49 + $4.99 per $1,000 to $500,000; $2,910.49 + $4.30 per $1,000 to $1,000,000; $5,060.49 + $2.86 per $1,000 above $1,000,000. Additional published fees: Plan Review Fee, Single-Family Residential — 65% of the calculated Building Permit Fee; Equipment Rate, Residential Air Conditioning (added to construction valuation) — $2.68 per square foot; Water Resources Fee (Bullhead City Contract Area), single family dwelling — $405.00 per dwelling unit; Sewer Residential Capacity Charge — $4,304 per dwelling unit, one time. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City's A.R.S. § 9-835 'Building and Zoning Permits' timeline guide (revised March 2026), the combined review timeframe is 60 working days: up to 15 working days for Administrative Completeness Review, then up to 45 working days for Substantive Review. The clock is suspended while the applicant is completing corrections.

You'll need: Permit Application (rev. 09/2022); Single Family Dwelling Handout; Site/Plot Plan; Construction Drawings. Depending on your project, Bullhead City may also ask for: Declaration of Intent for Owner-Builders. See the required-documents checklist on this page for details on each.

Bullhead City requires 4 inspection(s) for a residential building permit (new construction — single family dwelling), in order: Foundation/Footing, Framing, Rough Electrical/Plumbing/Mechanical, Final. Schedule each through City of Bullhead City Development Services Department — Building Division (928-763-0124).

Apply through City of Bullhead City Development Services Department — Building Division at 2355 Trane Road, Bullhead City, AZ 86442. Phone: 928-763-0124, email: schooniyom@bullheadcityaz.gov. Office hours: City Hall, 2355 Trane Road, Bullhead City, AZ 86442. Building Division main line 928-763-0124 (fax 928-763-0131); Inspection Requests line 928-763-0172. Development Services Director/Building Official: Saritti "Billy" Chooniyom, CBO (schooniyom@bullheadcityaz.gov). Sr. Plan Review/Administrative Manager: Wendy Lewis (wlewis@bullheadcityaz.gov). Manufactured-home permitting contact: dking@bullheadcityaz.gov. Permit Application Packets are submitted in person or by mail to the Building Division/Planning & Zoning Division at City Hall. Source: City of Bullhead City Building and Renovating page and 2025 AZBO Directory.. Official information: https://www.bullheadcityaz.gov/business-development/building-and-renovating/.

Bullhead City, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9, §§ 9-831 through 9-840). The City of Bullhead City runs its own Development Services Department / Building Division and independently adopts and administers its own construction codes; it does not defer permitting to Mohave County. Source: City of Bullhead City 'Adopted Building Codes' notice (effective 07/01/2026) and 'Work Exempt From Permits' handout (effective 07/01/2024).; 2018 International Building Code (IBC), as published by the International Code Council, adopted with local amendments (Bullhead City Municipal Code (BHCMC) Chapter 15.12). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Residential Code (IRC), for one- and two-family dwellings and associated accessory structures, adopted with local amendments (BHCMC Chapter 15.14). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026; City of Bullhead City 2018 IRC Design Criteria sheet, effective 07/01/2024.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with local amendments (BHCMC Chapter 15.20) — one edition behind the 2018 ICC code set. Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026. The City Council approved adoption of the 2018-cycle ICC codes and 2017 NEC on 04/16/2024, effective for applications beginning 07/01/2024. Source: Mohave Daily News, 'Bullhead City moves toward updating building codes.'; 2018 International Mechanical Code (IMC), adopted with local amendments (BHCMC Chapter 15.28). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Plumbing Code (IPC), adopted with local amendments (BHCMC Chapter 15.32). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Fuel Gas Code (IFGC), adopted with local amendments (BHCMC Chapter 15.34). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Energy Conservation Code (IECC), adopted with local amendments (BHCMC Chapter 15.22). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Existing Building Code (IEBC), adopted with local amendments (BHCMC Chapter 15.26). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with local amendments (BHCMC Chapter 15.30). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2018 International Fire Code (IFC) is referenced by the City for demolition/fire-safety provisions, but fire code administration in Bullhead City is handled by the Arizona Department of Fire, Building and Life Safety, which has separately adopted the 2024 International Fire Code; contact the Bullhead City Fire Department at (928) 758-3971 / planreview@bullheadfire.org for fire plan review. Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; 2010 ADA Standards for Accessible Design (ADAAG Manual, US Access Board) adopted, no local BHCMC chapter assignment (NA). Source: City of Bullhead City Adopted Building Codes notice, effective 07/01/2026.; Manufactured homes, factory-built buildings, and park model trailers are separately regulated through the City's intergovernmental agreement with the Arizona Department of Housing (ADOH) for installation, reinspection, additional inspections and extensions (fees per the ADOH Fee Schedule, A.R.S. Title 41, Chapter 37, Article 3); the City separately issues Zoning Clearance permits for placement/siting. Source: City of Bullhead City Comprehensive Fee Schedule FY2025-2026, Section A3.40.022.07.. Local amendments apply — see the Bullhead City overview page for the full list.

The 2018 IRC as adopted by the City (effective 07/01/2024, BHCMC Chapter 15.14), plus City-specific Climatic and Geographic Design Criteria: 115 mph ultimate wind speed (Exposure C), Seismic Design Category B, 39°F winter design temperature, and moderate-to-heavy termite potential.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bullhead City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.