Residential Building Permit (New Single-Family Home) — Camp Verde, Arizona · Requirements sheet
Verified 2026-08-16 · Source: https://www.campverde.az.gov/departments/community_development/permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Single-Family Home) in Camp Verde, Arizona
Required for new one- and two-family dwelling construction in the Town of Camp Verde. Reviewed against the 2024 IRC as adopted and amended by the Town via Ordinance 2026-A512 (effective February 26, 2026). Applications are submitted through the GovWell One-Stop Permitting Portal.
Verified 2026-08-16 · Source
When you need this permit
- Building permit required for new single-family and two-family dwelling construction within Camp Verde town limits, following a required Residential Zoning Clearance ($190, includes manufactured/factory-built/modular homes)
- Plans must comply with the 2024 IRC and Town of Camp Verde amendments, including the reduced 100 mph wind-speed design criteria (Risk Category I) adopted under Ordinance 2026-A512
- Valuation for new single/multi-family residences (excluding mobile/manufactured homes) is the applicant's valuation or the ICC Building Valuation Data (BVD) Table figure, whichever is greater
- A deposit equal to the Building Plan Review Fee is due at submittal ($250 of the deposit is non-refundable if the application is cancelled/withdrawn before plan review begins)
- Submittal via the GovWell One-Stop Online Permitting Portal (app.govwelltech.com/camp-verde)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): all eight Total Valuation tiers compared individually against the FY2026-27 workbook (Community Development section,… Show full citationHide
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): all eight Total Valuation tiers compared individually against the FY2026-27 workbook (Community Development section, 'BUILDING PERMIT FEES' → 'Total Valuation', rows 312-319) and found identical, base amounts and per-increment rates alike. No FY2026-27 change is recorded against any of the eight rows.UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): 'Zoning Clearance for Building Permits → Residential single family dwelling (includes Manufactured and… Show full citationHide
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): 'Zoning Clearance for Building Permits → Residential single family dwelling (includes Manufactured and Factory-Built/Modular Buildings) — $190' (row 294), no FY2026-27 change recorded. Prerequisite to the building permit.UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): 'New Single/Multi-Family Residence — Equal to Building Plan Review Fee ($250 is non refundable if the application is… Show full citationHide
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): 'New Single/Multi-Family Residence — Equal to Building Plan Review Fee ($250 is non refundable if the application is cancelled/withdrawn before plan review)' (Deposits for Building Permit Applications, row 345), no FY2026-27 change recorded. Due at submittal, non-refundable.Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, egress, per 2024 IRC and Town of Camp Verde design criteria
- 3
Rough Electrical/Plumbing/Mechanical
Prior to wall closure
- 4
Final / Certificate of Occupancy
All work complete per approved plans; scheduled 48 hours in advance per the Building Division's published process flow chart
See the full Camp Verde inspection guide — scheduling & re-inspection fees →
Tips
- Per the Town of Camp Verde Community Development Department's published 'Flow Chart – Permit Application Process' (Building Division), a new Single-Family Home plan review is 21-35 business days for the first review, following a 0-5 business-day application-completeness review. This is a verified, governing published figure — not an estimate.
- The permits page separately advertises a general 'Residential: 2-4 weeks' processing window; the Building Division's own detailed flow chart (21-35 business days for single-family homes specifically) is the more granular and authoritative figure and is used here.
- If the first plan review is not approved, additional reviews take 7-30 business days each per the published flow chart, repeating until approved.
- Permit issuance after final plan approval and balance-due payment takes 1-2 business days per the flow chart.
- A Residential Zoning Clearance must be obtained before a building permit will be issued; the Town's general zoning clearance processing estimate is 2 weeks.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Applications & forms
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Camp Verde building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Camp Verde's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Camp Verde yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Camp Verde lands. Privacy.
Other permits in Camp Verde
Residential Building Permit (New Single-Family Home) in other cities
Compare residential building permit (new single-family home) fees across Arizona →
Look up this fee in a different city →