Camp Verde building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Camp Verde, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 473 S. Main Street, Suite 108, Camp Verde, AZ 86322
- Phone
- 928-554-0050
- Office hours
- Monday - Thursday, 7:00 a.m. - 5:00 p.m. (closed Fridays). Applications, plans, and checklists are submitted through the GovWell online One-Stop Permitting Portal (app.govwelltech.com/camp-verde); Chief Building Official is Roxanne Jasman (928-554-0061); Building Inspectors are Josh Presmyk and Jon Rivero (928-554-0050 / 928-554-0065).
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit (New Building / Tenant Improvement)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing and connections per 2024 IBC and Town design criteria
- 3
Rough Electrical/Plumbing/Mechanical/Fire
Prior to wall closure, including Fire Marshal-required rough inspections where applicable
- 4
Final / Certificate of Occupancy
All work complete per approved plans; scheduled 48 hours in advance
Applies to: Residential Building Permit (New Single-Family Home)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, egress, per 2024 IRC and Town of Camp Verde design criteria
- 3
Rough Electrical/Plumbing/Mechanical
Prior to wall closure
- 4
Final / Certificate of Occupancy
All work complete per approved plans; scheduled 48 hours in advance per the Building Division's published process flow chart
Applies to: Manufactured / Modular / Factory-Built Home Installation Permit
- 1
Set / Foundation
Foundation and blocking/pier placement verification
- 2
Tie-Down
Anchoring and tie-down system per OMH/manufacturer standards
- 3
Final
Utility connections and site completion; three inspections total are included in the base OMH fee
Applies to: Residential Addition / Remodel / Accessory Structure Permit
- 1
Foundation/Footing
Required before concrete pour for additions/accessory structures with foundations
- 2
Framing
Structural connections to existing structure
- 3
Final
Completed work verified against approved plans
Applies to: Change of Use / Certificate of Occupancy (processed via Commercial Tenant Improvement Permit)
- 1
Rough Electrical/Plumbing/Mechanical
Where the change-of-use scope involves trade work, prior to wall closure
- 2
Final / Certificate of Occupancy
Terminal step of the building permit process per the Building Division flow chart ('Certificate of Occupancy or Completion'); no separate fee for a standard final CO
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
Circuit wiring before covering, where applicable
- 2
Final
EVSE connection operational and verified per adopted code
- 1
Rough-In
Fire alarm wiring/devices or sprinkler piping before covering, per CCFMD requirements
- 2
Final / CCFMD Acceptance Test
System tested and verified operational; the base CCFMD fee for most system categories includes up to 2 inspections
Applies to: Residential Over-the-Counter (OTC) Permit — Electrical / Mechanical / Plumbing / Building
- 1
Rough-In
Where applicable to the scope (electrical, plumbing, or mechanical rough-in) before covering
- 2
Final
Devices/fixtures installed and operational, verified per adopted code; up to 2 inspections included in the Combo OTC fee
Applies to: Residential Solar Photovoltaic (PV) / BESS / Wind Turbine / Generator Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified
Final inspection only: Demolition Permit, Sign Permit (Commercial/Business Signage)
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Camp Verde building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Camp Verde building permits
Get alerts for Camp Verde
We'll email you when Camp Verde's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.