Residential Solar Photovoltaic (PV) / BESS / Wind Turbine / Generator Permit — Camp Verde, Arizona · Requirements sheet
Verified 2026-08-16 · Source: https://www.campverde.az.gov/departments/community_development/permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Solar Photovoltaic (PV) / BESS / Wind Turbine / Generator Permit in Camp Verde, Arizona
Required for installation of rooftop or ground-mounted residential solar photovoltaic systems, Battery Energy Storage Systems (BESS), wind turbines, and generators in the Town of Camp Verde. Governed by the 2018 IFC Solar Photovoltaic Requirements referenced by the Town and the 2023 NEC as adopted (Ordinance 2026-A512).
Verified 2026-08-16 · Source
When you need this permit
- Governed by the 2023 NEC and the Town's referenced 2018 IFC Solar Photovoltaic Requirements
- Equipment cut sheets with UL Listing information and Manufacturer's Installation Instructions must be included with construction documents
- Systems up to 15kWh AC/DC (residential or commercial) are billed at a flat fee plus Zoning & Fire Marshal plan review fees
- Systems over 15kWh AC/DC are billed at 20% of applicant valuation or $2.75/watt (whichever is greater) plus Building, Zoning & Fire Marshal plan review fees
- Apply via the GovWell One-Stop Permitting Portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): the Residential and Commercial rows are separate lines carrying identical text — '$206.00 Flat Fee for all Systems up… Show full citationHide
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): the Residential and Commercial rows are separate lines carrying identical text — '$206.00 Flat Fee for all Systems up to 15kwh AC/DC Plus Zoning & Fire Marshal Plan Review Fees.' (rows 439-440). No FY2026-27 change recorded against either. The referenced Fire Marshal plan review fee is set by the fire district, not the Town: the current Copper Canyon Fire & Medical District schedule lists Residential Photovoltaic $200.00, Residential Photovoltaic with BESS $350.00, Commercial Photovoltaic $300.00 per system and Commercial Photovoltaic with BESS $450.00 per system (each including plan review and 1 inspection), read from a render of page 2 of that schedule on 2026-08-16.UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): Residential and Commercial 'Over 15kwh AC/DC' rows both read 'Systems Over 15kwh will be Calculated Using 20% of… Show full citationHide
UNCHANGED in the FY2026-27 schedule (Resolution 2026-1217, effective 7/1/2026): Residential and Commercial 'Over 15kwh AC/DC' rows both read 'Systems Over 15kwh will be Calculated Using 20% of Applicant Valuation or $2.75/watt, Whichever is Greater, Plus Building, Zoning & Fire Marshal Plan Review Fees.' (rows 441-442). No FY2026-27 change recorded against either. A utility-scale installation is separately priced by the fire district: the current CCFMD schedule lists 'Solar Farm (plan review & 2 inspections) — Based on project cost.'Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified
See the full Camp Verde inspection guide — scheduling & re-inspection fees →
Tips
- Per the Town's published Building Division process flow chart, Solar/BESS review is 7-21 business days for the first review — noted as its own distinct category, faster than a full single-family home review but slower than the OTC track.
- Note the permits page cites the '2018 IFC Solar Photovoltaic Requirements' specifically (not the 2024 IFC edition otherwise adopted town-wide) — confirm with Development Services (928-554-0050) whether this is a scrivener's holdover from the pre-2026 code set or an intentional retained reference.
- The permits page mentions residential photovoltaic installations must include all equipment cut sheets with UL Listing information and Manufacturer's Installation Instructions with construction documents — incomplete cut-sheet submittals are a common cause of first-review rejection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Applications & forms
Online permit portal
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Camp Verde building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Camp Verde's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Camp Verde yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Camp Verde lands. Privacy.
Other permits in Camp Verde
Residential Solar Photovoltaic (PV) / BESS / Wind Turbine / Generator Permit in other cities
Look up this fee in a different city →
Now live
Build your Camp Verde project checklist
Describe your project once and get every permit, document, and fee it triggers in Camp Verde — in one checklist. Free, for any city and any number of projects.
Get started →